Cameron & Barkley Co. v. American InsuranceCameron & Barkley Co. v. American Insurance
Plaintiff appeals an order granting summary judgment to defendants Blaine Hays Construction Company (Blaine Hays) and Marriott Corporation (Marriott) and denying its own motion for summary judgment. Plaintiff contends the trial court erred by ruling the “Claim of Lien and Notice of Claim of Lien” filed and served by plaintiff failed to comply with the notiсe requirements established in Article 2 of Chapter 44A of the North Carolina General Statutes, specifically those designated in
In particular, plaintiff, a second tier subcontractor, questions the court’s reading of the applicable sections of the statutory scheme. It asserts the notice requirements for the type of lien involved herein are controlled by
Pertinent facts include the following: in June 1987, Blaine Hays entered into a contract with Marriott for the construction of a Courtyard motel on a tract of real property owned by Marriott and located in Cary, North Carolina. In its capacity as general contractor for the project, Blaine Hays contracted out cеrtain electrical work to a first tier subcontractor, Roper Electric Contractors, Inc. (Roper). Roper ordered from plaintiff electrical supplies and materials to be incorporated into the Courtyard project.
Plaintiff allegedly delivered, pursuant to its agreement with Roрer, $63,919.78 worth of supplies and materials to the Courtyard construction site between 28 September 1987 and 5 January 1988. Roper subsequently abandoned work on the project, failed to compensate plaintiff, and filed for bankruptcy on 24 February 1988.
On 26 February 1988 plaintiff filed with the Wake County Clerk of Superior Court a dоcument entitled “Claim of Lien and Notice of Claim of Lien” against the real property owned by Marriott, and served copies on Marriott, Blaine Hays, and Roper. Plaintiff thereafter sought to enforce its purported lien by filing a complaint on 17 May 1988, setting forth claims based on a lien on any funds owed by Blaine Hays to Roper, pursuant to
Defendants denied liability in their jointly-filed answer. On 1 November 1989, Blaine Hays filed a surety bond in the amount of $79,899.73, conditioning payment upon a finding the purported lien was properly noticed and perfected. Plaintiff and defendants filed cross-motions for summary judgment, and a hearing was held on 12 November 1991. The court issued a memorandum of decision, *39 memorialized by order dated 3 February 1992, which denied plaintiff’s motion and granted that of defendants.
The court’s order reasoned the document filed by plaintiff did not comply with the notice requirements of G.S.
I.
Plaintiff first maintains the trial court committed reversible error by granting defendants’ motion for summary judgment pursuant to Rule 56 of the North Carolina Rules of Civil Procedure. Summary judgment is designed to “ferret out those cases in which there is no genuine issue as to any material fact and in which, upon such undisputed facts, a party is entitled to judgment as a matter of law.”
Haithcock v. Chimney Rock Co.,
In support of its motion below, defendants argued plaintiff’s lien was improperly noticed, was thus not perfected, and therefore plaintiff could not bring an action against defendants seeking enforcement of the alleged lien. The court agreed with defendants, stating in its order:
The claim of lien and nоtice of claim of lien filed and served by plaintiff fail to comply with the provisions of Chapter 44A . . . regarding liens by subrogation. Plaintiff failed to give proper notice of its claim of lien, in accordance with Article 2 of Chapter 44A, as required by . . . 44A-23. That being the case, plaintiff’s lien perfection action must fail as a matter of law.
A claim of lien must be properly noticed and properly filed, in order for the underlying lien to be perfected. If a lien is not per
*40
fected, it cannot be enforced.
Strickland v. General Bldg. & Masonry Contractors, Inc.,
We note G.S.
A . . . second . . . tier subcontractor, who gives notice as provided in this Article, may, to the extent of his claim, enforce the lien of the contractor created by Part 1 of Article 2 of this Chapter. The manner of such enforcement shall be as provided by G.S. 44A-7 through 44A-16. The lien is perfected as of the time set forth in G.S. 44A-10 upon filing of claim of lien pursuant to G.S. 44A-12. Upon the filing of the notice and claim of lien and the commencement of the action, no action of the contractor shall be effective to prejudice the rights of the subcontractor without his written consent.
G.S.
Plaintiff insists the notice requirements set out in G.S.
Assuming
arguendo
that plaintiffs “Claim of Lien and Notice of Claim of Lien” is in substantial compliance with the form specified in G.S.
The italicized words in G.S.
(a) Notice of a claim of lien shall set forth:
(1) The name and address of the person claiming the lien,
(2) A general description of the real property improved,
(3) The name and address of the person with whom the lien claimant contracted to improvе real property,
(4) The name and address of each person against or through whom subrogation rights are claimed,
(5) A general description of the contract and the person against whose interest the lien is claimed, and
(6) The amount claimed by the lien claimant under his contract.
