Opinion
Appellant California Clean Energy Committee (CCEC) appeals from a trial court’s judgment in favor of respondent City of San Jose (City). CCEC filed a petition for writ of mandate challenging City’s certification and approval of an environmental impact report (EIR) analyzing the potential environmental effects of a proposed update to City’s general plan, titled “Envision San Jose 2040 General Plan” (hereafter Envision San Jose), prepared pursuant to the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.). The trial court granted summary judgment in City’s favor, after finding that CCEC failed to exhaust its administrative remedies, as no administrative appeal was filed from City’s planning commission’s certification of the final EIR. 1
For the reasons set forth below, we find that the city council improperly delegated CEQA certification duties to the planning commission, and conclude CCEC adequately exhausted its administrative remedies. Accordingly, we reverse the judgment.
*1332 Factual and Procedural Background
City’s Approval of the Envision San Jose Plan
City made the EIR for the Envision San Jose plan available for public review on June 17, 2011. The Envision San Jose plan is a comprehensive update of City’s “Future San Jose 2020 General Plan,” adopted by the city council in 1994. As described by City, Envision San Jose is a “long-term plan that describes the amount, type and phasing of development needed to achieve the City’s social, economic, and environmental goals. [Envision San Jose] is the policy framework for decision making on both private development projects and City capital expenditures.” An EIR was prepared pursuant to CEQA, since the plan would have potentially significant environmental impacts on land use, transportation, noise, air quality, biological resources, aesthetics, population and housing growth, and greenhouse gas emissions. The public comment period on the EIR extended from June 17, 2011, to August 1, 2011.
On July 28, 2011, CCEC submitted a written comment letter in response to the draft EIR, criticizing the project and the draft EIR’s analysis with regard to certain environmental impacts, and also arguing that the draft EIR should be recirculated. The planning commission held a public hearing on the Envision San Jose final EIR on September 28, 2011. The draft EIR, along with a first amendment to the draft EIR, constituted the final EIR for the project. Notably, the notice of the public hearing prepared by the planning commission stated that the commission’s “action on rezoning, prezonings, General Plan Amendments and Code Amendments is only advisory to the City Council. The City Council will hold public hearings on these items.” Nonetheless, the action report from the meeting indicates that the commission members certified the final EIR for the Envision San Jose project as complete and in compliance with CEQA, and that the commission members further recommended approval of the project. The commission then issued resolution No. 11-059, where it declared the final EIR was completed in compliance with CEQA, that the final EIR reflected the independent judgment and analysis of City, and that the copies of the final EIR would be delivered to the decisionmaking body for the project.
CCEC then submitted a letter to City’s department of planning, building and code enforcement on October 31, 2011. The one-page letter included a request that the commission include in its administrative record a study prepared by StrongTowns.org, and included an encouragement that City reconsider the proposals made in the Envision San Jose plan. No appeal from the planning commission’s certification of the final EIR was filed, and the letter did not point to any specific deficiencies in the final EIR or the certification process.
*1333 The city council convened on November 1, 2011, and conducted a public hearing on the Envision San Jose plan. The city council’s minutes indicated it received the memorandum from the director of the department of planning, building and code enforcement transmitting the recommendations made by the planning commission. Public comments were made, and after a closed discussion, the city council approved the Envision San Jose plan and adopted resolution No. 76041.
Resolution No. 76041 in part stated that “prior to the adoption of this Resolution, the Planning Commission of the City of San Jose certified the [final EIR] prepared for the 2040 General Plan (also sometimes referred to herein as the ‘Project’) and found the [final EIR] was completed in accordance with the requirements of CEQA” and that “no appeal of the Planning Commission’s certification of the [final EIR] was filed with CITY as provided for under Title 21 of the San Jose Municipal Code.” In the resolution, the city council then certified the final EIR as in compliance with CEQA, and made the findings that it had independently reviewed and analyzed the final EIR prior to acting upon and approving the Envision San Jose plan. The resolution stated that the city council had “independently reviewed and analyzed” the final EIR and considered the comments and information contained therein, including the written and oral comments received at the public hearings on the final EIR. The city council issued resolution No. 76042 adopting the plan the same day. The minutes from the city council’s public hearing do not reflect that representatives from CCEC were present at the public hearing.
