189 Pa. 208 | Pa. | 1899
Opinion bv
The defendants in July, 1896, entered into a contract with the city of Pittsburg to build and complete within ten months what is known as the Schenley Park bridge. Preliminary to commencing the work, they contracted with plaintiffs to furnish all the stone necessary for it, of certain dimensions and quality, in accordance with the plans and specifications of the director of public works of the city, and subject to his inspection and approval; the delivery to commence July 25, 1896, and continue at a weekly average of quantity, the whole to be on the ground by September 15,1896. This contract although drawn as stated, was not actually signed by the parties; the plaintiffs rather feebly denied it to be the contract, and although they admit that a copy was delivered to them, and they followed its specifications, yet they alleged instead of all the stone for the bridge, they were only to deliver such quantity as could reasonably be taken out at their quarry; but the weight of the evidence was clearly against them on this point, and it having been submitted to the jury, they have found the unsigned instrument embodied the contract. We therefore assume it to have been the contract. It contains this stipulation:
“ In case the said first party (Canavan) fails to furnish suitable stone as fast as mentioned above, the said second party (Neeld & Foley) may purchase the deficiency, paying therefor open market rates, and charging said first party with any additional cost there may be.”
The burden of appellants’ complaint is set out in the fourth to ninth, inclusive, assignments of error; these all allege, that assuming the unsigned writing to be the contract, the court adopted a construction of it not warranted by its terms, and not in accord with the intention of the parties. It is, in substance, argued that but one particular default was contemplated, the failure to furnish all the stone, and that for this but one measure of damage was expressly provided, and that was the difference between the contract price of delivery and the open market price.
In interpreting this clause of the contract, we seek the intention, not alone from the exact words, but from what should be
Plaintiffs argue, that under the contract defendants had but
The reasonable construction of this clause, is that put upon it by the court below; that is, it measures the damages for plaintiffs’ default in this particular at a sum not exceeding the difference between the open market price and that specified in the contract; it might be less than this, but not more. ■ The words “ fail to furnish suitable stone as fastas” required by the agreement, meant that in no event was the partial or total failure of plaintiffs to work an interruption to defendants in completing their contract, but that they should have the right to at once go into the market and purchase. It did not restrict defendants to this single item of damages, but left open to them the right to claim other damages, which were the direct consequences of plaintiffs’ broken contract in this particular.
From the evidence in their whole conduct, it is highly probable defendants’ business methods saved to plaintiffs more money than they saved for themselves. Appellants certainly have no grounds for complaint. There is nothing of merit in the other assignment of error.
The judgment is affirmed.