MEMORANDUM AND ORDER
This diversity action for breach of contract raises a surprisingly novel question: what is the effect of an estimate in an output contract when the supplier produces less than the stated estimate? I conclude that New York law would hold that good faith, rather than the stated estimate, would control whether a breach has occurred.
Background
Plaintiff Canusa seeks damages for lost sales as a result of an alleged breach of contract by defendants Loboseo as well as attorneys’ fees in connection with an equipment lease to Loboseo. The case was tried without a jury, where the following facts are found.
Plaintiff Canusa is a Maryland corporation that recycles and brokers waste paper. A & R Loboseo (“Loboseo”) is a New York corporation that receives, collects, cleans and resells this recyclable paper to paper mills or brokers like Canusa. Michael Loboseo is A & R Lobosco’s president.
In late 1992, Loboseo entered into an agreement with the City of New York to accept 850 tons per week (3,400-3,500 tons per month) of material to be recycled. See Trial Tr. (Tr.) at 233; Def.’s Ex. A, “Agreement and Bid Specifications” at B-7. To handle this paper, Loboseo needed a bailer, a piece of equipment to process and bale the recyclable paper. At about the same time, Canusa heard from a third party also in the paper recycling business that Loboseo had obtained a City contract and might be looking for a baler. See Tr. at 337-9. Loboseo had put down a deposit on a baler with another firm, but ultimately decided to enter into an arrangement with Canusa because Canusa would finance the baler, while the other arrangement obligated Loboseo to obtain separate financing. See id. at 237. Canusa’s president, Bruce Fleming, testified that Canusa only enters into baler financing agreements to obtain a steady supply of paper. Fleming testified that Canusa obtains 30% of its paper from contract sources like Loboseo and obtains the balance in the spot *726 market. Of that 30%, approximately half, or 15% of Canusa’s total supply of waste paper comes from agreements similar to the one Canusa had with Lobosco.
Loboseo began receiving recyclables from the City in January of 1993; later that month, Michael Loboseo entered into negotiations with David Knight, a Canusa vice president, for a baler. See id. at 236. On March 15, 1993, the parties entered into an Equipment Lease secured by a personal guarantee signed by Michael Lobosco. See Pl.’s Ex. 1 (“Equipment Lease”); Pl.’s Ex. 2 (“Personal Guarantee”). Among other things, the Equipment Lease provided that the lessee (Loboseo) would be liable for costs, fees and reasonable attorneys’ fees for any action taken to preserve Canusa’s rights. See Pl.’s Ex. 1, ¶ 14.
The lease also provided that Loboseo was to pay rent, but did not specify an amount. The lease did, however, refer to an “Output Agreement” (“Agreement”) that the parties had entered into on March 1, 1993. See Tr. at 56. Thus, Loboseo would finance the baler by supplying Canusa. with paper, which would then be credited to its account. Michael Lobosco testified that under these agreements Lobosco was to pay $1,551.00/ week toward the baler; any amounts of paper sent in excess of that would be credited to Lobosco’s account. See id. at 240. Michael Lobosco also testified that he was aware that Canusa would resell his paper to third parties. See id. at 238.
The Agreement (captioned an “Output Agreement”) recited that the parties were entering into an output contract with a five-year term, but it also contained language stating that Lobosco would initially ship 1100 tons per month of number 8 quality old news print (ONP 8) 1 per month to Canusa in 1993, and 1500 tons per month thereafter (1994-97). Both parties presented evidence that they understood this number to mean the minimum number of tons Lobosco was obligated to provide to Canusa. See Tr. at 123, 241. The Agreement also provided that the price per ton of ONP would be set each month between the parties and defined acceptable ONP. Fleming described ONP 8 as “anything that normally comes in a household newspaper.” Tr. at 36. Materials that have no relationship to paper, such as garbage, masonry, metal, etc., are called prohibi-tives. Materials that are acceptable in small amounts are called outthrows. Examples of outthrows include Sunday newspaper magazines and coupon circulars. See id. Some paper products, most notably telephone books, are also considered prohibitives. The Agreement specified that no prohibited materials would be accepted, and that total out-throws could not exceed one quarter of one percent (.25%) by weight. See Pl.’s Ex. 3 ¶ 8. The Equipment Lease and Guarantee provided for the application of Maryland law, while the Agreement provided for the application of New York law.
