136 Iowa 243 | Iowa | 1907
Under a written contract witb the defendant city, the plaintiff constructed a bridge across the Des Moines river. After tbe completion of the work and the payment of the stipulated price, this action was 'brought to recover for extra work and extra material which it was alleged the city by its proper officers had required or requested the plaintiff to furnish beyond and in excess of the labor and material required by the plans and specifications under which the contract was performed. The alleged cause of action is stated in three counts. The ease as made by the first count is, in substancej that the plans and specifications upon which the plaintiff made its bid and upon which it entered into the contract represent that the city had already made borings at the site of the bridge, and thus located the surface of the solid rock or ’ foundation upon which the bridge was to be erected. It was further stipulated that in case the surface of such rock should be found to be other than as shown by the plans and borings referred to, and the party of the first part was thereby put to extra labor, work,
In the second count of the petition, the same matter is stated, though in somewhat different form, and it is further alleged that in making its - bid and entering into its contract for the erection of the bridge, plaintiff relied upon the representations made by the officers and the agents of the city as to the character of the soil and the distance from the surface to a suitable rock foundation, which representations after-wards proved to be untrue and misleading, thereby causing the plaintiff great damage.
The third count set up a claim for damages because of a suspension of the work by order of the officers and agents of the city, but this claim w.as by the trial court withdrawn from the consideration of the jury, and we need not further consider it
The fourth count of the petition states that the contract plans and specifications called for the use in constructing the bridge of a large quantity of iron ribs one-fourth of an inch in thickness, and that, after the work had been entered upon, the defendant’s officers and board of public works requested and required the plaintiff to make use of iron ribs of a thickness of three-eights of an inch, instead of one-fourth inch, as required by the plans, and that the additional cost and value of the iron thus used amounted to a large sum, for which recovery is sought. The defendant denies each and all of the claims thus made against it, and alleges that plaintiff has waived its right to assert such claims, and that
While the record transmitted to this court is very voluminous, the material questions presented by the appeal are comparatively few so far as the merits of the controversy are concerned. The arguments of counsel are largely devoted to the claim stated in the first and second counts of the petition growing out of the alleged extra labor and •expense occasioned by ■ the character of the soil and rock through which excavation was made for the foundation of the bridge. The specifications upon which the contract was at first prepared contained a clause in the following words: “ (4) Survey. The site of the structure has been carefully surveyed and marked on the ground for examination. Five borings have been made on the center line of the structure and as shown on the plans.” It further provided that the excavation for abutments and piers should be carried to solid rock. In the body of the contract, as distinguished from the specifications, is also found the following clause:
The said party of the first part further agrees to perform said work in strict accordance with this contract, and with the plans and specifications hereinbefore referred to, for the sum of seventy-four thousand nine hundred dollars ($14,900), which shall be in full compensation for the cost of the entire work; and the city of Des Moines shall not be liable to the said party of the first part for “ extras ” of any kind, nor for any damage which he may sustain by coming in contact with rock, sand, water or any other unforeseen material or obstruction, nor for any damage by the elements before the work is completed and finally accepted by*247 the city, nor for delays in the completion of said work except as herein otherwise provided; it being’ expressly understood that the contract price above specified shall be in full for all work and material furnished under this contract.
When the contract was submitted for the signatures of the parties, some difference of opinion was disclosed as to the meaning and effect of the original draft of the instrument, and, after considerable discussion, there was added thereto certain provisions entitled “ addenda^” among which was the following:
The plans and specifications for the bridge show that five (5) borings have been made by the city of Des Moines locating the surface of the solid rock for the foundation. It is agreed that in case the surface of said rock is found to be otherwise than as shown by the plans and borings, and the party of the first part is put to extra labor, work, and material in order to make a suitable foundation, then the party of the first part shall be compensated for the extra work and material as provided in the specifications for the compensation of extra work upon the order of the city engineer ; but, if the cost to the contractor is less than that of the construction, as shown by the plans and specifications, the amount of the difference shall be deducted from the contract price.
