54 P. 1093 | Or. | 1898
delivered the opinion.
This is a suit to foreclose a mechanic’s lien. The facts are that on March 6, 1893, the defendant Byan, being the owner of lots 1 and 2, in block No. 44, in the City of Salem, gaye a mortgage thereon to the defendants, Easton and Chase, to secure the payment of $2,500, and, in April following, entered into a written contract with the plaintiff, wherein the company agreed to furnish the lumber then intended to be used in the construction of a building on one of the lots included in the mortgage, for the agreed sum of $666, and also such extra lumber as might be needed at the market price, to be paid, for in monthly installments of $50 each, the first payment to
Three questions were discussed by counsel at the hearing : First, as to whether the plaintiff was entitled to a lien for the installments which became due under its contract with Ryan over six months prior to the commencement of the suit; second, whether it was an original contractor, and therefore entitled to sixty days in which to file its lien, or a material man or lumber merchant, and only entitled to thirty days; and, third, whether the lien of Noble’s mortgage was entitled to priority on the land.
The evidence shows that some time in May, 1893, and while the building upon which plaintiff claims a lien was in process of construction, Easton and wife offered to sell to the defendant, Noble, the $2,500 mdrtgage held by Mrs. Easton, and the defendant Chase. Noble declined to purchase the entire mortgage, but offered to take $1,025 of the amount secured thereby, which was accepted. The mortgagees, however, were unwilling to assign the mortgage, as they still held some $1,500 of the original debt; and it was thereupon arranged that two
At the time this change was made in the form of the security for the original indebtedness, the lien of plaintiff had not been filed, nor had Ryan made default in his payments; and, this being so, it would be carrying the doctrine further than any adjudged case of which we have knowledge to hold that the defendant Noble is not entitled to have his lien restored to the position of the original mortgage as against the plaintiff’s lien, simply because he knew that the building was then in process
Affirmed.
Section 3072: “Every building or other improvement ♦ ♦ * constructed upon any lands with the knowledge of the owner, or the person having or claiming any interest therein, shall be held to have been constructed at the instance of such owner or person having or claiming any interest therein; and the interest owned or claimed shall bo subject to any lien filed in accordance with the provisions of this act, unless such owner or person * * * shall give notice that he will not be responsible for the same.”