From the beginning, the relationship was a rocky one. Canusa provided documentation demonstrating the actual tons of material shipped to it from 1993 into May 1994, Lo-bosco’s last shipment date. 2 Only in the very first month of the contract, April 1993, did Lobosco come close to the estimate in the Agreement, shipping 942 tons. Michael Lo-bosco gave several reasons for his firm’s inability to meet the schedule set in the Agreement. First, he stated that the materials from the City had a much higher proportion of garbage than what he had previously obtained from similar programs in the suburbs. See Tr. at 245. Second, he noted that he did not always get the amount promised under the City contract. See id. He also testified, without contradiction, that of the material he received from the City, ultimately 28% was convertible into ONP 8. Michael Lobosco derived this figure as follows: he testified that 30% of each load from the City consisted of prohibitives such as garbage, *727 thus leaving 70% of the initial amount. Of this remainder, Loboseo estimated that 40% of it was ONP 8. See id. at 266. During this time, Loboseo also received about 150 tons per month of newspaper from other sources. See id. at 292.
At the same time Loboseo was not meeting the specification of the Agreement, it was shipping another paper product to Mandala Recycling. See Tr. at 265; Pl.’s Exs. 15, 29-32. Loboseo testified that this product contained “50-60%” newspaper. See Tr. at 265. There was no direct testimony by the buyer or the seller as to the outthrow content of this proprietary package, which was to be sent overseas, but the principal of Mandala, Stephen Batty, testified that he was allowed “a little more latitude” in the material that he shipped to Indonesia. See id. at 223. 3
Beginning in September 1993, after a series of attempts to have Loboseo’s output conform to ONP 8, Canusa offered to modify the Agreement. Specifically, Canusa offered to accept 500 tons per month of ONP 7/8 (also known as “export news”) instead of the higher quality ONP 8. See Ex. 49-A, (Ltr. from David Knight to Mike Loboseo dated December 13, 1993); Ex. 49-B (Ltr. from David Knight to Ken Knigan of Loboseo dated September 13, 1993). Michael Lobos-co never signed this agreement; however, he testified that he acted pursuant to his understanding of it. See Tr. at 261. Loboseo also testified that he told Knight not to ship this product to a newsprint mill because it would be rejected, but that Knight went ahead and did so. See id. Knight’s testimony was similar, except that Knight stated that the material was rejected because it had rotted due to moisture. See id. at 146, 157-8. In the month following this amendment (October, 1993), the amount of paper Loboseo shipped to Canusa almost doubled.
Although Loboseo had shipped 440 tons in January of 1994, that number decreased to 270 in February and zero in March. In January 1994, Canusa offered to accept a “baler fee” payment of $3.00 per ton, relieving Loboseo of any obligation under the Agreement. See Pl.’s Ex. 50 (Ltr. from Can-usa to Loboseo dated January 25, 1994). In March 1994, Canusa again offered to modify the Agreement. Loboseo would pay, in addition to the regular baler payment, $3,000.00 per month. This amount was computed on the basis of a $2 per ton profit on the 1500 tons that Loboseo was to have shipped to Canusa. In return, Canusa would release Loboseo from its obligation under the Output Agreement. See Pl.’s Ex. 52 (Ltr. from Can-usa to Loboseo dated March 30, 1994). Lo-bosco never accepted this proposal. See Tr. at 51-2. Canusa filed its complaint on June 27,1994.
Canusa sought damages for breach of contract, fraudulent inducement, and replevin of the baler. The parties entered into a stipulation of partial settlement on June 30, 1994, which provided that Loboseo would purchase the baler from Canusa, settling the replevin and rent claims, but that Canusa reserved all of its other rights under the Equipment Lease, guarantee, and Agreement. See Pl.’s Ex. 4 (Stipulation of Partial Settlement) At trial, Canusa’s fraudulent inducement claim was dismissed; thus, only the action for breach of contract under the Agreement and fees and costs associated with the replevin action remain to be decided.
