339 Mass. 231 | Mass. | 1959
This is a petition under G. L. c. 258 for compensation alleged to be due from the Commonwealth for extra work done by the petitioner under a contract of August 11, 1953, for the construction of a section of highway at the intersection of Routes 3 and 128 in Burlington.
The judge found for the respondent and filed a “report of material facts,” expressly stated to be a report of all the
The petitioner filed and was heard on a motion for a new trial on the grounds that the finding was against the weight of the evidence and constituted a mistake of law, and claimed an exception to the denial of the motion. Three days after this motion had been denied the judge allowed the petitioner to file, and the judge denied subject to the petitioner’s exception, the request for a ruling that a “finding for the respondent is not warranted on the law and evidence of this case.” Two evidential questions are also presented by the bill of exceptions.
1. Where the basis for a general finding or decision is not in dispute an exception thereto suffices to raise the question of law whether it was warranted. Leshefsky v. American Employers’ Ins. Co. 293 Mass. 164, 166-167. Barton v. Cambridge, 318 Mass. 420, 424. Employers Mut. Liab. Ins. Co. v. Merrimac Mills Co. 325 Mass. 676, 678, n. 2. Contrast Graustein v. Boston & Maine R.R. 317 Mass. 164, 166-168.
We assume that the belated request for a ruling was received in connection with the motion for a new trial. So received, it could have been denied on the ground that it presented a question of law which was or could have been raised at the trial. Haines Corp. v. Winthrop Square Cafe, Inc. 335 Mass. 152, 154. We think, however, that the action of the judge in allowing it to be filed, and denying it without specification of ground, shows an intent that the petitioner have the right of review of the issue stated.
We rule that the exception to the voluntary report was an exception to the general finding and decision for the respondent and that it brings here the question of the correctness of the decision on the facts which the judge found, and stated were the basis for his conclusion, and on the subsidiary rulings; and that the denial of the request for a ruling raises the issue of the sufficiency of the evidence to support the finding for the respondent. We do not intimate that,
The statute, G. L. c. 231, § 129, gives but two grounds for filing a motion for a new trial as of right; mistake of law and newly discovered evidence. Therefore, no question is presented by the exception to the denial of the motion on the ground that the finding was against the weight of the evidence. Scano, petitioner, 338 Mass. 7, 8-9.
2. To judge the correctness of the finding for the respondent on stated facts we must accept those facts as the judge has found them. We do not for this purpose refer to the evidence summarized in the bill of exceptions.
The report finds as follows: This petitioner had a contract with the Commonwealth for the construction of about a mile of new Route 3, and the issue relates to an area in the southwest quadrant of the clover leaf where Route 3 crosses Route 128. The cross section plan applicable to the quadrant called for the removal of all material therein. The resident engineer “having such authority as is granted by the chief engineer under the . . . specifications” staked out the quadrant in such a way as not to require the removal of the ledge, and to leave an “island” of rock between access ramps.
We think that, on these facts, it was error to rule that the staking out of the area to leave the island unexcavated was not “an act of omission or commission” by an agent of the Commonwealth. The report implies a finding that the
There is an implied ruling that if this is the proper construction of article 58 the petitioner is entitled to its additional expenses. The findings that “$5,000 would be more than adequate compensation ” and that “¡T]he only additional expense I find not to exceed $5,000 as above set forth,” are subject to the construction that the judge in making them acted on evidence and, where he found it uncertain, made maximum allowance for the petitioner.
There is no basis for claim of error in the other rulings of the judge underlying the finding for the respondent.
3. The denial of the request to rule directs our attention to the evidence, but only to determine if on the evidence a finding for the Commonwealth was warranted. We think it was not in the respect already indicated. Article 1 of the specifications defines “engineer” as “The chief engineer of the department acting directly or through an authorized representative, such representative acting within the scope of the particular duties entrusted to him.” The chief engineer testified that the resident engineer works under the supervision of the district highway engineer and that the resident engineer is an authorized representative of the chief engineer on the job site. Article 28 provides that “[t]he engineer shall . . . decide all questions which may arise as to the interpretation of any part of the contract, especially the plans and specifications which are a part thereof, as to the fulfillment of this contract on the part of the contractor, and the determination and decision of the engineer shall be final and conclusive . . ..” We think that “engineer,” as used in article 28, was, on the chief engineer’s testimony, inclusive of “resident engineer.” See M. DeMatteo Constr. Co. v. Commonwealth, 338 Mass. 568, 577, n. Article 35, which provides that “[t]he engineer may appoint . . . assistants and representatives” and that “assistants are not authorized ... to issue instructions contrary to the plans and specifications,” does not appear to restrict the authority of the resident engineer as an “authorized representative of the chief engineer on the job site.”
It does not follow that a new trial must be had because of the erroneous denial of the request to rule that a finding for the respondent was not warranted. No more is required in the way of new proceedings than is necessary to correct the error. On the record the error will be corrected by the entry of judgment for the petitioner as stated in point 2. But the petitioner is entitled to have the judge decide the issues raised by the motion for a new trial, and exercise his discretion in respect thereto, in the light of the correct ruling on the request. The order denying the motion for a new trial must be vacated and the case is to stand subject to determination in the Superior Court of the extent, if any, to which further findings should be had, with or without the taking of evidence, in order that the petitioner have the recovery shown due by the rulings of the judge, as modified by our ruling, as applied to proved facts.
4. We see nothing in the evidential exceptions. In any event they related to evidence bearing on the issue on which we have ruled for the petitioner.
5. The entry is to be: exceptions sustained; further proceedings in accord with this opinión.
So ordered.
The evidence shows a possible basis for an interpretation in that the cross section plan showed the grades of the resulting slopes to be those specified for earth banks, and the “typical section” for rock excavation showed a steeper slope grade. It is stated in the bill that a change in staldng was made by the resident engineer after rock was discovered.
The bill of exceptions, in stating evidence, not at this point relevant, states that there was conflicting evidence on the question of damages, and that “Witnesses for the petitioner originally claimed damage in varying amounts of $122,500 and $106,281.63. Later it was developed that a breakdown of damages submitted to the Commonwealth by the petitioner was in the amount of $72,559.77. Neither of the above figures credited the Commonwealth of Massachusetts with $23,790 actually paid by the Commonwealth for the removal of this disputed material at the contract price of 78 cents per cubic yard.” It does not appear that there was no other evidence on damage, and the statement that the bill contains all the evidence material to the issues raised by it is not conclusive because the only aspect of damage relevant to the denial of the request for a ruling was whether there was any evidence of damage.
In view of this statement we do not reach the issue of the effect of the provision in article 58 reading: “All claims ... for compensation ... on account of any act of omission or commission . . . must be made in writing to the engineer .... The determination of the engineer shall be final upon all questions as to the amount and value of such work, and the fact and extent of such damage.” See G. L. Rugo & Sons, Inc. v. Lexington, 338 Mass. 746; 749-751.