The Petition for Writ of Mandate
CCEC filed a petition for writ of mandate in the trial court on November 4, 2011, arguing that the approved final EIR fell below the standards set forth in CEQA, and that the EIR should have been recirculated as it contained significant changes from the draft EIR. City filed a motion for summary judgment on the basis that CCEC had failed to exhaust its administrative remedies as no one appealed the planning commission’s certification of the final EIR. After a hearing, the trial court issued an order on July 17, 2012, granting City’s motion for summary judgment. Judgment was entered in City’s favor on August 18, 2012. CCEC appealed.
Standard of Review
We review the trial court’s grant of summary judgment under a de novo standard of review.
(Monticello Ins. Co. v. Essex Ins. Co.
(2008)
We further apply a de novo standard of review to the question of whether the doctrine of exhaustion of administrative remedies applies in this case.
(Citizens for Open Government v. City of Lodi
(2006)
Discussion
The trial court never reached the merits of CCEC’s petition for writ of mandate, as it granted summary judgment on the ground that CCEC failed to exhaust its administrative remedies as required by Public Resources Code section 21177. Accordingly, on appeal CCEC argues the trial court erred on two grounds: (1) the exhaustion doctrine was satisfied because the city council, acting as the lead agency with the ultimate responsibility to approve or disapprove the final EIR and project, certified the final EIR with knowledge of CCEC’s objections, and (2) the planning commission’s certification of the final EIR was unlawful because the San Jose City Charter permits the planning commission only to make recommendations.
We address CCEC’s contentions in turn. First we address the lawfulness of the planning commission’s certification of the EIR, because if the EIR was not lawfully certified by the planning commission then no administrative appeal need be taken to exhaust administrative remedies. We conclude that the EIR was not properly certified by the planning commission, as the planning commission could not be delegated the duty to certify a final EIR given that it is not a decisionmaking body with respect to the Envision San Jose project. Second, we address CCEC’s argument that it exhausted its administrative remedies by filing its comment letters with the planning commission. We conclude that CCEC exhausted its administrative remedies with respect to the challenges to the sufficiency of the EIR and CCEC’s argument that the draft EIR should have been recirculated, as these points were adequately raised with the city council via CCEC’s comment letter.
*1335 1. The Planning Commission’s Certification of the Final EIR
Preliminarily, we briefly review the relevant provisions of CEQA, the CEQA guidelines, and the implementing San Jose Municipal Code sections that discuss EIR certification and delegation of duties under CEQA.
Overview of Appropriate Delegation of the EIR Certification Process
The CEQA guidelines (Cal. Code Regs., tit. 14, § 15000 et seq.) provide an outline of the procedures required to certify an EIR and to approve a project. Certain tasks may be delegated, but others may not. 2 The CEQA Guidelines specifically mandate that the decisionmaking body of a public agency shall not delegate the function of “[rjeviewing and considering a final EIR or approving a negative declaration prior to approving a project.” (CEQA Guidelines, § 15025, subd. (b)(1).) This guideline works in conjunction with the certification process for the final EIR. The CEQA Guidelines provide that prior to approval of a project, the lead agency must certify that (1) the final EIR complies with CEQA, (2) the final EIR was presented to the decisionmaking body of the lead agency and the decisionmaking body reviewed and considered the information in the final EIR prior to approving the project, and (3) the final EIR reflects the lead agency’s independent judgment and analysis. (Id., § 15090, subd. (a).)
However, this is not to say that delegation is improper in all circumstances. The lead agency may delegate certain duties under CEQA, such as the certification of the final EIR, as provided by Public Resources Code section 21151. Public Resources Code section 21151, subdivision (c), states that “[i]f a nonelected decisionmaking body of a local lead agency certifies an environmental impact report, approves a negative declaration or mitigated negative declaration, or determines that a project is not subject to this division, that certification, approval, or determination may be appealed to the agency’s elected decisionmaking body, if any.” The CEQA Guidelines appear to provide for a similar delegation power, as it specifies that “[w]hen an EIR is certified by a non-elected decision-making body within a local lead agency, that certification may be appealed to the local lead agency’s elected decision-making body, if one exists. For example, certification of an EIR for a tentative subdivision map by a city’s planning commission may be appealed to the city council. Each local lead agency shall provide for such appeals.” (CEQA Guidelines, § 15090, subd. (b).)
