106 Mich. 414 | Mich. | 1895
This action was brought t-o recover for a balance claimed to be due for constructing a sewer in Woodward avenue in the city of Detroit. There was a written contract between the parties, executed on behalf of the city by the board of public works. On the trial the two questions presented were — First, whether, under the contract, the plaintiff was entitled to recover the price per foot stipulated, as determined by measuring each cylinder as a separate sewer, or whether he was limited to the number of lineal feet of the entire substructure; and, second, whether the plaintiff was entitled to recover -extra compensation for the reason that t7ieconstruction of the sewer was made more expensive by a variation from the line marked on the plan. The circuit judge held in favor of the plaintiff on the first proposition, but held that he was not entitled to recover for bxtra work. Both parties appeal.
1. The first question is to be determined by a construction of the contract. The agreement on the part of the plaiutiff, as expressed in the contract, wa,-s “to build and finish complete, together with the back filling, according to the plans on file in the board of public works office and the specifications hereto attached, Woodward avenue dock, outlet, and sewer, from river -to north line of State street. * * * The said construction shall, in all respects, be in accordance with the plan of said sewer on file in the office of said board.” The city undertook to pay “'for furnishing all the labor and material, except water-lime, and building and finishing complete, together with the back filling, according to the plans; * * * Woodward avenue dock, outlet, and’ sewer, from river to north line of State street, the sum of
( Length of sewer and dock, 2,568 feet.
Sewer \ Size “ “ 2-6' 8" cyls., 2 R. C. B.
( “ “ “ 9' 0"cyl., 3 R. C. B.
The letters “R. C. B.” mean “rings of common brick.” The distance named is the single length of the Ime of sewer. We are all of the opinion that this contract should be construed as providing for the payment of $14.49 per lineal foot, and that it is not open to the construction that each cylinder was to be treated as a distinct sewer. The word “sewer” is used throughout to indicate the structure in all its parts, consisting of a single cylinder where but one is used, and including both cylinders where two are used, and, in either case, the masonwork, cement, etc., shown in the transverse section on the plan.
2. The plan upon which the bid was based indicated the course of the sewer, and, while the distance from the curb is mot marked in figures, it is claimed that the line which plaintiff attempted to build was in accordance with the plan. After he commenced work, the superintendent directed him to construct the sewer nearer the center of the street. The plaintiff protested, but did as directed, and subsequently served notice on the board of public works, stating that he would hold the city liable for the increased cost and damage resulting from the change. There was evidence that by reason of the change he came in contact with an old sewer for a portion of the distance, and additional expense was incurred by reason of this, amounting to about $4,000.
By the city charter, no contract can be made for any public work unless it (the contract) shall have been ap
“The law holds those dealing with a municipal corporation to a knowledge of the extent of the authority conferred, and of the mode of its exercise, and of all illegalities committed by its agents in not pursuing the authority in the manner pointed out.”
In this case the plaintiff had but one contract with the city, and that was the one awarded to him after competitive bidding. If the demand of the superintendent was not justified by the contract, he had the right to
Dut it is urged that the contract in this case provides • for changes and extras. Plaintiff’s counsel say:
“We do not contend that the plaintiff is entitled to recover damages for not being allowed to perform his contract according to its terms, or that the city is liable upon an implied contract arising from the doing and acceptance of work not contemplated by the contract. It is our claim that, under the terms of the contract and specifications, the line of the sewer might be changed, subject to the obligation to make fair compensation for extra work caused by thé change, and that the plaintiff was hound ho follow the line given him, although it departed from that laid down upon the plans.”
The provisions of the contract which are thought to sustain this contention will be separately considered. The first provision relied upon is: “The work embraced in this contract shall be prosecuted in such order, and at such places and parts of the work, as the said board may direct.” It is clear that this provision relates to the order of the work, and the places referred to are the places provided for by the contract.
The second provision referred to is contained in the specifications, and reads: “The excavations to be made to the depths shown on profile and plans on file in the
The third provision is: “Any work connected with the construction of said sewer which may be required to be done, but which is not specified herein, shall be performed .in accordance with the directions of said'board, and shall be paid for at their valuation.” If it be assumed that this provision is lawful, under the charter, it does not authorize a departure from the specifications. There is no pretense that the work done was not specified, but the claim is that it was made more expensive by a deviation from the course specified.
The only remaining provision is: “The said contractor hereby agrees that he will perform this contract as specified, but will make any alterations in the form, dimensions, or materials which may be directed in writing by the said board of public works.” This provision certainly does not authorize a change in the course or direction of the sewer.
None of these provisions, taken separately, nor all of them, read together, authorize any substantial change in the plans and specifications as to the course or location of the sewer. It is unnecessary to consider to what extent these provisions of the contract conflict with the charter provisions, as none of them sustain plaintiff’s claim. Nor is it necessary to consider the effect of a provision of the contract which makes the decision of the board final as to every question relating to the execution of the contract, as to which see Rens v. City of Grand Rapids, 73 Mich. 237. For the reason stated, we think the circuit judge was right in holding that the city was not liable on this branch of the case.
For the error committed on the first branch of the case, the judgment will be reversed, with costs of both courts, and no new trial ordered.
Act No. 393, Laws of 1873.