MEMORANDUM
Presently before the Court are the motions of defendants Aetna Casualty
I. BACKGROUND 2
Cain Village Associates is the owner of the Cain Village Shopping Center. Cain Village Associates is owned, inter alia, by Hough-Loew Associates, Inc., George Goldstone and Jack Loew. Hough-Loew Associates, Inc. is also the general partner of Cain Village Associates. (Appendix in Support of Defendant, American Insurance Company’s Motion for Summary Judgement (“Fireman’s Fund App.”), Tab 3 at 12, & Tab 4 at 37). Herbert Yentis and Company (“HYC”) is the managing agent of the Cain Village Shopping Center. Charles Ambrose has been the vice president of HYC since 1991 and was responsible for the day to day inspection of the Cain Village Shopping Center.
Construction of the Cain Village Shopping Center began in the latter half of 1990 and was substantially completed in September, 1991. Hough-Loew Construction, Inc., (“Hough-Loew”) was the general contractor. Hough-Loew in turn is owned by Jack Loew. (Fireman’s Fund App., Tab 4 at 37). HYC rented the stores and tenants moved into the stores in late September, 1991.
The shopping center has twenty-two inline stores which are divided into three sections and four individual stores. The center section contains stores D through K. Cain Village asserts that those eight stores (D-K) suffered damage for which it is entitled to insurance coverage. Specifically, Cain Village claims that the general contractor’s use of un-cured slag during construction has resulted in ongoing and progressive damage to the stores. Because the slag was un-cured, Cain Village contends that it has swelled and as a result the concrete floors in each of the stores (D-K) has risen which in turn has caused damage to the floors, doorways, walls, ceilings and fixtures.
The record is replete with internal memos and letters to and from Cain Village representatives complaining about damage to the stores at the shopping center. The complaints range from small things that need fixing (weather stripping, toilet seats and sticking doors) to water problems caused by driving rain entering the through doors to the rear of the stores and cracks in the walls and floors. Complaints about settlement cracks were a consistent theme, beginning in 1992. (See Fireman’s Fund App., Tabs 13-32). The record indicates that on January 8, 1992, Ambrose reported to a Hough-Loew representative that there was a “severe settlement crack” in unit E. (Id. at Tab 13). The crack was approximately 20 feet long which had run completely through a four inch concrete slab. (Goldstone Dep. at 125). Settlement problems were again reported on August 7, 1992. (Fireman’s Fund App. at Tab 17). A January 8, 1993, memo queries whether Hough-Loew has resolved the floor cracking problem yet.
(Id.
at Tab 19). On January 15, 1993,-Ambrose called Hough-Loew about a crack in the wall through
On September 21, 1993, Mr. Goldstone, a part-owner of HYC, wrote to Hough-Loew with concerns about the continuing settlement problem. “We have a serious problem, with the settlement condition, which is continuing along the fronts of the stores in the D through K units.” (Id. at Tab 8, Exh. H (emphasis in original)). Goldstone explained that the settling caused the window sills to move down and, as a result, Cain Village expected to experience problems with glass breakage or leakage. He also linked the sticking of doors to the falling of the thresholds and settlement of door jams. Finally, he explains that the flash patching and new tiles which apparently had been provided by Hough-Loew only provided a temporary solution. 3 (Id.).
During the Spring of 1994, the “settling problem” began causing cracks to appear not just in the floors but also the walls. (Fireman’s Fund App. at Tab 30). On June 9,1994, Ambrose reported to Hough-Loew that the brick facade of one of the stores was separating from the walls around the window and door areas. (Id. at Tabs 32). Also, in one of the stores the sink was separating from the wall. (Id.).
By July 27, 1994, Hough-Loew had identified the cause of the “problem” at the Cain Village Shopping Center. An internal memo attributes the “problem” to expansive fill beneath the floor slabs. (Id. at Tab 33). According to the memo, the uncured slag was drawing in moisture and changing chemically which can cause uncured slag to expand up to 10% of its volume. (Id.). Although the memo stated that it is “impossible to determine” how long the expansion process takes, it also stated that it is possible to determine, by means of core drilling and x-ray diffraction analysis, if the chemical reaction is complete. (Id.).
On July 28, 1994, Mr. Thompson, President of Hough-Loew, wrote to Jack Loew, a principle in Cain Village, stating:
I spoke with Dave Davis regarding the apparent expansive slag problem at Cain Village. He did not see the necessity of getting an expert in at this time. He did however feel that it was extremely important to put the various subcontractors and insurance company [sic] on notice of the problem.
He also felt it was very important to level (no pun intended) with Yentis as to the problem and probable cause. To this end, I wrote you the attached memo with may be suitable to forward to them.
(Id. at Tab 34). Attached to the letter from Thompson was the July 27, 1994, memo in which Hough-Loew states that the damage at Cain Village is consistent with expansive fill beneath the floor slab, resulting in cracked and raised door thresholds, drywall cracks and cracks in the rear, painted block wall. (Id. at Tab 33).
