119 N.Y.S. 128 | N.Y. App. Div. | 1909
On the 1st day of April, 190o, the plaintiff entered into a contract with the city of Albany to furnish the material and labor
“ In addition to the ten years’ maintenance of the asphalt pavement, all the work herein provided for shall be kept in good condition and repair by the contractor, without notification from the city, for a period of two years from the date of its acceptance by the city, and in case the contractor neglects or refuses to repair the pavement, or other work herein specified, and to restore the same to the grade and to an even and true shape and form of surface, when the same shall be necessary, the Commissioner of Public Works shall have the right to cause said work to be done and charge the expense thereof to the contractor or his sureties ; and the City Treasurer will retain for the period of two years from the date of said acceptance five per cent of the amount due or to become due under the contract, and shall, by such contract, have the right to pay the expense of said repairs and restoration on the certificate of the Commissioner of Public Works out of the five per cent retained by him, or to collect such cost and expenses from such contractor or his sureties.” It was also agreed that the work and materials were to be in strict conformity in every particular with the plans and specifications which were made part of the contract.
This action is brought to recover among, other things five per cent of the amount due under the contract which, according to the provisions thereof above quoted was. retained in behalf of the
The learned referee found that the plaintiff failed to keep the work done in good condition and repair for the period of two years; that the commissioner of public works of the city of Albany caused the necessary repairs and restoration to be made*; that the expense thereof was $3,161.75 which was paid by the defendant, and that the amount due to the defendant after applying the amount retained was $669.96.
The judgment determines that the plaintiff is not entitled to recover the five per cent of its contract price expended by the city in restoring the pavement, and also charges the plaintiff with the additional amount of $669.96 expended by the defendant for that purpose in addition to said five per cent of the contract price retained by defendant.
The learned referee also found as a fact that the plaintiff “ performed the work and furnished the materials in accordance with the conditions thereof and performed all the conditions thereof on its part to be performed ; that during the time of the performance of said work the defendant inspected the materials furnished and the work performed, and on or about the 4th day of December, 1905, accepted the work in said contract mentioned as having been done in accordance therewith and the materials as having been furnished as provided for in said contract.” It also appears that the contract was prepared by' the city and the work was done under its superintendence and in full conformity with its plans and specifications.
The fact is that the city specified a defective plan and method of construction which, although fully and fairly executed, was insufficient to keep the pavement in repair, and the question for determination is whether the plaintiff can recover its contract price without repairing the pavement for two years after its acceptance by the city, although the plaintiff has in every respect complied with the plans and specifications adopted and required by the city.
In MacKnight Flintic Stone Co. v. Mayor (160 N. Y. 72) the plaintiff contracted to make a boiler room watertight in the manner and under the conditions prescribed in specifications provided by the
That case seems to be applicable here and if applicable a reversal of this judgment must follow. As indicated in that case if the plaintiff had executed a plan of its own resulting in a proper and sufficient pavement it would not have been a performance of its contract because it was bound hand and foot to the plan of the defendant. It had no discretion as to the material to be used or the manner in which the work should be done. It was an impossibility for the defendant to construct the pavement according to the terms of the contract and at the same time produce such a pavement as the defendant required. The reasonable interpretation of the contract, therefore, is that plaintiff was not to keep the pavement in repair as against the defective plan provided by defendant.
The case cited also disposes of the contention that the certificate
The judgment should be reversed on the law and facts, the referee discharged and a new trial granted, with costs to the appellant to abide the event.
All concurred, except Smith, P. J., and Sewell, J., dissenting.
Judgment reversed on law and facts, referee discharged and new trial granted, with costs to appellant to abide event.