In this action for the foreclosure of certain mechanic’s liens and other relief, the defendant owners of the real property move for partial summary judgment dismissing the first cause of action on the grounds: (1) that plaintiff was acting as agent for defendants when it performed work on the realty and therefore is not a valid lienor; and (2) that the filing of a lien is an unconstitutional taking of property without due process of law.
The court will deal first with the constitutional challenge. Generally, legislative enactments are accorded a strong presumption of constitutionality. (See Wasmuth v Allen, 14 NY2d
Movants contend that the creation of an interest in real property by the filing of a mechanic’s lien without any prior judicial determination is an unconstitutional deprivation of due process. The United States Supreme Court has held in Sniadach v Family Finance Corp. (
For a prejudgment seizure to be valid there must be a factual demonstration by the party seeking the seizure of the nature, extent and validity of his claim to a judicial authority empowered to grant or deny the seizure and an opportunity for an expeditious adversary adjudication of the claim either prior to or shortly after the seizure. (Mitchell v W. T. Grant Co.,
The central question then is whether the creation of a mechanic’s lien constitutes such a seizure of property as to require the compliance with the standards of due process set
It is also noted that the court, in both Fuentes and Mitchell, considered instances of parties with existing security interests in the property. The constitutional issues did not involve the creation of those interests but the prejudgment seizure of the property in enforcement thereof. Here, movants seek to apply those procedural requirements to the creation of the interest. The enforcement of that interest can only be had after a full plenary trial which far exceeds the requirements set forth in Fuentes and Mitchell.
Thus, it clearly appears that movants have failed to meet
The court must now consider movants’ contention that plaintiff was their agent and not a "contractor” and accordingly not a party entitled to file a lien. This contention is based on terms of the contract pursuant to which plaintiff did not have independent control of the construction. In particular, movants refer to the fact that plaintiff’s responsibility relative to subcontractors and materialmen was to procure bids but the contracts were entered into by the owner. Movants also refer to the provision which deprived the plaintiff of authority to undertake any expense over $2,500 without the owner’s approval.
The Lien Law provides that a "contractor” is "a person who enters into a contract with the owner of real property for the improvement thereof’ (Lien Law, § 2, subd 9). While read broadly, that definition would include anyone who makes a contract with the owner, the term for purposes of the Lien Law must be restricted to "one who would be so characterized in the common speech of man” (McNulty Bros. v Offerman,
Even if movants’ contention that plaintiff is not a "contractor” be true, it does not follow that the liens are invalid. In addition to "contractors”, anyone who provides services in the improvement of real property at the behest of the owner may be entitled to a lien. (Lien Law, § 2, subd 11; § 3.) The question then is whether the work done by plaintiff is a service in improvement of the real property within the meaning of the Lien Law. The basis of the claimed liens is the general supervision of the project. Such was clearly one of plaintiff’s duties as called for in the contract with movants. Supervision
However, procurement of bids and negotiation of contracts for the services of subcontractors, also called for in the contract, cannot provide the basis of a lien separate from the work of a "contractor” or architect. (Goldberger-Raabin, Inc. v 74 Second Ave. Corp., supra.) Since the sole basis of plaintiff’s liens is supervision, there are issues of fact present as to whether the entire sum claimed due is for that work only or, in part, for other nonlienable work.
Movants’ reliance on McNulty Bros. v Offerman (supra) and Dorn v Johnson Corp. (
The final point at issue is whether plaintiff participated as a joint venturer with movants in the supervision of certain work done for movants’ tenants. In some of the notices of lien claim is made for such work. Essential to the creation of a joint venture is the agreement not only to share profits but also bear the burden of making good any losses.. (Matter of Steinbeck v Gerosa,
Accordingly, the motion for partial summary judgment is denied.