As shown from the CEQA Guidelines cited above, there are different duties and responsibilities assigned to lead agencies and decisionmaking *1336 bodies. The CEQA Guidelines define a “lead agency” as “the public agency which has the principal responsibility for carrying out or approving a project.” (CEQA Guidelines, § 15367.) In this instance, the lead agency would be City, acting through the city council, as it is the entity that has the principal responsibility for approving the Envision San Jose general plan. “The lead agency will decide whether an EIR or negative declaration will be required for the project and will cause the document to be prepared.” (Ibid.) A “decision-making body,” on the other hand, is defined as “any person or group of people within a public agency permitted by law to approve or disapprove the project at issue.” (Id., § 15356.) In accordance with these guidelines, the lead agency for a particular project could be a city council, and the decisionmaking body can be a nonelected body such as a planning commission, so long as the planning commission has the ability to approve or disapprove the project at issue.
The CEQA Guidelines therefore provide that a lead agency may delegate certification of the final EIR to a decisionmaking body, defined as a group of persons who have the ability to approve or disapprove a project. 3
The San Jose Municipal Code Ordinances
CEQA Guidelines section 15022 states that a public agency shall adopt procedures consistent with both CEQA and the guidelines in order to administer the agency’s responsibility for environmental review. This includes “[assigning responsibility for determining the adequacy of an EIR or negative declaration.” (CEQA Guidelines, § 15022, subd. (a)(8).) City has enacted municipal code ordinances in order to implement the requirements of CEQA, and to delegate certain duties to various bodies within City’s organizational structure.
San Jose Municipal Code section 21.04.010, subdivision A, states that this particular title of City’s municipal code “incorporates by reference and adopts the objectives, criteria and procedures for environmental review contained in [CEQA] and the CEQA Guidelines.” The code section further specifies that to the extent any conflicts exist between this title of City’s municipal code and CEQA or the CEQA Guidelines, the relevant provisions in CEQA or the CEQA Guidelines control. (San Jose Mun. Code, § 21.04.010, subd. B.)
*1337 The San Jose Municipal Code dictates that City’s planning commission certifies the final EIR of projects requiring environmental review. (San Jose Mun. Code, § 21.07.010 et seq.) Section 21.07.020 of the San Jose Municipal Code states that the planning commission shall hold hearings to certify the final EIR as complete and prepared in compliance with CEQA. Upon conclusion of the certification hearing, the planning commission is entitled to find a final EIR complete and in conformity with the requirements of CEQA. (San Jose Mun. Code, § 21.07.030.) “If the planning commission certifies the final EIR, it may then immediately act or make recommendations on the project associated with the EIR.” (Id., subd. B.) Actions or recommendations by the planning commission cannot be deemed final until after the expiration of the appeal period specified in San Jose Municipal Code section 21.07.040. (Id., § 21.07.030, subd. C.) Individuals may file written appeals of the planning commission’s certification no later than 5:00 p.m. on the third business day after certification. (Id., § 21.07.040, subd. A.)
The San Jose Municipal Code in Conjunction with CEQA and the CEQA Guidelines
CCEC argues that under the CEQA Guidelines, only a decisionmaking body is able to certify a final EIR, and since the planning commission has no power to approve the general plan under the relevant municipal ordinances, its certification could not be legal. City counters that the certification process was essentially bifurcated into two parts, with the planning commission certifying that the final EIR was complete and in compliance with CEQA, and the city council certifying the other requirements set forth under CEQA Guidelines section 15090. 4 We disagree with City’s characterization of the bifurcated certification process, and further find fault with City’s delegation of CEQA approval to the planning commission, a nondecisionmaking body with respect to the general plan.
