¶ 1. This appeal arises out of an action George and Mary Capoun 1 filed in Dane County Circuit Court seeking to prevent the Depart-, ment of Administration (DOA) from holding a hearing on Aftab Ansari's request that the Department of Natural Resources (DNR) 2 issue a permit for a retention pond he had already constructed on his property. The circuit court granted summary judgment dismissing the Capouns' action. On appeal, the Capouns argue that the DNR did not have subject matter jurisdiction to issue a permit to Ansari for the retention pond because it had already been constructed and the statutes limit the DNR's authority to issue permits to those instances where construction has not yet begun. The Capouns also contend that the granting of this permit denied them due process of law. We conclude that the DNR has subject matter jurisdiction to issue permits *339 relating to waterways, both before and after construction has commenced. We also conclude that the Capouns' claim that they were denied due process is without merit. Accordingly, we affirm the circuit court.
BACKGROUND
¶ 2. The relevant facts are largely undisputed. The Capouns own property that lies adjacent to property owned by Ansari. Sometime during 1995 or 1996, Ansari constructed a retention pond on his property. The Capouns claim that the pond has created an increase in the water flowing onto their property, causing damage to them.
¶ 3. Ansari did not apply for a Wis. Stat. § 30.19 (1997 — 98) 3 permit 4 from the DNR prior to beginning construction of the pond. Ansari did, however, apply for a permit after the pond was constructed. The Capouns, opposing the issuance of the permit, filed objections with the DNR. They also commenced this action seeking a permanent injunction against the DOA and the DNR to prevent them from holding a contested case hearing for the permit Ansari was seeking. However, after the Capouns made their objections, the DOA held a formal contested case hearing to determine whether the DNR should issue a permit for the pond.
¶ 4. It appears that the Capouns had notice of, and also participated in, the hearing, which lasted three days. 5 However, before the hearing examiner *340 issued his decision about whether to issue a permit, the Capouns moved for summary judgment in this case, arguing that the DNR did not have subject matter jurisdiction necessary to issue an after-the-fact permit. They also claimed that they were denied the use of their land without due process of law. Before the circuit court ruled on the Capouns' motion, the DNR issued written findings of fact and conclusions of law, granting Ansari the permit. The Capouns appealed that determination to the circuit court in Kenosha County in a Wis. Stat. ch. 227 proceeding. 6 Therefore, the procedure used by the DNR in its hearing and the merits of its decision to issue a permit are not before this court on appeal. Later, in the case now before us, the circuit court concluded that the DNR had the authority to issue permits after-the-fact and that no due process violation had been demonstrated. Therefore, it granted summary judgment in favor of Ansari, the DNR and the DOA. It is from this decision that the Capouns appeal.
*341 DISCUSSION
Standard of Review.
¶ 5. A grant or denial of summary judgment is an issue of law which we review
de novo,
applying the same methodology as the circuit court.
See Smith v. Dodgeville Mut. Ins. Co.,
¶ 6. Additionally, construction of a statute, or its application to undisputed facts, is a question of law, which we review
de novo. See Ansani v. Cascade Mountain, Inc.,
*342 Authority to Issue After-the-Fact Permits.
¶ 7. The Capouns assert that whether the DNR has the authority to issue a permit after-the-fact is a question of subject matter jurisdiction, requiring a
de novo
review by this court. When we are asked to construe the breadth of power an agency has been delegated by the legislature, we note that, as a creature of the state, an agency has only those powers the state has given it.
See Silver Lake Sanitary Dist. v. DNR,
¶ 8. The DNR and Ansari, without contesting the framing of the issue as one of subject matter jurisdiction,
7
urge us to defer to the DNR's interpretation of the statute, citing
Harnischfeger Corp. v. LIRC,
¶ 9. It is WlS. Stat. § 30.19 which we are asked to construe in this appeal. It provides in relevant part:
(1) Permits REQUIRED. Unless a permit has been granted by the department or authorization has been granted by the legislature, it is unlawful:
(a) To construct, dredge or enlarge any artificial waterway, canal, channel, ditch, lagoon, pond, lake or similar waterway ....
(2) Permits for work or to enlarge waterways. Before any work or connection specified in sub. (1) is undertaken the applicant shall file an application with the department....
¶ 10. The Capouns contend that because Wis. Stat. § 30.19(2) clearly states that a permit must be obtained
before
work is undertaken, the DNR has no subject matter jurisdiction to consider any requests for after-the-fact permits. The Capouns' argument presents a question of statutory construction. Our goal in interpreting a statute is to discern legislative intent and to give meaning to the statute which comports with that intent.
See Rolo v. Goers,
¶ 11. We note that the legislature formed the DNR in 1965 " 'to protect human life and health, fish and aquatic life, scenic and ecological values and domestic, municipal, recreational, industrial, agricultural and other uses of water.'"
See Reuter v. DNR,
¶ 12. The Capouns' argument that the DNR has subject matter jurisdiction only over before-the-fact permits and not after-the-fact permits is based on a very narrow construction of WlS. STAT. § 30.19. It also ignores Wis. Stat. § 30.28, which deals with the same subject matter. However, rules of judicial construction require us to consider statutes pertaining to the same subject matter together. "When multiple statutes address the same subject matter, we properly read the two statutes in pari materia such that both will be
*345
operative."