Discussion
A. Breach
In this diversity action, the parties do not dispute that New York law governs the question of breach of the Agreement, while Maryland law governs the Equipment Lease and Guarantee. Under New York law, because the Agreement is a contract for the sale of goods, it is governed by New York’s version of the Uniform Commercial Code (“UCC”).
*728 Canusa contends that Lobosco breached its contract by failing to meet the minimum set forth in the Agreement. Lobosco contends that there was no breach because it supplied Canusa with all the ONP 8 that it produced. The initial dispute, then, is over the meaning of an estimate in an output contract. Canusa argues that under the Agreement it is entitled to the minimum tonnage specified, while Lobosco argues that output agreements like this one are subject only to the requirement of good faith. Significantly, Canusa did not offer any evidence to prove, nor advance the theory at trial, that this contract was a fixed quantity contract; indeed, it would be difficult to do so given the document itself. In fact, Knight testified at trial that Canusa subsequently changed its contracts to supply contracts to ensure that it would receive a specified amount. See Tr. at 167-9; Def.’s Ex. F. Thus, there is no dispute that the Agreement is an output contract; the issue is what weight should be given to the Agreement’s estimate.
Output contracts are governed by § 2-306, which provides in part:
A term which measures the quantity by the output of the seller or the requirements of the buyer means such actual output or requirements as may occur in good faith, except that no quantity unreasonably disproportionate to any stated estimate or in the absence of a stated estimate to any normal or otherwise comparable prior output or requirements may be tendered or demanded.
N.Y.U.C.C. § 2-306(1) (McKinney 1993). Prior to the introduction of the UCC, estimates in output contracts were just that: estimates.
See Orange and Rockland Utils., Inc. v. Amerada Hess Corp.,
Because these decisions do not address the concerns that arise in the specific factual context of this case they are inapposite. Three cases do, however, shed light on this issue. The first, a leading case in New York, is
Feld v. Henry S. Levy & Sons, Inc.,
*729
The second relevant case is
Empire Gas Corp. v. American Bakeries Co.,
The court began its analysis of the disproportionate proviso by noting that case law distinguishes between overdemanding and underdemanding cases, and that at common law the sole test of underdemanding was good faith. See id. at 1337 (citing eases) The court then read the statute to mean that the “unreasonably disproportionate” language as providing a specific articulation of good faith, the general standard, in the context of an overdemanding case. See id. at 1338. Thus, the “unreasonably disproportionate” language of § 2-306(1) has no application in the context of an underdemanding ease.
At least one circuit court has adopted the reasoning of
Empire Gas
in a factual setting similar to this case. In
Atlantic Track & Turnout Co. v. Perini Corp.,
Although
Atlantic Track
is not controlling and although neither
Feld
nor
Empire Gas
is directly on point, the reasoning of these three cases is compelling here. First, as the
Feld
court noted, good faith is the general standard by which output contracts are measured.
See Feld,
Moreover, a mechanical adherence to the estimate in the contract would essentially convert all output contracts with an estimate into fixed contracts. The fallacy of this proposition is illustrated by this case: having bargained for the flexibility of an output contract, Canusa now seeks to treat it as a fixed goods contract. An output agreement is not transformed into a fixed quantity contract by the insertion of an estimate. Thus, where an output contract provides for a certain amount of goods to be produced, the appropriate test for a seller’s reduction in output is good faith rather than the estimate in the contract. 5
After discounting the estimate in the Agreement as the appropriate yardstick, the baseline for the defendant’s good faith must be set at Michael Lobosco’s own estimate of the ONP 8 he could produce from the City’s material, because Canusa failed to establish any other basis. Despite being given the opportunity, Canusa did not offer
any
evidence of other percentages of ONP production from
any
city’s recycling program. Measured by its own standard, however, Lo-bosco’s performance does not comport with good faith. When asked why he failed to produce ONP 8 in quantities consistent with his own production estimate, Michael Lobos-eo’s only explanation was that it would have taken more time to sort the material.