As explained, ante, CEQA Guidelines section 15090 requires that prior to approval of a project, the lead agency must certify that (1) the final EIR is compliant with CEQA, (2) the final EIR was presented to the decisionmaking body of the lead agency and the decisionmaking body reviewed and considered the information in the final EIR prior to approving the project, and (3) the final EIR reflects the lead agency’s independent judgment and analysis. (CEQA Guidelines, § 15090, subd. (a).) The lead agency in this situation is the city council, which neither City nor CCEC disputes. However, City states in its brief that it considers the planning *1338 commission to be a nonelected decisionmaking body. We disagree. While the planning commission may be a nonelected decisionmaking body for certain projects that require environmental review, it is not a “decision-making body” with respect to City’s general plan. The CEQA Guidelines define a “decision-making body” as any group that has power to approve or disapprove the project at issue. (Id., § 15356.) Here, the planning commission was not vested with the power to approve or disapprove a general plan. 5 Accordingly, as noted ante, the city council should be considered the lead agency as well as the decisionmaking body with respect to the Envision San Jose project. The planning commission is therefore a nonelected nondecisionmaking body with respect to the Envision San Jose project.
The City contends that the certification process under CEQA Guidelines section 15090 is delegated like so: (1) the planning commission certifies the first requirement under CEQA Guidelines section 15090, subdivision (a), that the final EIR is complete and in compliance with CEQA, and (2) the lead agency, or city council in this case, then certifies the second and third requirements under CEQA guidelines section 15090, subdivision (a), namely that the final EIR was presented to the decisionmaking body which reviewed and considered the final EIR, and that the final EIR reflects the decisionmaking body’s independent judgment and analysis. We find that such a delegation of duties is improper under CEQA.
CEQA Guidelines section 15025 specifically prohibits the lead agency’s decisionmaking body from delegating its obligation to review and consider a final EIR to another, inferior entity within its agency. The lead agency’s obligation to review and consider a final EIR is the second of the three certification requirements outlined in CEQA Guidelines section 15090, subdivision (a). As a leading treatise on CEQA notes, “[t]he first aspect of certification, as noted earlier, is the conclusion that ‘[t]he final EIR has been completed in compliance with CEQA.’ CEQA Guidelines, § 15090, subd. (a)(1). The third finding required for certification, discussed above, is that ‘[t]he final EIR reflects the lead agency’s independent judgment and analysis.’ Id. at subd. (a)(3). There are no express prohibitions against the *1339 delegation of these two aspects of certification.” (Remy et al., Guide to CEQA: Cal. Environmental Quality Act, supra, at p. 376.) We agree that the language of CEQA Guidelines section 15090, subdivision (a)(1) and (3), does not specify that the decisionmaking body must be the entity making these respective findings.
Nonetheless, the CEQA Guidelines make it clear that there are certain duties that may not be delegated to nondecisionmaking bodies. A decision-making body, for instance, cannot delegate its duty under the guidelines to “review[] and consider[]” the final EIR. (CEQA Guidelines, § 15090, subd. (a)(2).) The language of the San Jose Municipal Code provides that the planning commission may, after conclusion of its certification hearing, find that the final EIR is “complete and conforms to the requirements of CEQA.” (San Jose Mun. Code, § 21.07.030, subd. A; see id., subd. B.) The San Jose Municipal Code does not state the planning commission is then tasked with certifying that the final EIR reflects the lead agency’s independent view and judgment, nor that the decisionmaking body has reviewed and considered the final EIR.
Yet for all intents and purposes, the certification of the final EIR by the planning commission is meant to be final for the purposes of CEQA, as the San Jose Municipal Code provides that after the planning commission “certifies the final EIR, it may then immediately act or make recommendations on the project associated with the EIR.” (San Jose Mun. Code, § 21.07.030, subd. B.) An alternate reading of the municipal code would produce a strange result where the planning commission has made only one out of the three required findings under CEQA Guidelines section 15090, subdivision (a), for all projects requiring CEQA approval, with no provisions for further CEQA certification by the planning commission or the lead agency. Logically, the planning commission would not be able to “immediately act” if it did not make all three of the requisite findings under CEQA Guidelines section 15090, subdivision (a).
