67 W. Va. 525 | W. Va. | 1910
The Town of New Martinsville, a municipal corporation., on June 11, 1902, entered into a contract with O. Skidmore for the paving'of particularly named streets. For doing the work in the manner specified, Skidmore was to receive stated prices for the curbing, excess excavating, and brick paving necessary to. complete the contract. The work was to be completed by November first, of that year. Payments were to be made to Skid-more every thirty days, upon estimates of eighty per cent, of the work completed. Final payment was to be made at the completion of all the work and its acceptance. Just here it may 'be observed that the contract was to be performed and the work paid for during the current municipal fiscal year of 1902 within which it was made. The contract does not relate to future j'ears, nor does it pretend to bind future levies for its payment.
Though many -exceptions were presented in the original assignments of error, the brief of counsel for the town relies upon but two points. The neglected assignments, however, have been considered by us. Finding them not well taken, we overrule them. This written opinion may well be devoted to the two points raised in the brief.
Two special pleas were interposed by the defendant .town. One of the pleas alleged a breach of the contract by Skidmore and averred that defendant was damaged by that breach to the amount claimed by plaintiff. The other plea denied the validity of the contract upon the averment that the town undertook to incur an indebtedness payable out of revenues for years other than the one as to which the contract was made. Plaintiff demurred to each plea, but the court overruled the demurrers. Then plaintiff replied generally to each plea. Issues were thus joined, without objection on the part of defendant. Now, defendant insists that when plaintiff failed in the demurrers to the pleas the issues presented by the pleas were thereby finally settled against plaintiff. In other words, it is submitted that plaintiff could not reply to the pleas after the demurrers thereto were overruled unless the demurrers were withdrawn. True it is that at the common law the plaintiff could give one answer, either of law or of fact, but no more, to each plea. 4 Minor’s Inst. (3d Ed.) 1167. This common law rule is changed by our statute only in one particular. More than one answer in pomr of fact to a special plea is now allowed — more than one replica
The court instructed the jury that the evidence was insufficient to justify a finding that the contract' was an illegal and invalid one. 'This instruction-was a proper one in the premises. Defendant did not prove that at the time the town entered into the contract it thereby assumed an indebtedness which, with other liabilities then existing or assumed, overreached the dependable resources of the municipality for the current year.
The- only issue of fact submitted for the determination of the jury related to the alleged breach of the contract by Skid-more — to his failure to do the work contemplated by it in the manner stipulated. That issue the jury, on conflicting facts and circumstances, determined in favor of plaintiff. Their finding is warranted by the evidence. Nothing appears by which we can overthrow it.
The record plainly calls for an affirmance of the judgment. It will be so ordered.
Affirmed.