OPINION
Capitol Indemnity Corporation appeals from a final judgment against it in a suit to recover on a payment bond. See Tex. Gov’t Code Ann. § 2253.073 (Vernon 2000). We affirm the trial court’s judgment.
BACKGROUND
In February 2001, Capitol Indemnity Corporation issued a payment bond on a public works project pursuant to Texas Government Code Chapter 2253 for a project involving additions and renovations to Natalia Independent School District buildings. That same month, Kirby Restaurant Equipment and Chemical Supply Company entered into a contract with the general сontractor for the project in which Kirby agreed to provide labor and materials. In May 2003, Kirby instituted this suit against both the general contractor and Capitol, as surety on the рayment bond, alleging that it had provided the labor and materials as agreed but had not been paid by the general contractor.
Kirby alleged it had properly perfected its claim against the payment bond by correspondence dated May 7, 2002. Capitol denied that the correspondence was sufficient to comply with the notice requirements set out in the Texas Government Code for perfection of a claim. See Tex. Gov’t Code Ann. § 2253.041(c) (Vernon 2000). On cross-motions for summary judgment, the trial judge granted summary judgment in favor of Kirby. This appeal timely followed.
Analysis
In its sole issue on appeal, Capitol contends that the trial court erred in granting Kirby’s cross-motion for summary judgment and denying Capitol’s motiоn for summary judgment. Capitol asserts that Kirby’s claim for payment on the bond should have been barred as a matter of law due to Kirby’s failure to strictly comply with the notice requiremеnts provided in section 2253.041 of the Government Code. We disagree and accordingly affirm the trial court’s judgment.
Standard of Review
A summary judgment is reviewed
de novo. Natividad v. Alexsis, Inc.,
Hеre, the facts regarding Kirby’s claim are essentially undisputed. Capitol does not dispute that Kirby provided labor and materials for the public works project, nor does it challenge the amount of the claim asserted by Kirby. The only issue before the court is whether the notice provided by Kirby to Capitol and the general contractor, together with the accompanying sworn statement, is sufficient to satisfy the notice
Perfection of a Claim
A governmental entity that enters into a public wоrks contract with a general contractor must under certain circumstances require the contractor to execute performance and payment bonds before work begins. Tex. Gov’t Code Ann. § 2253.021(a) (Vernon Supp.2004-05). The purpose of the payment bond is to protect claimants who provide labor or materials in the constructiоn of public works, because public property is protected from forced sale and therefore may not be made the subject of a mechanic’s lien.
City of LaPorte v. Taylor,
Kirby’s Notice to Capitol
The notice provided by Kirby to Capitol сonsisted of a letter dated May 7, 2002, accompanied by a sworn document entitled, “Application and Certificate for Payment.” In the letter, Kirby states that the letter is intended to provide notice that the identified account has not been paid in accordance with the work performed for the month of February 2002. The letter states, “The sum of Seventy nine thousand nine hundred fifty six dollars and seventy five cents ($79,956.75) is currently unpaid and owing for such work, this amount does not include any agreed retainage .... if this deficiency should not be оtherwise paid or settled, a claim may be filed on your bond.” The attached sworn certificate for payment includes the following statement:
The undersigned Contractor [Kirby] certifies that to the best of the Contractor’s knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certifications for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
The document indicates that $79,956.75 is the “current payment due.”
Capitol contends that Kirby’s claim is barred as a mаtter of law because Kirby’s letter and sworn statement are inadequate to properly perfect a payment bond claim. The alleged deficiencies arе that the sworn statement does not indicate that “the amount claimed is just and correct,” nor does it state that “all just and lawful offsets, payments, and credits known to the affiant hаve been allowed.” See Tex. Gov’t Code Ann. § 2253.041(c).
Compliance with Statute
Capitol contends that a claimant must strictly comply with the statute’s notice requirements in order to properly perfect a claim. While it is true that notice is a substantive condition precedent to the ability to pursue a claim on the bond, we disagree that the notice must strictly conform to the exact languagе provided by the
The statute establishing the procedure for presenting a claim against a payment bond on a public contract is remedial in nature and should therefore be cоnstrued liberally to accomplish its purposes.
Taylor,
Kirby’s letter and sworn statement indicate that the amount of the claim is “currently unpaid and owing,” “now due,” and represents the “current payment due.” It further affirms that the amount claimed is for work that has been сompleted in accordance with the contract. We conclude that this language is sufficient to inform the surety, in substance, that the amount claimed is “just and correct” in сompliance with the statute.
See Featherlite,
Because we conclude that Kirby’s notice substantially complies with the statutory requirements for perfection of its claim against the bond, and because no other issues were raised challenging the claim, we affirm the trial court’s judgment against Capitol.
Notes
. The current version of the McGregor Act is codified in the Texas Government Code. See Tex.Rev.Civ. Stat. Ann. art. 5160' (Vernon 1987), repealed by Act of May 22, 1993, 73rd Leg., R.S., ch. 268, § 46(1), 1993 Tex. Gen. Laws 583, 986 (current version at Tex. Gov’t Code Ann. §§ 2253.001-.079 (Vеrnon 2000 & Supp.2004-05)).
. We presume that the agreed upon price for the labor and materials to be provided by Kirby was "just” as it was negotiated by sophisticated and knowledgeable parties, and there is no complaint that the amount claimed is not in accordance with the parties’ agreement.
See Featherlite,