Furthermore, even if the city council delegated to the planning commission the power to certify the final EIR only with respect to the aspect of certification that the final EIR was complete and in compliance with CEQA (CEQA Guidelines, § 15090, subd. (a)(1)), such a delegation is improper. CCEC argues that a delegation of the duties to review and consider the EIR to the planning commission is against the procedures set forth in the CEQA Guidelines, citing the decision in
Kleist v. City of Glendale
(1976)
Delegation of certification of an EIR to a nonelected
decisionmaking
body has been condoned by courts. In
California Oak Foundation v. Regents of University of California
(2010)
But here, certification of the final EIR was not delegated to a nonelected decisionmaking body. Rather, it was delegated to a nonelected nondecisionmaking body, the planning commission. We find that such a delegation was improper under CEQA, which explicitly allows for such a delegation only to a decisionmaking body. (CEQA Guidelines, §§ 15025, 15090.)
As noted above, there appears to be no express prohibition against delegating the certification of the aspect that the final EIR has been completed in compliance with CEQA (CEQA Guidelines, § 15090, subd. (a)(1)). However, cases have held that “ ‘[p]ublic participation is an “essential part of the CEQA process.” ’
([Laurel Heights Improvement Assn. v. Regents of University of California
(1993)] 6 Cal.4th [1112,] 1123 [
“ ‘The foremost principle under CEQA is that the Legislature intended the act “to be interpreted in such manner as to afford the fullest possible protection to the environment within the reasonable scope of the statutory language.” ’ ”
(Pocket Protectors v. City of Sacramento
(2004)
Under our analysis, the city council, as the decisionmaking body with respect to the Envision San Jose plan, is the entity tasked with certifying that the final EIR was compliant with CEQA. The delegation as part of its certification duty to the planning commission, as a nonelected nondecisionmaking body, therefore improperly segregated environmental review from project approval. We conclude that the planning commission’s certification of the final EIR as completed in compliance with CEQA was erroneous.
*1342 However, the city council’s certification was not faulty. In the resolution approving the project and certifying the final EIR, the city council stated that it certified the final EIR as in compliance with CEQA, and that it had independently reviewed and analyzed the final EIR prior to acting upon and approving the Envision San Jose plan. Given the city council’s declarations and findings, we must presume that its official duties were performed, absent evidence to the contrary. (Evid. Code, § 664.) The issue is thus whether CCEC exhausted its administrative remedies by filing its comment letter to the planning commission, and by filing its one-page letter after the planning commission’s certification.
2. Exhaustion of Administrative Remedies
Before addressing CCEC’s claims, we briefly discuss the doctrine of exhaustion of administrative remedies in the context of CEQA.
Overview of the Doctrine of Exhaustion of Administrative Remedies
The doctrine of exhaustion of administrative remedies bars individuals from seeking redress in the courts over an administrative action if they have failed to “exhaust” the remedies available to them during the proceeding itself.
(California Aviation Council v. County of Amador
(1988)
In the context of CEQA actions, Public Resources Code section 21177 provides that “[a]n action or proceeding shall not be brought pursuant to Section 21167 unless the alleged grounds for noncompliance with this division were presented to the public agency orally or in writing by any person during the public comment period provided by this division or prior to the close of the public hearing on the project before the issuance of the notice of determination.” (Pub. Resources Code, § 21177, subd. (a).) 7 “Section 14.5 of chapter 1514 of the Statutes of 1984, the measure by which [Public *1343 Resources Code] section 21177 was enacted, ‘states that the “intent of the Legislature in adding [Public Resources Code] [s]ection 21177 . . . [is] to codify the exhaustion of administrative remedies doctrine.” [Citation.] It further provides that “[i]t is not the intent [of the legislation] to limit or modify any exception to the doctrine of administrative remedies contained in case law.” [Citation.] “We are thus directed to read [Public Resources Code section 21177] with reference to a specific common law rule.” [Citation.] That rule has to do with the law of administrative remedies as it preceded the enactment of [Public Resources Code] section 21177.’ ” (Tahoe Vista, supra, 81 Cal.App.4th at pp. 589-590.)
