Cargill, Incorporated v. Frank Weston, Individually and D/B/A Weston Elevator Company, a Sole ProprietorshipCargill, Incorporated v. Frank Weston, Individually and D/B/A Weston Elevator Company, a Sole Proprietorship
Plаintiff, Cargill, Inc., appeals the trial court’s grant of judgment in favor of defendant, Frank Weston, on its claim for damages for breach of a contract to deliver soybeans. Weston, an Arkansas farmer who owns 156 acres and rents about 800 acres for his farming operation, began in 1972 to buy, sell and store grain in bins on his farm under the name of Weston Elevator Company. The parties contracted September 5, 1972, for the delivery of 20,000 bushels of # 1 yellow soybeans to be delivered in October and November, 1972, at a contract price of $3.35 per bushel. The contract was accepted “Weston Elevator by Frank Weston.”
Due to unprecedented weather conditions in the South-Central United States
Many of the sellers under contract with Cargill were experiencing similar difficulties fulfilling their contracts during this same period of time. It is undisputed that during this same period the price of soybeans was beginning its risе to record heights. Instead of cancel-ling all these contracts when the time for performance passed and covering in the market, Cargill mailed extension agreements to the sellers in which it agreed to extend the delivery datеs for an additional 30 days. Weston never ex-cuted any of these extension agreements mailed by Cargill.
The first personal contact between Weston and Cargill was sometime in January, 1973. At that time it was Car-gill’s understanding that Weston wished additional time to рerform, though Weston denies ever requesting any extension. His position was, however, that all beans harvested by him from his own and rented lands would be delivered to Cargill at the contract price. A personal visit was made to Weston January 31, 1973, by Allen Housh, Memphis Manager for Cargill, as evidenced by his letter of February 1, 1973, to Weston. 1
Deliveries of soybeans were made by Weston in December, January, March and April, for which he was paid the contract price. There remained 10,585 bushels of soybeans undelivered on the contract on May 31, 1973, the date Car-gill cancelled the contract pursuant to its receipt of a letter from Weston. 2 The market price at that time was $10.48 per bushel and Cargill sought damages of $75,471.05 for Weston’s breach.
The case was tried to a jury and submitted on special interrogatories.
3
Ac
The parties have stated the question on appeal as being whether judgment notwithstanding the verdict was properly granted. While the trial court’s action had the same effect as a judgment n. o. v., it is clear that judgment n. o. v. was not granted nor could it have been grаnted on the present record. The requisites for the grant of judgment n. o. v. pursuant to
It is therefore clear that the judgment entered on behalf of Weston cannot stand.
See Compton v. United States,
We believe the proper disposition is to order a new trial of this action. The trial court clearly indicated its belief that the jury’s verdict was erroneous and that Cargill’s actions in attempting to extend the contract were unconscionable. Pursuant to
Furthermоre, this court has been hampered by the appellant’s failure to prepare an appendix in compliance with
The judgment is reversed and the cause remanded to the District Court with directions to grant a new trial.
Notes
. That letter read in pertinent part:
Thank you for visiting with me during my visit in Corning yesterdаy. This letter will confirm our agreement regarding the open balance on our soybean contract PR 49995, dated September 5, 1972.
******
2. Weston Elevator Company will deliver the balance of the beans that remain open during February or March аs weather permits.
. Weston’s May 29, 1973, letter to Cargill read:
Reference is made to your letter dated May 17, 1973 which I received on May 21, 1973 by certified mail.
On contract # PR 49995, you have seemed to over looked or forgotten to fulfill your obligations to cancel out contract # PR 49995, which Mr. Allen Housh and I discussed over the phone April 12, 1973, that I would deliver approximately 3200 bu. Soybeans at the time after these were delivered there would be no more Soybeans available, do to heavy losses and bad flooding in this area, to cancel out balance of contract # PR 49995 at market price, which should be on April 19, 1973.
. Those interrogatories and the jury’s answers were as follows:
1. It is undisputed that Cargill attempted several times to obtain an agreement from Mr. Weston to extend the delivery date under the original September 5, 1972 contract. Did Mr. Weston ever, at any time from December 1, 1972 until May 31, 1973, agree to any such extension?
ANSWER: Yes.
If your answer is “No” do not answer the remaining parts.
(a) What was the date or approximate date of such extension agreement?
ANSWER: January, 1973.
(b) What was the latest extended date for delivery agreed upon?
ANSWER: April 19, 1973.
2. As of November 30, 1973 — the last date for performance under the September 5, 1972 agreement — did the representatives of Cargill who dealt with Mr. Weston have a definite opinion and expectation that the market price of soybeans in the following months would significantly rise; would remain the same; would fall, or did they have no opinion on this matter?
ANSWER: Would rise significantly.
3. (a) It is undisputed that Mr. Weston delivered only 1,537 bushels of Soybeans to Cargill prior to the end of November 1972. However, it is also undisputed that subsequent to December 1, 1972 he delivered at various dates an additional 7,878 bushels of soybeans to Cargill, for which he was paid by Cargill the price of $3.35 per bushel, although the actual market price of soybeans at the dates of the actual deliveries varied from $4.03 and three-quarters to $6.73 and one-quarter per bushel.
What was the understanding and agreement of the parties, if any, concerning the delivery and receipt of the soybeans after December 1, 1972? Did the parties agree to settle Cargill’s claim against Mr. Weston if Mr. Weston would make every effort to salvage the beans in his crop and deliver all such beans to Cargill at the original contract priсe on the additional understanding that Cargill would have no further claims against Mr. Weston?
ANSWER: No.
4. Did Mr. Weston, when he made the original agreement with Cargill in September 1972, contemplate that he would perform the contract by delivering to Cargill soybeans which he had grown on his own land and upon land rented from others?
ANSWER: No.
. The District Court, prior to entering the verdict for Weston, stated for the record:
It is undisputed and there is absolutely no basis or factor in law for the existence of any extension agreemеnt prior to the defaulting under the original agreement.
It then made the following determinations:
First, I do not believe there is an adequate basis for the finding of 'an extension agreement, even though the jury has found one. I do not believe, additionally, that even though there may have been an agreement as they contemplate that — that is, a meeting of the minds — that there was any consideration which would have supported it.
******
I think the law requires them and required them to cover their loss without some agreement extending the date for performance prior to its expiration. * * *
In other words, in contemplation of the law they should have covered. They would have been out between 6 and $7,000.00. They have subsequently received beans where the difference in the value of those beans between the contract price of $3.35 and what the market prices were on the various dates of delivery exceeded the 6 to $7,000.00.
If a counterclaim had been filed I believe that Mr. Weston would be entitled to recover. He has not filed it and the Court is not going to award any judgment against Car-gill. But it is going to find that he has fully paid the damages suffered by Cargill. * *
I must say also that I have a bad feeling about the case, one that I did not start with at all but one which grew as the tеstimony went on; the feeling being that a company of great stature and power and great knowledge and awareness in this whole field was using its knowledge and power in a way that I cannot view as any other than unconscionable. I think if there wаs a so-called extension agreement it certainly was unconscionable under the circumstances.
.
Motion for Judgment Notwithstanding the Verdict.
Whenever a motion for a directed verdict made at the close of all the evidence is denied or for any reason is nоt granted, the court is deemed to have submitted the action to the jury subject to a later determination of the legal questions raised by the motion. Not later than 10 days after entry of judgment, a party who has moved for a directed verdict may move to have the verdict and any judgment entered thereon set aside and to have judgment entered in accordance with his motion for directed verdict.
.
. Notice was given the parties before oral argument in this case that the aрpendices filed herein failed to comply with