See
Tr. at 298. The fact that it would cost more to clean the material to reach the ONP 8 standard does not demonstrate good faith; nor does it provide an excuse,
see Feld,
Lobosco did not raise the defense of waiver at trial. Even if it had, Canusa’s efforts to work with Lobosco is not a waiver of the good faith requirement, because a party need not terminate the contract, but may instead seek to resolve the problem.
See Horn Waterproofing Corp. v. Bushwick Iron & Steel Co., Inc.,
The only issue remaining is at what point can it be said that Lobosco breached the contract. Although an earlier date can. be supported by the record, it would appear that as late as October, 1993, Lobosco was seeking to resolve his differences with Canu-sa. In that month, he sent substantially more than the minimum requirement and double the previous month. In November, shipment began to deteriorate again, never to recover. Therefore, the breach can fairly be ascribed as occurring in November, 1993, and damages will be calculated from that date.
B. Damages
Canusa contends that under the UCC it is entitled to damages for the loss of profits it could have had, had it received Lobosco’s ONP 8.
See Kenford Co., Inc. v. County of Erie,
Lobosco argues that because Canusa covered its contractual obligations to its purchasers, it has no damages. This argument must be rejected for three reasons. First, although neither § 2-713 or § 2-715 speaks in terms of “lost profits,” as noted above, in the case of a buyer-reseller or broker, lost profits are available as consequential damages. Second, the general objective of the damages provisions in the UCC is to put the aggrieved party “in as good a position as if the other party had fully performed____” N.Y.U.C.C. § 1-106(1) (McKinney 1993). Canusa provided evidence in the form of testimony that it could have sold all the material Lobosco produced in addition to any cover that Canusa obtained.
See
Tr. at 65. Lobosco does not contest that there was a viable market for ONP 8; therefore, the fact that Canusa sold all the ONP 8 it acquired does not bar it from recovering damages for the
loss
of the ONP 8 it could have sold if it was obtainable. In
Apex Oil Co. v. Vanguard Oil & Service Co., Inc.,
To recover damages in New York a plaintiff must prove “causation, foreseeability, [and] certainty (reasonable or less).”
Coastal Aviation,
Finally, “the alleged loss must be capable of proof with reasonable certainty.”
Kenford,
Canusa devoted much energy to producing receipts from Mandala Recycling and SGS, an inspection firm, to show that Lobos-co actually sold far more material to Mandala than it otherwise accounted for. Canusa argues that by looking at this evidence, it is clear that Lobosco could have met the stated minimum. While this argument is relevant on the issue of whether Lobosco has acted in good faith or breached the contract, Lobos-co’s sales to Mandala are irrelevant to Canu-sa’s damages. First, Canusa was unable to show that the material sold to Mandala was ONP 8 or close to it. At trial, both an official and a field employee of SGS testified as to SGS’s inspection procedure, but neither witness testified that the inspected bales consisted of ONP 8 as defined in the Agreement. See Tr. at 320-23; 332-33. Mandala’s president, Steven Batty, refused to state what the content of the export bales was, except to state that they contained a higher percentage of outthrows than ONP 8. See id. at 223. Lobosco argued, without contradiction, that even if the outthrow proportion of this export material could be established, that the tonnage figures for material shipped to Mandala could not be related to the tonnage shipped to Canusa because outthrows are denser than newspaper. See id. at 275, 369. Second, Canusa, in any case, is not entitled to Lobos-co’s profit on its sales to Mandala for a more important reason. Canusa’s agreement was not an exclusive contract. Lobosco was not prohibited from selling non-ONP 8 material to third parties provided it in good faith sought to meet its obligation to Canusa. Consequently, Canusa did not establish for the purposes of computing damages that the material sold to Mandala by Lobosco should be included in the damages calculation.