Tahoe Vista interpreted Public Resources Code section 21177 and the exhaustion of administrative remedies doctrine to preclude plaintiffs from litigating actions in the trial courts unless they have pursued and specifically raised arguments in available administrative appeals. (Tahoe Vista, supra, 81 Cal.App.4th at pp. 590-591.) The Tahoe Vista court reasoned that once “ ‘a wrongful administrative action has been taken the focus of the affected members of the public is sharpened. If some reasonable administrative remedy, such as the right to appeal the action of a planning commission, were afforded to challenge such improper action the doctrine of administrative remedies would bar suit by litigants who failed to employ it.’ ” (Id. at p. 590.) Of course, “ ‘[consideration of whether such exhaustion has occurred in a given case will depend upon the procedures applicable to the public agency in question.’ ” (Id. at p. 591.)
Nonetheless, the
Tahoe Vista
court concluded that administrative remedies were exhausted if a plaintiff “raise[s] all issues before the administrative body with ultimate or final responsibility to approve or disapprove the project, even if those issues were not raised before subsidiary bodies in earlier hearings.”
(Tahoe Vista, supra,
*1344
Tahoe Vista
dealt with a situation where a plaintiff sought relief from the trial courts, arguing on appeal that an EIR should have been prepared instead of a negative declaration. This issue was brought to the attention of the planning commission during the public comment period.
(Tahoe Vista, supra,
(14) We understand the
Tahoe Vista
decision as combining the requirements of Public Resources Code section 21177 with the common law doctrine of exhaustion of judicial remedies. Specifically, issues must be first raised with the final decisionmaking authority if one wishes to seek judicial relief. However, we also understand that Public Resources Code section 21177 allows plaintiffs to litigate any issue that is raised before the final decision-making authority, even if the plaintiff bringing the litigation was not the one who filed an administrative appeal or was not the one who brought the issue to the final decisionmaking authority’s attention.
(Citizens for Open Government, supra,
Such an interpretation of the exhaustion doctrine comports with relevant case law that holds administrative remedies to be exhausted if the final decisionmaking body of the project reviews and considers a project EIR de novo, including the criticisms brought by a challenging organization.
(Audubon Society, supra,
Moreover, “ ‘[t]he exhaustion of administrative remedies doctrine has never applied where there is no available administrative remedy. [Citations.] [f] . . . [O]nce a wrongful administrative action has been taken the focus of the affected members of the public is sharpened. If some reasonable administrative remedy, such as the right to appeal the action of a planning commission, were afforded to challenge such improper action the doctrine of administrative remedies would bar suit by litigants who failed to employ it.’ ”
(Tahoe Vista, supra,
Application of the Exhaustion Doctrine to CCEC
As shown from the cited cases above, whether the exhaustion doctrine applies depends on the relevant procedures available in a specific jurisdiction. Here, the San Jose Municipal Code empowers the planning commission with the ability to certify a final EIR as complete and in compliance with CEQA. (San Jose Mun. Code, §§ 21.07.020, subd. A, 21.07.030, subd. A.) An administrative appeal process is also laid out in City’s municipal code, which provides that “[a]ny person may file a written appeal of the planning commission’s certification of the final EIR with the director, no later than 5:00 p.m. on the third business day following the certification.” (Id., § 21.07.040, subd. A.) The city council conducts appeal hearings if it is the lead agency. (Id., subd. D.)
*1346 Though it is unclear from the text of relevant municipal code sections whether the administrative appeal is limited to the specific issues set forth in the appeal form, the municipal code provides that appeals must state “with specificity” the reasons.why a final EIR should not be found to be complete and in compliance with CEQA (San Jose Mun. Code, § 21.07.040, subd. B), and appeals will not be considered unless they are based on issues previously raised in public hearings (id., subd. C). San Jose Municipal Code section 21.07.060, subdivisions A and C provide that the appeal will be reviewed “de novo,” and that upon conclusion of the certification appeal hearing the city council may find the final EIR complete and in conformity with CEQA.
CCEC argues that the designated final administrative arbiter is the city council, and since the city council “reviewed” the final EIR, including CCEC’s lengthy comment letter, it was not deprived of meaningful review. As we agree with CCEC’s contention that the planning commission’s certification of the final EIR was not proper, no administrative appeal had to be taken in order to exhaust administrative remedies.