(b) All notices of claims of liens by first, second or third tier subcontractors must be given using a form substantially as follows:
NOTICE OF CLAIM OF LIEN BY FIRST, SECOND OR THIRD TIER SUBCONTRACTOR
To:
1 .owner of property involved.
(Name and address)
2., general contractor.
(Name and address)
3., first tier subcontractor against
(Name and address) or through whom subrogation is claimed, if any.
*42 4.. second tier subcontractor
(Name and address) against or through whom subrogation is claimed, if any.
General description of real property where labor performed or material furnished:
General description of undersigned lien claimant’s contract including the names of the parties thereto: .
The amount of lien claimed pursuant to the above described contract: $ .
The undersigned lien claimant gives this notice of claim of lien pursuant to North Carolina law and claims all rights of subrogation to which he is entitled under Pаrt 2 of Article 2 of Chapter 44A of the General Statutes of North Carolina.
Dated .
., Lien Claimant
(Address)
G.S.
Under this statute, therefore, in order to provide proper notice to the owner of the property, it is mandatory that a claimant set forth with specificity the information required by each part of subsection (a) abovе listed. Moreover, in so doing, there must be substantial compliance with the given statutory form.
Contract Steel Sales, Inc. v. Freedom Construction Co.,
We now contrast the precise language of the “Claim of Lien and Notice of Claim of Lien” filed by plaintiff with the wording of the form included within G.S.
*43 CLAIM OF LIEN AND NOTICE OF CLAIM OF LIEN
NOW COMES Cameron & Barkley Company and provides the following Notice of Claim of Lien.
1. Name and address of the person- claiming the lien:
Cameron & Barkley Comрany, 2864 Azalea Dr., Box 10067, Charleston, SC 29411.
2. Name and address of the record owner of the real property claimed to be subject to the lien at the time the claim of lien is filed:
Marriott Corporation, Marriott Drive, Washington, D.C. 20058
3. Name and address of the general contractor or subcontractor agаinst or through whom subrogation is claimed, if any:
Roper Electrical Company, P.O. Box 5662, Sta B, Greenville, SC 29605
4. Description of the real property upon which the lien is claimed:
Courtyard by Mariott [sic], 102 Edinburgh, South, Cary, NC 27511
5. Description of the lien claimant’s contract including the names of the parties thereto:
Cameron & Barkley cоntracted with Roper Electrical Co. to provide electrical equipment to be used for the improvement of real property described above.
6. Name and address of the person with whom the claimant contracted for the furnishing of labor or materials:
Roper Electrical Cоmpany, P.O. Box 5662, Sta B, Greenville, SC 29605
7. Date upon which labor or materials were first furnished upon said property by the claimant:
*44 Electrical supplies and materials were first furnished by Cameron & Barkley on September 28, 1987.
8. Date upon which labor or materials were last furnished upon said property by the claimant:
Electrical supplies and materials were last furnished by Cameron & Barkley on January 5, 1988.
9. General description of the labor performed or materials furnished:
Electrical supplies and materials
10.Amount claimed by lien claimant:
$63,919.78.
This the 23 day of February, 1988.
With respect to liens against real property by way of subrogation to the lien rights of the general contractor, “substantial compliance” with the statutory form requires more than plаintiff has provided herein. This is particularly so because the form is replete with references to the fact a
subcontractor
is claiming a
lien by way of subrogation.
We hold plaintiff’s notice of claim of lien is inadequate to convey the notice required by G.S.
Preliminarily, plaintiff’s “Notice” is not titled in a manner which makes it unmistakable from the outset the lien is being claimed by way of subrogation, or by a subcontractor. Instead it reads: “CLAIM OF LIEN AND NOTICE OF CLAIM OF LIEN.”
Next, plaintiff never names Blaine Hays. G.S.
*45
The form provided in G.S.
We recognize plaintiff designedly attempted to conform to the provisions of G.S.
Although a second tier subcontractor must
notice
its claim of lien using a format substantially similar to that provided in G.S.
(a) Place of Filing. — All claims of lien against any real property must be filed in the office of the clerk of superior court in each county wherein the real property subject to the claim of lien is located. . . .
(b) Time of Filing. — Claims of lien may be filed at any time after the maturity of the obligation secured thereby but not later than 120 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the lien.
G.S.
Plaintiff filed its instrument at the place and within the time-frame indicated. However, as we have determined the notice provided by plaintiff was ineffective, the claimed lien was not perfected, and the action brought by plaintiff seeking its enforcement was fatally flawed. No genuine issue of material fact remained for trial, and the court properly ruled defendants were entitled to summary judgment as a matter of law.
II.
Plaintiff contends in its second assignment of error the trial court reversibly erred by not granting plaintiff’s own motion for summary judgment, or, in the alternative, partial summary judgment. We need not address this contention, however, because our holding the court properly granted summary judgment in favor of defendants renders moot plaintiff’s second assignment of error.
The order of the trial court is affirmed.