See Providence Catholic Sch. v. Bristol Sch. Dist. No. 1,
¶ 13. Of particular relevance to this appeal is Wis. Stat. § 30.28(2m)(b) which provides ”[i]f the applicant applies for a permit... after the project is begun or after it is completed, the department shall charge an amount equal to twice the amount of the fee that it would have charged under this section." The Capouns do not dispute that § 30.28(2m)(b) applies to permits such as the one sought by Ansari. However, they contend that it merely sets forth a fee schedule for permit applications. We do not find the Capouns' reasoning persuasive because if the DNR has the authority to issue permits only before construction has begun, there would be no reason for the legislature to direct the DNR to charge a double application fee for those persons who seek a permit after the project either has begun or has been completed. Therefore, the interpretation of Wis. Stat. § 30.19 that the Capouns urge us to adopt would cause the directive of § 30.28(2m)(b) to be meaningless. This is a statutory interpretation we cannot accept.
See Providence Catholic Sch.,
*346
¶ 14. The Capouns also argue that even if the DNK has subject matter jurisdiction to consider an application filed after a project has begun, the agency-exceeded its rule-making authority when it promulgated a rule that conflicted with a statute. While we agree with the Capouns that "[a]n administrative rule that conflicts with an unambiguous statute exceeds the rule-making authority of the administrative agency,"
see Seider v. Musser,
Due Process.
¶ 15. The Capouns also claim that they were denied the use of their property without due process of law. The Wisconsin and United States Constitutions prohibit governmental actions that deprive any person of life, liberty or property without due process of law.
See
U.S. Const, amend. V and XTV; Wis. Const, art. I, § 1." 'In procedural due process claims, the deprivation by state action of a constitutionally protected interest in 'life, liberty, or property' is not in itself unconstitutional; what is unconstitutional is the deprivation of such an interest
without due process of
law.'"
Casteel v.
*347
McCaughtry,
¶ 16. The Capouns cannot establish either due process element. First, the Capouns cannot show that the DNR has deprived them of a property interest by granting an after-the-fact permit to a neighboring property owner. The Capouns do not articulate what property interest it claims the DNR has taken. Rather, they complain that the retention pond built by Ansari is flooding their property. The building of the retention pond was an action taken by a neighboring property owner, not by the DNR. The due process clause addresses only actions taken by the state or an agent thereof. 9
¶ 17. Additionally, even if the Capouns could establish a deprivation of a property interest by the DNR, they cannot show that the process they received was constitutionally inadequate. The supreme court recently explained: " '[D]ue process is satisfied if the statutory procedures provide an opportunity to be heard in court at a meaningful time and in a meaningful manner. Due process is flexible and requires only
*348
such procedural protections as the particular situation demands.'"
Estate of Makos v. Wisconsin Masons Health Care Fund,
CONCLUSION
¶ 18. We conclude that the DNR has subject matter jurisdiction to issue permits relating to waterways, both before and after construction has commenced, and that the Capouns' claim that they were denied due process is without merit. Accordingly, we affirm the circuit court's ruling.
By the Court. — Order affirmed.
Notes
George and Mary Capoun brought this suit in their capacity as trustees of the George and Mary Capoun Revocable Trust. For ease of reference, we refer to the appellants as the Capouns throughout this opinion.
The Capouns sued David H. Schwarz, the division head of the Department of Administration, Division of Hearings and Appeals, and George Meyer, the Secretary of the Department of Natural Resources. For ease of reference, however, we shall refer to these respondents as the DOA and the DNR, respectively, throughout this opinion.
All references to the Wisconsin Statutes are to the 1997-98 version unless otherwise noted.
None of the parties have alleged that a permit was not needed for the pond. Therefore, for purposes of this appeal, we assume that a permit was required.
In its statement of facts, the DNR maintains that the Capouns had notice of, and participated in, the three-day hear
*340
ing. The DNR also states that the Capouns appealed the decision to award the permit Ansari had requested to the Keno-sha County Circuit Court. The Capouns have not challenged these alleged facts in their reply brief; therefore, we accept this procedural history as true.
See Schlieper v. DNR,
See footnote 5 above.
The Capouns phrased the issue as one of subject matter jurisdiction and the respondents have not objected to setting the issue in that way, so we will accept that as the issue we are asked to determine.
If we were asked to determine whether the DNR correctly interpreted WlS. Stat. § 30.19 when it issued Ansari a permit, then the standards of review set forth in
Harnischfeger Corp. v. LIRC,
The Capouns try to establish state action by contending that it was the DNR's granting of the after-the-fact permit which denied them of their use of their land. However, it is clear from their pleadings that it is the increase in water from the retention pond that they claim has caused them damage.
In their brief, the Capouns assert that they were deprived of due process by an "after-the-fact hearing." However, the three days of hearings were held before the DNR issued the permit, not after.