(Tahoe Vista, supra,
The situation presented here is analogous to the situation outlined in
Audubon Society
and in our prior decision in
Browning-Ferris Industries v. City Council
(1986)
*1347
In
Browning-Ferris,
we addressed the argument that BFI had failed to exhaust its administrative remedies, relying on the holding in
Audubon Society, supra,
In this situation, as in Browning-Ferris, the agency with the ultimate responsibility for giving final approval of the Envision San Jose plan and its corresponding EIR was not the planning commission, but the city council. The planning commission was not a decisionmaking body with respect to the plan. CCEC submitted a detailed letter to the planning commission identifying specific deficiencies in the draft EIR, arguing that the draft EIR failed to consider certain environmental impacts. Therefore, our consideration turns on whether CCEC’s letter sufficiently raised its arguments regarding the sufficiency of the EIR to the city council.
“To advance the exhaustion doctrine’s purpose ‘[t]he “exact issue” must have been presented to the administrative agency . . . .’ [Citation.] While ' “less specificity is required to preserve an issue for appeal in an administrative proceeding than in a judicial proceeding” because, . . . parties in such proceedings generally are not represented by counsel . . . [citation]’ [citation], ‘generalized environmental comments at public hearings,’ ‘relatively . . . bland and general references to environmental matters’ [citation], or ‘isolated and unelaborated comments] ’ [citation] will not suffice. The same is true for ‘ “[g]eneral objections to project approval . . . .” [Citations.]’ [Citation.] ‘ “[T]he objections must be sufficiently specific so that the agency has the opportunity to evaluate and respond to them.” ’ ”
(Sierra Club v. City of Orange
(2008)
The situation presented to us is dissimilar to the situation addressed in Tahoe Vista, where the ultimate decisionmaking authority’s review was specifically confined to issues raised in the administrative appeal. City reviewed and certified the EIR de novo, as it is the decisionmaking body with respect to the Envision San Jose plan. Indeed, the city council’s resolution stated that it had reviewed and considered the final EIR, along with the comments submitted during the public hearing and comment period. Accordingly, the comment letter issued by CCEC to the planning commission during the public comment period, which specified the alleged deficiencies in the EIR, sufficiently apprised the city council of CCEC’s arguments regarding the adequacy of the EIR and the need for recirculation. As previously noted, a review of the contents of the letter and claims CCEC alleged in its petition for writ of administrative mandamus indicates that the claims raised in CCEC’s petition were raised in its initial comment letter. 11 Since the city council had the comment letter at the time it certified the final EIR and approved the project, it was fairly apprised of CCEC’s objections. Accordingly, CCEC exhausted its administrative remedies.
*1349 3. Conclusion
Since delegating to the planning commission the duty to certify that the final EIR was complete and in compliance with CEQA is faulty, no administrative appeal was available to CCEC. CCEC therefore adequately exhausted its administrative remedies when it submitted its comment letter raising the inadequacy of the EIR’s environmental review and the need for recirculation of the EIR. Therefore, we conclude that the trial court’s grant of summary judgment in favor of City was in error.
Disposition
The trial court’s judgment is reversed. CCEC is entitled to its costs on appeal.
Rushing, R J., and Elia, J., concurred.
Respondent’s petition for review by the Supreme Court was denied January 29, 2014, S215137.
Notes
The record indicates that the EIR considered by City was actually called a “program environmental impact report,” or a PEIR. For clarity we will simply refer to the Envision San Jose PEIR as a final EIR, or EIR, when appropriate.
The CEQA guidelines, which implement provisions of CEQA, are codified at California Code of Regulations, title 14, section 15000 et seq. Further references to the “CEQA Guidelines” are to California Code of Regulations, title 14, section 15000 et seq.
This interpretation follows the analysis set forth in a well-regarded treatise on CEQA, which states: “The decision-making body need not necessarily be the lead agency’s elected officials. . . . The CEQA Guidelines define ‘decision-making body’ as ‘any person or group of people within a public agency permitted by law to approve or disapprove the project at issue.’ CEQA Guidelines, § 15356. Thus, for example, a city council may delegate the EIR certification function to an appointed body such as its planning commission, if the relevant city ordinance empowers the planning commission to approve or disapprove the project at issue.” (Remy et al., Guide to CEQA: Cal. Environmental Quality Act (11th ed. 2007) pp. 375-376.)