On August 3, 1994, Goldstone wrote to Jack Loew acknowledging receipt of the memorandum advising him that the cause of the problems at Cain Village was likely expanding un-cured slag.
(Id.
at Tab 35). In the letter, Goldstone also suggests that core samples should be taken to determine
In August of 1996, Cain Village sued Hough-Loew for breach of contract and negligence. (Id. at Tab 25). On September 5, 1996 Cain Village commenced this action against defendant Home. On November 11, 1996, Cain Village filed suit against defendants Aetna and Fireman’s Fund in state court. By agreement, Aetna and Fireman’s Fund were joined in this action.
The Aetna policies covered a period from October 19, 1991 through February 1, 1993. (PltApp. at Tabs 2 & 3). The Fireman’s Fund policies covered a period from May 26, 1993 through January 1, 1998. (Id. at Tabs 5-9). The Home policies covered the period of May 26, 1990 through May 26, 1991 (with an effective date of Oct. 17, 1990) and May 26, 1992, through May 26, 1993 (with an effective date of March 22, 1993). 4 (PltApp. at Tabs 1 & 4).
All three policies state that the insurer covers loss or damage “commencing during the policy period shown in the Declarations.” (See PltApp. at Tabs 42, 43, 44). All three policies also contain a suit limitation clause which states that no legal action may be brought unless the action is “brought within 2 years after the date on which the direct physical loss or damage occurred.” (Plt-App. at Tab 1, 2, 5).
II. LEGAL STANDARD
Defendants have moved pursuant to Federal Rule of Civil Procedure 56 for summary judgment. Under Federal Rule of Civil Procedure 56(c), summary judgment may be granted when, “after considering the record evidence in the light most favorable to the nonmoving party, no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law.”
Turner v. Schering-Plough Corp.,
III. DISCUSSION
The policies of all three defendants contain the same suit limitation clause. The clauses state, in pertinent part: “No one may bring a legal action against us under the Coverage Part unless ... [t]he action is brought within two years after the date on which the direct physical loss or damage occurred.” See (Plt.App. at Tabs ISIS). Defendants argue that the damage occurred prior to September 5, 1994 and, because this lawsuit was not commenced until September 5, 1996, this action is time barred. 5
Cain Village argues that the suit limitation clause is unreasonable and, therefore, unenforceable. Cain Village also argues that the defendants must meet a prejudice requirement before invoking a suit limitation clause. Cain Village further argues that the suit limitation language is ambiguous when applied to a ongoing and continuous loss or damage because there is no date on which the damage occurred and, therefore, the suit limitations clauses are either invalid or should be construed against the defendants. Finally, Cain Village argues that even if the clauses are valid, the discovery rule should apply to this case because the damage was not readily apparent. 6
It is well established in Pennsylvania that a contractual modification of the ordinary statute of limitations is valid and enforceable.
Lyons v. Nationwide Ins. Co.,
Provided that the insurer did not lead the insured to believe that the contractual limitation period would not be enforced, an insurer does not need to show prejudice to enforce a suit limitation provision.
Hosp. Support Sens. Ltd. v. Kemper Group, Inc.,
Cain Village next argues that the language contained in the suit limitation clause is ambiguous when applied to continuous loss or damage and, therefore, is invalid or should be construed against the insurer. In essence, Cain Village is arguing that because the damage is ongoing
The task before the Court then is to determine when the loss insured against occurred. In Pennsylvania, courts apply an “effects” analysis to determine when an occurrence happens.
D’Auria v. Zurich Ins. Co.,
Here, the undisputed evidence is that: cracks in the floor appeared almost immediately after the construction was complete; Cain Village has admitted that some of the physical damage manifested itself prior to January, 1992; the number and size of the cracks progressively increased; the rear wall began to separate from the building; the cracks and problems associated with the foundation moving were continual and became more pronounced with the passage of time; remedial efforts were unsuccessful; and finally, the Cain Village received a report suggesting that the problems were consistent with . expansive fill beneath the floor slabs and that it was impossible to determine how long the process would take. In hindsight, it appears from the
Moreover, contrary to the assertion of Cain Village' — that it did not know of the injury until after receiving an engineer’s report definitively attributing the problems to expanding un-cured slag- — it is un-controverted that there was a sufficient manifestation of the injury to satisfy the test of an occurrence prior to it receiving its expert report.
As
the
D'Auna
Court explained, it is not necessary to wait for the ultimate injury to become a certain proposition before the existence of the injury could be ascertained by reasonable diligence.
IV. CONCLUSION
Based upon the foregoing analysis, I will grant the motions. An appropriate Order follows.