Canusa is, however, entitled to the damages it incurred as a result of Lobosco’s failure to perform the contract in good faith. If Lobosco had done so, Canusa would have at a minimum received as ONP 8 28% of the tonnage the City delivered to Lobosco. Additionally, Canusa is entitled to rely on the fact that Michael Lobosco stated that he had other sources of paper. At trial, he testified that these sources produced another 150 tons per month of ONP 8.
Canusa claims damages through the remaining period of the contract. Canusa is entitled to judgment against A & R Lobosco in an amount equal to 28% of the City’s tonnage plus 150 tons per month times its *734 gross profit over the term of the contract, starting in November, 1993. 9
C. Attorney’s Fees
Canusa also seeks recovery of fees expended on the replevin action for the baler. Loboseo argues that Canusa is not entitled to attorney’s fees because there was no failure to pay rent under the lease. This argument is grounded in the assertion that Loboseo never sent a check for rent to Canusa. Because of the relationship between the Agreement and the lease, this argument is dubious at best. It is unnecessary to consider it, however, because the lease gives Canusa the right to bring an action upon a default under the Agreement. See PL’s Ex. 1 ¶ 14. Canu-sa is thus-entitled to recover fees as provided for by Maryland law.
Under Maryland law, attorney’s fees may be awarded to the prevailing litigant when they are provided for in a contract.
See Maxima Corp. v. 6933 Arlington Development Ltd. Partnership,
Canusa submitted sufficient evidence in the form of bills and testimony to support an award of fees. Canusa submitted bills documenting the specific work and the number of hours billed by Niles, Barton, its counsel in Baltimore and by Hill, Rivkins, its counsel in this area.
See
PL’s Ex. 7A (invoice from Hill, Rivkins for $18,145.00); PL’s Ex. 7 (revised invoice from Hill, Rivkins for $16,388.01); PL’s Ex. 10 (invoice from Niles, Barton for $2,000.21). Canusa also produced testimony supporting these invoices from the Hill, Rivkins lawyer who had performed the work.
See
Tr. at 101-05. First, under Maryland law, the fees are not unreasonably disproportionate as a matter of law.
See Reisterstown,
Conclusion
By failing to produce all the ONP 8 that it admitted it could have produced, Lobosco breached its output contract with Canusa. Canusa is entitled to damages under the UCC consistent with what Lobosco’s good faith production would have yielded. Additionally, under the Equipment Lease, Canusa is entitled to attorneys’ fees and costs for the action to replevin the baler. Judgment to be entered against A & R Lobosco, Incorporat-. ed, in the amount $125,597.59 (see Appendix). Judgment to be entered against A & R Lo-bosco, Incorporated and Michael Lobosco in the amount $20,138.22. The Cleric of the Court is directed to enter judgment accordingly and close the case.
SO ORDERED.
Canusa v. A & R Lobosco, CV-94-3030
Appendix
l. Month 2.Tonnage sent to Lobosco as reflected on Lobosco invoices to City (PI. Exs. 19-24) 3.Lobosco’s production estimate plus non-City sources (28% of Col. (2) Plus 150 tons) 1 4.Tons of ONP 8 delivered to Canusa (PI. Ex. 13) 5.Difference between amount delivered and Lobosco’s production estimate (Col. (3) minus Col. (4)) 6.Canusa’s Lost (Col. (5) x $4.1349 (average prof-ii/ton))*
11/93 1451 556 403 153 $ 633
12/93 1499 570 348 222 918
1/94 1057 446 444 2 8
2/94 561 307 270 37 153
3/94 1942 694 0 694 2,870
4/94 1674 619 186 433 1,790
5/94 2037 720 79 641 2,650
6/94 1928 690 0 690 2,853
7/94 1687 622 0 622 2,572
8/94 1672 618 0 618 2,555
9/94 1760 643 0 643 2,659
10/94 1707 628 0 628 2,597
11/94 1807 656 0 656 2,712
12/94-1700 2 626 0 24,414 100,949
2/98
Total: $125,920
Notes
. The Agreement defined ONP 8 as "Tare free, sorted, fresh dry pre-consumer or post-consumer newspaper, free from magazines and paper other than newsprint____ Prohibited materials are not permitted and total outthrows may not exceed one quarter of one percent (.25%).” Prohibited materials included, in addition to non-paper material, "gift wrap, windowed envelopes, carbon paper, fax paper, hardcover books, telephone books, paper bags, ... [and] cardboard____” Agreement ¶ 8.