Notably, in its resolution certifying the final EIR, the planning commission also stated that it certified that the final EIR reflected City’s independent judgment and analysis. However, City did not argue below or here on appeal that the planning commission certified the final EIR as to this aspect.
The San Jose City Charter bestows upon the planning commission certain powers and duties, including the power to “[m]ake recommendations to the [city council] respecting the adoption, amendment, or repeal of master, general, comprehensive, precise or specific plans for future physical development of the City or any part thereof, and periodically review the same,” and the power to “[e]xercise such other powers and perform such other functions and duties as may be expressly given to it by other provisions of [the] Charter, or exercise such other powers or perform such other functions as may be prescribed by the [city council] not inconsistent with the provisions of [the] Charter.” (San Jose City Charter, art. X, § 1000.) Both City and CCEC assert that the city council is the decisionmaking body in its briefs. In its reply brief, City makes the statement that the “[city council] is the decision-making body for approving projects such as [Envision San Jose].”
However, this is not to say that an elected decisionmaking body cannot adopt the findings made by a nonelected body.
(Vedanta Society of So. California
v.
California Quartet, Ltd.
(2000)
As explained in
Tahoe Vista Concerned Citizens v. County of Placer
(2000)
Accordingly, under Public Resources Code section 21177, a plaintiff must allege noncompliance with CEQA at some point in the administrative review process before acquiring standing to litigate the case in the trial court. (Tahoe Vista, supra, 81 Cal.App.4th at pp. 590-591.) Here, since it is undisputed that CCEC issued a comment letter on the draft EIR raising concerns with the adequacy of its environmental review, CCEC would certainly have standing to litigate the issue in court. However, the pertinent issue here is not whether or not CCEC had standing, but the related issue of whether it exhausted its administrative remedies by filing the letter.
City argues that the portion of the
Audubon Society
opinion where (he court determined the Audubon Society sufficiently exhausted its administrative remedies through its appearance before the final decisionmaking body is dictum and has no precedential value, since the court disposed of the issue on the other grounds stated in its opinion.
(Audubon Society, supra,
155 Cal.App.3d at pp. 747-748.) We find this argument unavailing. Though we are not bound by precedents created by other appellate courts, we may find the reasoning set forth in their decisions, including dicta, persuasive as to the facts we are presented with on appeal.
(People v. Valencia
(2011)
Furthermore, after the planning commission’s hearing, CCEC submitted a letter to City’s department of planning, building and code enforcement, which stated that it was attaching a written study to the letter, and that CCEC believed this written study further supported its “request that the City consider the long-term viability of the fiscal strategy laid out in the EIR and alternative methods for increasing local economic growth.” The full text of CCEC’s letter reads: “Dear [Senior Planner]: [][] Enclosed with this letter please find a copy of Chapter 6 of the SB A 2006 Report to the President and ‘Curbside Chat,’ a study prepared by StrongTowns.org. We are requesting that these be included in the administrative record. These documents further support the request that the City consider the long-term viability of the fiscal strategy laid out in the EIR and alternative methods for increasing local economic growth. Given the importance of improving the City’s long-term fiscal circumstances, both of these documents contain important information for the City’s consideration.” This subsequent letter does not make any specific claims, but CCEC’s specific arguments regarding the need for recirculation of the EIR and the alleged deficiencies in the EIR were contained in its initial comment letter on the draft EIR.
Public Resources Code section 21092.1 provides that “[w]hen significant new information is added to an environmental impact report after notice has been given pursuant to Section 21092 and consultation has occurred pursuant to Sections 21104 and 21153, but prior to certification, the public agency shall give notice again pursuant to Section 21092, and consult again pursuant to sections 21104 and 21153 before certifying the environmental impact report.”
In CCEC’s petition for writ of administrative mandamus and its initial comment letter on the draft EIR, CCEC argued there were deficiencies in the EIR’s analysis of greenhouse gas emissions, its analysis of energy conservations, and its analysis of alternatives.