ORDER
AND NOW this 23rd day of November, 1999, upon consideration of the motions for summary judgement of defendants, Aetna Casualty Company of Connecticut (Document No. 33), The Home Indemnity Company (Document No. 34), and The American Insurance Company of Fireman’s Fund (Document No. 35), and the response of plaintiff Cain Village Associates, L.P. (Document No. 40) and reply of defendants thereto, as well as the supporting memo-randa, pleadings, discovery record, exhibits and affidavits submitted by the parties, having found that there are no genuine issues of material fact and that the defendant is entitled to judgment as a matter of law, and for the reasons set forth in the foregoing memorandum, it is hereby ORDERED that the motions are GRANTED. Judgment is hereby entered in favor of the defendants, Aetna Casualty Company of Connecticut, The Home Indemnity Company, and The American Insurance Company of Fireman’s Fund and against plaintiff Cain Village Associates, L.P.
This is a final Order.
Notes
. The Court notes that jurisdiction is proper pursuant to 28 U.S.C. § 1332 as the parties are diverse and the amount in controversy exceeds $75,000.00, exclusive interest and costs. Also, it is undisputed that Pennsylvania law applies.
. The following facts are based on the evidence of record viewed in the light most favorable to plaintiff Cain Village, the nonmoving party, as required when considering a motion for summary judgment.
See Carnegie Mellon Univ. v. Schwartz,
. It appears that during this time Hough-Loew continued to address the various problems the shopping center was experiencing, both those obviously related to settling (by doing floor repairs, replacing tiles, flash patching etc.) as well as other repairs (insulating pipes, repairing drywall). (Aetna App. at Tab 8, Exh. V). Indeed, in a May 24, 1994 letter to Cain Village, a Hough-Loew representative explained that the crack in one of the stores was a result of a "cold joint” (when the concrete is poured at two separate times) and that, although there is movement in the floor it is minimal and does not require any type of repair. (Id. at Tab 8, Exh. N).
. Home inexplicably argues that the only insurance it provided was from February 1, 1993 through May 26, 1993. It strenuously reiterates this position in its reply brief, although it presumably had a copy of plaintiffs appendix containing, behind the first tab, a copy of an insurance policy issued by Home insuring the Cain Village Shopping Center between May 26, 1990 and May 26, 1991 (with an effective date of October 17, 1990). (See Plt.App. at Tab 1). In its brief, plaintiff asserts that another Home also insured the shopping center from October 19, 1991, through May 26, 1991. (Pit. Memorandum in Opposition to Defendant's Motion for Summary Judgment at 1-2 n.2). Plaintiff, however, has not included any verification that such a policy existed.
. Depending upon its circumstance, each defendant offers a variation on this theme. For instance, because suit was not brought against defendants Fireman's Fund and Aetna until November 11, 1996, it argues that the damage occurred prior to and certainly no later than November 11, 1994. Also, Aetna argues that because coverage ended on February 1, 1993, any action brought after February 1, 1995 is time barred (because it is only liable for damage that occurred during the policy period). While these differences are not insignificant, they do not change the result when assuming the latest date by which Cain Village could have brought suit under any of the policies at issue.
. The defendants also argue that the policies only provide coverage for "loss or damage commencing ... during the policy period” and that because the damage commenced pri- or to the policies at issue here, they are not liable. Specifically, Fireman's Fund argues that the damage commenced prior to May 26, 1993, when its policies first went into effect, Aetna argues that the damage commenced prior to October 19, 1991, when its policies first went into effect, and Home argues that the damage commenced prior to February 1, 1993, although there is a policy issued by Home insuring the property between May 26, 1990 and May 26, 1991 (with an effective date of October 17, 1990).
(See
Plt.App. at Tab 1). Cain Village, in turn, argues that the term "commencing” is ambiguous in the context of continuous and progressive damage and should be construed against the insurer.
See Kief Farmers Coop. Elevator Co. v. Farmland Mut. Ins. Co.,
.Cain Village argues that the applicable statute of limitations would be either six years (under the general statute of limitations clause, 42 Pa.Cons.Stat.Ann. § 5527) or twelve years (under the statute for actions seeking indemnity for construction deficiencies, 42 Pa.Cons.Stat.Ann. § 5536). Section 5536 applies to persons "performing or fur
. Moreover, even if I did find that the clause was ambiguous, I would not excise it from the policy. Suit limitations clauses do not run counter to the public policy of Pennsylvania.
See, e.g., Lyons,
. Cain Village notes that statute of limitations cases have little bearing on when an event occurs for purposes of insurance coverage.
See City of Erie, Pennsylvania v. Guaranty National Ins. Co.,
. As a general rule, a factual determination of when a reasonable person had would have discovered or had notice of an injury is usually for the jury.
See Cappelli v. York Operating Co., Inc.,
. Cain Village argues that in cases of continuing and ongoing progressive damage, the Court should apply the discovery rule. The discovery rule, when applied, operates to toll the statute of limitations until such time as the plaintiff discovers, or should have reasonably discovered the injury. The discovery rule generally "arises from the
inability
of the injured,
despite the exercise of due diligence,
to know of the injury or its cause.”
Pocono Int'l Racexvay, Inc. v. Pocono Produce,
