177 Mass. 398 | Mass. | 1901
This is an action to recover for extra work in grading, and laying pipes, and stone work on an estate of the defendants in Dedham. The plaintiff was a sub-contractor under one Whitcomb, who had a contract to build a house and stable, and to grade and prepare the grounds. The plaintiff’s contract with him included all the grading, trench digging, stone work and pipe laying, according to the plans and specifications in the contract betweeen Whitcomb and the defendants. It was in evidence that the land was wild land, and very high — a ledge of mountain and forest — when the plaintiff went to work there.
In the progress of the work certain changes were made, some of which were admitted by the defendants to be departures from the original contract, in order the better to complete the construction according to their general purpose and desire. In regard to most, of the changes the parties are in dispute, the defendants contending that they were either corrections of mistakes of the plaintiff in the work under the contract, or made for his convenience, to save him from greater expense which would have been involved in complying literally with the requirements of the contract; while the plaintiff contends that they were directions for additional work. The defendants, who were husband and wife, were hardly ever on the ground on working days during the progress of the work, but the defendant, William Farnsworth, made three voyages to Europe during the time, and he was represented in the supervision of the work by one Smith, and by Longfellow, the architect. Most of the changes were made as a result of conversation between the plaintiff and Smith, who was on the premises very often to see what was being done. The principal question before us arises on the refusal of the judge to give two instructions requested by the defendants: “ First. There was no evidence to warrant a verdict for the plaintiff except upon the items contained in the auditor’s report. Second. The same request in detail as to each item of the declaration, except as to those items in which the auditor found for the plaintiff.”
The first question is whether there was any evidence to warrant a finding that Smith was authorized to make changes in the work to be done under the specifications, and to bind the
The next question is whether there was evidence that the plaintiff did work outside of his contract under Smith’s direction. The question before us is not what is the weight of the evidence, but whether there was any evidence in favor of the plaintiff on this point. Looking at the printed report of the testimony, we think it probable that the conclusion of the auditor was correct rather than that of the jury. But we think there was evidence on which the jury might find as to each item that the plaintiff did work outside of his contract by direction of the defendants’ representative, and although as to most of this work it seems probable that it was demanded and performed as a part of that required by the contract, we cannot say as matter of law that the judge was bound so to rule, or the jury so to find. It would serve no useful purpose to consider the testimony as to each item in detail. We are of opinion that this question was rightly submitted to the jury.
It was in dispute whether the profile plan of the driveway extending into the street was in existence when the contract was signed, and the question whether the driveway terminated at the line of the street or extended to the centre of it, was properly left to the jury.
It also appeared from an answer of the jury at the same time, that the jury, by an oversight, allowed $44 for a part of item twelve, for which the plaintiff had waived his claim. Inasmuch as no request nor ruling was made in regard to this, the verdict would not be disturbed on account of it if there were no other error; but since the exceptions must be sustained unless the plaintiff remits the amount allowed under item three, this mistake may well be corrected at the same time. The order therefore will be,
Exceptions sustained, unless the plaintiff remits from the verdict $50 and $44, $94 in all, with interest from the date of the writ to the date of the verdict. If he remits this amount within fifteen days after the rescript is sint, the entry will be, Exceptions overruled.