. See Appendix for a listing of tons shipped.
. Canusa argues that the material sold to Mandala should be considered as the equivalent of ONP 8 even though Canusa admits that its outthrow content may have exceeded the requirements for ONP 8 by a considerable margin (10% versus .25%). In support of this argument, Canusa produced evidence from an inspection firm (SGS) which certified to the destination country (Indonesia) that the bales sold to Mandala and shipped from Lobosco’s premises were exportable recycled paper. See Tr. at 310-33. For reasons explained in the "Damages” section of this opinion, infra at 733, Canusa is not entitled to damages based upon Lobosco’s sales to Mandala.
. Section 1-203 of the UCC states: "Every contract or duty within this Act imposes an obligation of good faith in its performance or enforcement.” (McKinney 1993). Section 2-103(l)(b) states: " 'Good faith’ in the case of a merchant [§ 2-104] means honesty in fact and the observance of reasonable commercial standards of fair dealing in the trade.” (McKinney 1993). Here, both parties are merchants within the meaning of the UCC. See N.Y.U.C.C. § 2-104(1) (McKinney 1993).
. An alternative analysis under common law principles of contract law would reach the same result. As a matter of law, the contract is ambiguous because there is more than one reasonable reading of it.
See Breed v. Insurance Co. of N. Am.,
Testimony taken at the trial clearly demonstrated that the figure placed in the Agreement was based solely on the figure from the City contract.
See
Tr. at 240-41. Furthermore, Michael Lobosco testified that although he gave Knight the tonnage figure from Lobosco's contract with the City, it was Canusa that specified the tonnage figures in the Agreement. In this context, the pertinent interpretive principle is the rule that "[i]n cases of doubt or ambiguity, a contract must be construed most strongly against the party who prepared it, and favorably to a party who had no voice in the selection of its language.”
Jacobson v. Sassower,
. As a result, there is no need to reach Lobosco's impossibility defense, because impossibility is merely a "[particular application!]” of good faith. N.Y.U.C.C. § 1-203, cmt. (McKinney 1997);
see also
§ 2-615, cmt. 6; § 2-615, cmt. 11 ("An excused seller must fulfill his contract to the extent which the supervening contingency permits.... ”). In any event, Lobosco has not demonstrated that its performance is commercially impracticable within the meaning of § 2-615. Section 2-615 requires a breaching seller to show (1) a contingency (2) the impracticability of performance as a consequence of the occurrence of that contingency, and (3) that the nonoccurrence of the contingency was a basic assumption of the contract.
See Luria Bros. & Co., Inc. v. Pielet Bros. Scrap Iron & Metal, Inc.,
. Section 1-207 of the UCC provides: "A parly who with explicit reservation of rights performs or promises performance or assents to performance in a manner demanded or offered by the other party does not thereby prejudice the rights reserved." (McKinney 1997). New York's own commentary on this section is illuminating: "This section permits a party involved in a Code-covered transaction to accept whatever he can get by way of payment, performance, etc., without losing his rights to demand the remainder of the goods, to set-off a failure of quality, or to sue for the balance of the payment, so long as he explicitly reserves his rights.” N.Y.U.C.C. § 1-207, N.Y. Annot. (McKinney 1997);
see also Horn,
. The parties discuss at length
R.E. Davis Chemical Corp. v. Diasonics, Inc.,
. For the calculation of the damages, see Appendix.
. Rounded to the nearest whole dollar.
. The City’s shipments to Lobosco apparently stabilized at approximately 1,700 tons per month after July 1994. Therefore, Canusa’s damages for the 39 months remaining on the contract will be figured on the basis of 1,700 tons per month.
