Canon School District No. 50 v. W.E.S. Construction Co.Canon School District No. 50 v. W.E.S. Construction Co.
OPINION
We are asked to determine whether Canon School District No. 50 (School District) is bound by its contractual agreement to arbitrate procurement-related claims brought against it by W.E.S. Construction Company, Inc. (W.E.S.). This issue arises because the administrative rules adopted by the Arizona Board of Education pursuant to
Factual and Procedural Background
In January 1989, W.E.S. entered into a contract with the School District for the construction of a school building in Black Canyon City. The contract included a provision requiring all disputes between the parties to be resolved through arbitration. 1
After W.E.S. began construction, the School District apparently experienced problems obtaining the requisite building permits from Yavapai County. W.E.S. claims that because of these problems, the School District instructed W.E.S. to discontinue its work on the project until the dispute was resolved, and consequently, construction was delayed for more than 2 months.
W.E.S. further alleges that in May 1989, it was prepared to resume construction upon receiving certain necessary information from the project architect. However, a dispute arose between W.E.S. and the project architect after each claimed that the other was not expeditiously performing its duties under the contract. Thus, in early July 1989, W.E.S. served the School District with a demand for arbitration, contending that the School District had breached the contract. W.E.S. claimed that as a result of these breaches, it incurred delay-related damages as well as lost profits and consequential damages.
After receiving the demand for arbitration, the School District filed a complaint in Yavapai County Superior Court requesting that the court enter a show cause order as to why the arbitration should not be stayed. The School District maintained that
The School District appealed from the trial court’s judgment, and the court of appeals affirmed the judgment in part and reversed in part.
Canon School Dist. v. W.E.S. Constr. Co.,
In this court, W.E.S. filed a petition and the School District filed a cross-petition seeking review of the court of appeals’ decision. We granted review, and for the reasons discussed below, we hold that
Discussion
This Article [Article 10, School District Procurement Code; AAC. R7-2-1001 to -1195] provides the exclusive procedure for asserting a cause against the school district and its governing board arising in relation to any procurement conducted under this Article.
(Emphasis added.)
The School District argues that, notwithstanding its contractual agreement to arbitrate, all of W.E.S.’s procurement-related claims must be resolved according to the Board of Education’s exclusive remedy procedure. To the contrary, W.E.S. maintains that
A contract for the procurement of construction shall include a provision which provides for negotiations between the school district and the contractor for the recovery of damages related to expenses incurred by the contractor for a delay for which the school district is responsible, which is unreasonable under the circumstances and which was not within the contemplation of the parties to the contract. This section shall not be construed to void any provision in the contract which requires notice of delays, provides for arbitration or other procedure for settlement or provides for liquidated damages.
(Emphasis added.)
In light of the apparent conflict between the language of
In construing
As evidence of the Legislature’s intent, the court of appeals primarily relied upon similarities between
We have long recognized that one of the fundamental goals of statutory construction is to effectuate legislative intent.
See, e.g., Automatic Registering Mach. Co. v. Pima County,
It is only where there is no doubt as to the intention of those who frame [a] ... statute that a court may modify, alter or supply words that will “obviate any repugnancy to or inconsistency with such intention,” and by so doing permit “particular provisions” to be read or construed otherwise than “according to their literal meaning.”
Board of Supervisors v. Pratt,
Unlike the court of appeals, we do not find the legislative intent in this case sufficiently unambiguous to warrant the conclusion that the words “this section” in
Moreover, we do not agree that similarities between
We agree with the court of appeals that similar statutes should be construed consistently whenever possible. However, we do not believe that interpreting the words “this section” in
Additionally, the effect and consequences of alternative statutory constructions, although not determinative, may be taken into consideration.
DOR v. Southern Union Gas Co.,
For the reasons discussed above, we construe the words “this section” in
Disposition
We affirm the trial court’s judgment that the School District’s contractual agreement to arbitrate is valid and enforceable, and we therefore vacate the court of appeals’ opinion. In addition, we affirm the trial court’s judgment awarding attorney’s fees and costs to W.E.S. Although the court of appeals declined to award attorney’s fees to either party on appeal upon determining that neither party was the “successful party,” pursuant to
Notes
. This provision was taken from a standard form contract drafted by the American Institute of Architects (AIA), which reads in relevant part:
7.9 ARBITRATION
7.9.1 All claims, disputes and other matters in question between the Contractor [W.E.S.] and the Owner [School District] arising out of, or relating to, the Contract Documents or the 177 Ariz.Reps.-20 breach thereof ..., shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.
"General Conditions of the Contract for Construction,” AIA Document A201 (1976).
. We also granted review on three additional issues not discussed in the text of this opinion, two from W.E.S.’s petition for review and one from the School District’s cross-petition.
The two issues from W.E.S.’s petition were the due process and estoppel issues presented to and decided by the court of appeals. Because we find the statutory construction issue dispositive in this case, we need not reach the other two issues at this time.
The issue from the School District’s cross-petition was whether a school district is authorized to enter into a procurement contract that contains an agreement to arbitrate disputes. This issue is a corollary of the statutory construction issue we resolve above, and as such, we answer it in the affirmative.
. Section 41-2617 provides:
A contract for the procurement of construction shall include a provision which provides for negotiations between the state governmental unit and the contractor for the recovery of damages related to expenses incurred by the contractor for a delay for which the state governmental unit is responsible, which is unreasonable under the circumstances and which was not within the contemplation of the parties to the contract. This section shall not be construed to void any provision in the contract which requires notice of delays, provides for arbitration or other procedure for settlement or provides for liquidated damages.
. We note that while this case was pending in the court of appeals, the parties proceeded to arbitration. The arbitrators entered an award in favor of W.E.S. on both its claim and the School District’s counterclaim. After the trial court confirmed the arbitration award, the School District appealed. On appeal, the court of appeals affirmed.
Canon School Dist. v. W.E.S. Constr. Co.,