This is an action by a subcontractor against a surety for payment pursuant to a private labor and materiаls payment bond. On April 8, 1973, Priestly Contracting, Inc., the general contractor for a private construction prоject, and defendant surety signed the bond in question. Priestly Contracting thereafter subcontracted work to plaintiff. However, Priestly Contracting permanently ceased work on the construction project in April, 1974, leaving sums still owing tо plaintiff.
Plaintiff filed a complaint against defendant surety on August 26, 1976. 1 Defendant filed a motion for accelerаted judgment, alleging that plaintiff’s claim was time barred by the following provision of the bond:
*221 "No suit or action shall be commenced hereunder by any claimant:
* * *
"After the expiration of one (1) year following the date on which Principal ceased work on said Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to bе equal to the minimum period of limitation permitted by such law.”
The trial court ruled that the language of the above provision was ambiguous, and that it could be construed to require interpolation of the general statutory six-yеar period of limitations for contract actions. 2 MCL 600.5807(8); MSA 27A.5807(8),MCL 600.5813; MSA 27A.5813. Commenting further that shorter limitations on contractual actions are not to be favorably regarded, the trial court denied defendant’s motion. Plaintiff was ultimately granted summary judgment under GCR 1963, 117.2(3) on its claim for payment pursuant to the bond. Defendant appeals from both dispositions.
We сonclude that the trial court erred in ruling that the wording of the disputed contractual limitation clause is ambiguous. On thе contrary, the bond clearly provides that suits thereunder must be brought within one year of the date on which the principal ceases work on the project covered, unless the controlling state law prohibits such a contractual limitation on suits pursuant to a private construction bond. Michigan statutory law contains no such exprеss prohibition. 3
Furthermore, Michigan precedent has condoned
*222
such contractual limitations on claims against private sureties, holding them to be valid, enforceable, and in accord with public policy. As the Michigan Supreme Court stated in
Commissioner of Insurance v Central West Casualty Co,
"A statutory bond is one commanded or provided by statute. In such a bond, the existing law becomes a part of the bond, omitted conditions required by law are read into the bond and conditions contrary to the law are read out of it. The doctrine of 'what is оmitted will be read in and what is in conflict will be read out’ applies only to bonds required by statute. In such a bond the general statute of limitations becomes a part of the bond. In a common-law bond the parties may provide for a shorter time for bringing suit than is provided by the statute of limitations and, in general, are bound by their agreement. ” (Emphasis supplied.)
Forest Twp v American Bonding Co of Baltimore,
Thus, unless defendant is for some reason estop *223 ped from asserting the one-year limitation on plaintiffs suit рursuant to the bond or unless plaintiff can show that Priestly Contracting did not cease work on the project in April, 1974, plaintiffs claim is time barred.
But plaintiff insists that a distinction must be made between the immediate parties to a contrаct, who should be bound by any limiting contractual provisions to which they agreed, and third parties seeking recovery under the surety contract, against whom it would be unreasonable to enforce the contractual limitation. 6 We find the distinction unpersuasive in the context of this private construction bond. There is nothing unreasonable аbout requiring a subcontractor to investigate its right to payment within one year after the general contractor has abandoned the project. It would furthermore be totally incongruous to hold that plaintiff herein has six years within which to commence suit on a private bond, when other claimants must by statute press their suits pursuant to a rеquired public bond within one year of the completion and acceptance of a public works рroject. MCL 570.104; MSA 26.324.
The trial court erred in holding that the contractual limitation on bringing suit pursuant to the bond was ambiguous, and in granting plaintiff’s motion for summary judgment on the grounds of that erroneous ruling.
Reversed and remanded for proceedings nоt inconsistent with this opinion.
Notes
Plaintiff also filed a suit for payment against the general contractor, and obtainеd a default judgment for $18,848 with costs and interest on July 6,1977, which has not been paid.
See 21 Michigan Law & Practice, Suretyship, § 44, p 230.
By contrast, MCL 570.104; MSA 26.324 specifically provides that a suit pursuant to a public works bond must be brought within one year after the completion and acceptаnce of the project.
Accord, e.g., Gossen v Indemnity Ins Co of North America, 234 F2d 463 (CA 6, 1956); 12 Am Jur 2d, Bonds, § 37, p 503.
The trial judge recognized that a private surety may limit its contractual liability to сlaimants to a period shorter than the otherwise applicable statute of limitations, but concluded that such foreshortening of liability was to be unfavorably viewed. The cited Michigan cases do not support this conclusion. If the parties to a private surety or insurance contract clearly agree to a time rеstriction on the commencement of actions, the courts generally enforce it without reluctancе.
To this end, plaintiff also asks us to examine precedent from other states. However, as one of the cases relied upon by plaintiff concludes:
"The cases from other states are in hopeless conflict. Some hold that such contractual provisions are binding on the insured third person, while others hold that they are not. Some of them turn upon the wording of particular statutes or policies. No useful purpose would be served by citing or discussing these cases.” Olds v General Accident Fire & Life Assurance Corp, 67 Cal App 2d 812;155 P2d 676 , 683 (1945).