Both the principal draft of the contract and the addenda above mentioned were then duly executed by both parties, and, with the plans and specifications therein referred to, constituted the final agreement under which the bridge was constructed. The blueprints or copies of the plans furnished by the city to the appellee purport to contain a showing of the borings which had been made at the sites of the abutments and piers and to indicate the character of the earth through which the excavations were to be made, and the depth at which the rock for the foundation would be reached. This showing the plaintiff claims was incorrect and misleading, and that the excavation developed material much more difficult to work, thereby causing in
The material question as to counts 1 and 2 of the petition, which you are called on to consider in relation to said contract, is the character of the material which was necessary to be excavated in order to reach the rock upon which the foundation was to be laid, as shown by the contract, and as actually found during the work. You are instructed that where parties have entered into a contract with reference to a certain state of fact within' the knowledge of one party, and upon which the other entirely relied, and the one having the knowledge represented and stated in said contract certain facts to be true, and you find the same were material facts, then and in that case the party so stating and representing such material -facts shall be bound by them. And in this case if you find that the plaintiff bid upon the work named in said contract with reference to the plans and specifications, and, relying upon said plans and specifications to be true and correct, he made his bid and entered into the contract referred to, and you further find that the representations on said plans were not true and correct, then you will further inquire and determine from the evidence whether, by reason of such difference, the work of making the excavations for abutments and piers was thereby rend*249 ered more expensive. And, if yon find that it was, yon will then proceed to determine from the evidence the difference between what it wonld have cost to do said work, if the conditions had been as represented by the contract, and the reasonable and necessary cost of doing the work, under the conditions that yon find existed, as shown by the evidence: In ascertaining such difference, you will take into consideration the additional labor and material, if any, necessary to do said work, as the conditions existed. And, if you find as above stated, yon will allow plaintiff such difference, if any yon so find, not exceeding the amount claimed in the first and second counts, to-wit, $23,314.23.
In Slusser v. Burlington, 47 Iowa, 300, this court had to deal with a case involving a claim not materially unlike the one which appellee herein asserts in the first and second counts of its petition. In that case the plaintiff entered into a written contract to excavate a portion of a street of the' defendant city at a fixed price per cubic yard. After the work had been done, the plaintiff brought action to recover a sum in excess of the contract price, claiming that, before making the contract, the city by its engineer had pointed out the depth of the excavation which wonld be required to reach the established grade, and that, relying upon such representations, plaintiff had' made his bid and taken the contract and entered upon the work. It is further alleged that said representations were not true, and that the
Evidence was offered on the .trial upon the question whether this provision of the contract had been complied with. It was also, at the close of plaintiff’s testimony, made the greund of a motion for a directed verdict in the defendant’s favor, and was one of the grounds of defendant’s motion for a new trial after the return of the verdict. The trial court in its statement to the jury of the issues in the case recites this as one of the defenses pleaded to the ap-pellee’s claim, but nowhere in the charge is any further reference made to such issue, and the jury were given no directions as to the law governing the same. Error is now assigned upon this omission by the trial court. It is argued by the appellee that this objection, even if well founded as an original proposition, was waived by the appellant, because it failed to make specific request that the jury be instructed upon that issue. In support of this position, we are cited to several cases decided by this court. None of them aré in point. Cox v. Allen, 91 Iowa, 463, and Hall v. Manson, 90 Iowa, 585, do no more than announce the well-established rule of practice that such objection cannot be raised for the first time in this court, while. Parmateer v. Bass, 113 Iowa, 68, and Hall v. Railroad Company, 115 Iowa, 18, clearly restate the well-settled rule that, where an instruction upon any issue submitted to the jury is correct so far as it goes, failure to give further or more specific instructions upon such point will not be held error in the absence of any request therefor by the appellant. But it has often been held that the trial court is bound to see that in every case which goes to a jury they have clear and intelligent notions of the point which they are to decide, and to this end should give necessary and proper instructions upon
We are thus brought to the consideration of the single question whether, had this issue been properly submitted to the jury and the verdict thereon had been in favor of appellant, it would afford a sufficient defense to appellee’s claim. It was entirely competent for the parties in making their contract to hedge the possibility of claims for extra compensation with all such reasonable restrictions as they might devise or agree upon. Experience has shown that such claims are the fruitful' source of controversy and litigation, and it was not unreasonable to provide that, before the final settlement and payment of the contract price, the contractor should present to the proper authority its claims of every kind growing out of the work which it had undertaken to perform, and to make its right to insist upon such claim and enforce payment thereof dependent upon such presentation being made within the limit of time thus fixed. The defense based upon this provision of the contract was therefore valid and sufficient, and, if established upon the trial, entitled the defendant to a verdict and to be discharged with its costs. Whether that defense was thus established was a question for the jury, and, in failing to submit it with proper instructions, there was prejudicial error, because of which a new trial must be ordered.
Other questions argued by counsel will not necessarily
For the reasons stated, the judgment of the district court is reversed.