177 P. 849 | Cal. | 1918
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *339
This is an appeal from a judgment after verdict for $44,452.19, the contract price for drilling two oil wells by plaintiff for defendant, and from the order denying defendant's motion for a new trial. Well No. 7 was drilled under contract dated February 7, 1912. Well No. 6 was drilled under a contract dated December 31, 1912. Both wells were to be paid for by the foot. It is admitted that well No. 6 conformed to the contract, and that plaintiff is entitled to be paid the contract price therefor. All the difficulties in the case grow out of the contract for the drilling of well No. 7 and its relation to the second contract. The question is whether or not the plaintiff completed the well as required by the contract for the drilling of well No. 7, and, if not, whether said well was accepted by the defendant as completed in August, 1912, at which time plaintiff claims that it had sunk well No. 7 to a depth of 3,215 feet, and "into the oil sand," and had placed therein at the request of the defendant a perforated four-inch pipe; that the well was thereupon accepted as completed, but that five days thereafter, defendant having discovered that the well was crooked, returned it to the possession *340
of the plaintiff to be straightened; that thereafter, for a year, the plaintiff was actively engaged in attempting to straighten the well, and in July, 1913, having straightened the well and sunk it to a depth of 3,241 feet — 26 feet farther than it was at the time it was accepted by the defendant — they had thus fully performed their contract. The case thus presented two main questions, that of acceptance and of completion. Plaintiff contends that the jury having found a general verdict in its favor, it must be considered to have found an acceptance, even though the special interrogatory requiring a finding thereon was unanswered, and this may well be true. (Benson v. Southern Pac. Co.,
The question of the completion of the well being thus submitted to the jury as a mixed question of law and of fact, appellant contends that the evidence was insufficient to justify the finding of the jury that the well was completed. Inasmuch *344 as the jury was clothed with no power to incorrectly decide the law, we must, in considering this contention, assume that they applied the law correctly to the facts. In other words, we must assume that they correctly construed the contract and applied that construction to the facts as presented to them. The contract, as we construe it, required the drilling of the well into producing oil sand, that is, sand-producing oil in reasonably paying quantities, and in default of such a showing of oil to continue to drill the well to a depth of three thousand five hundred feet if required by the defendant. The question, then, is, Does the evidence justify the finding of the jury that the plaintiff completed the well by drilling the same into producing oil sand? The theory of the plaintiff is that it had drilled a well "into the oil sand" when it had attained the depth of 3,215 feet, that the well was then accepted and returned to it merely for straightening, and that when they had straightened the well and again sunk it to a depth of 3,215 feet they had completed the well, in that it was again just as far into the oil sand as it was in the first instance. The defendant denied that it ever accepted the well or ever considered it as completed or ever took it over as completed. It is admitted by the plaintiff that it never tested the oil well either by pumping or bailing. It is shown beyond question that the well never produced any oil and that no oil was ever taken therefrom except the oil that was pumped into it for the purpose of testing it. In the effort to straighten and deepen the well the point of 3,215 feet was passed at least four times; that is to say, by reason of loss of tools and other defects in the well it was necessary to go back and redrill the well, and in so doing the well was drilled past this point at least four times. Plaintiff's general manager testified that they had no log of any of these drillings which showed any oil sand; that when the well had reached a depth of 3,241 feet it was in blue shale. The log of the original drilling to a depth of 3,215 feet was lost as to the drilling for the last week or two, in July and August, 1912, and the only testimony offered as to the showing of oil sand was the testimony of some of the well drillers and of plaintiff's general manager. One of these drillers testified that in his opinion the well showed signs of oil sand for about ten feet. On cross-examination he admitted that the rotary drill might show signs of oil sand long after it had been passed through, and that a showing of *345 ten feet of oil sand by a rotary drill might mean only four or five feet of oil sand. If it is true that there were four or five feet of producing oil sand at about 3,215 feet, the fact remains that the plaintiff, upon whom the burden lay of showing that such sand was producing sand, made no effort to test the well. It would seem that this was a case for the application of the doctrine that where weaker and less satisfactory evidence is offered, when it appears that stronger and more satisfactory was within the power of the party, the evidence offered should be viewed with distrust. (Code Civ. Proc., sec. 2061, subd. 7.) But viewed in the light of the conduct of the parties subsequent to the alleged acceptance of the well, it is clear that the well was never completed. If we assume in favor of the respondent that when the contract of December 31st referred to well No. 7 as uncompleted, it had reference to the fact that the well was crooked and in a process of being straightened and that when straightened to a depth of 3,215 feet it would be considered by the parties as complete, we are met by a great many difficulties. On March 13, 1913, the plaintiff entered into a contract with two subcontractors to drill well No. 7 to a depth of three thousand three hundred feet. No good reason for making this contract is offered consistent with the theory that the well was to be completed when down to a depth of 3,215 feet and straight. There was correspondence between the plaintiff and defendant in regard to the completion of well No. 7. On May 31, 1913, plaintiff wrote the defendant: "We are undecided whether to go on and try and finish No. 7 or not. If we do not finish No. 7, the string of four and a quarter inch casing which is in No. 7 could be used on No. 6. We have some drillers who are very anxious to take another labor contract to finish No. 7. They say they are pretty sure of finishing well No. 7, but we are pretty badly disgusted with this well and will hold up the contract until the writer sees you. We have about concluded that if your company will pay us for No. 6 at the contract price of $6.50 per foot, then we will quit No. 7 as it is, and by doing that the string of four and a quarter inch casing could go to No. 6 and we would drill a new well for No. 7 under No. 7 contract. But if your company wants to hold up the payment on No. 6 until No. 7 is completed, we will take one more chance in contracting the completion of No. 7. There is a chance, although small, of finishing No. 7. But if *346 your company would prefer to have a new well drilled we will start drilling on a new well, or you may take No. 7 as it is and pay us for No. 6 at the contract price and wait until you finish No. 6, and then the condition may be favorable for your going ahead with No. 7." Plaintiff's general manager, Mr. Edwards, testified that on June 4 or 5, 1913, he made defendant a proposition that "if they would accept No. 6 and pay for it at the contract price and release me on well No. 7 that I would accept it. I also stated that the outlook of finishing well No. 7 was very discouraging; that we had been working on it pretty nearly a year and had not made any headway toward getting it finished, and we would either drill a new well to replace No. 7, or take another chance of going ahead and finishing, or I believe I told them at that time I would take one more chance of finishing it under some new men who thought very strongly that they could finish the well. That was Mr. Chappis and Mr. Gibson. They didn't accept my proposition, so I put my men on No. 7 and went to work again." Mr. Chappis testified that when he went to work on well No. 7 the tools went down somewhere in the neighborhood of 3,217 to 3,220 feet. The evidence, therefore, is insufficient to justify the finding of the jury that the well was drilled into the oil sand according to the contract.
At the plaintiff's request the court instructed the jury as follows: "The court instructs the jury that if you find that there was no custom in the West Side Oil Fields as to who should test the oil sand, then the plaintiff does not have to show that it tested the oil sand, unless the contract expressly or impliedly provides for such test." In view of the fact that no oil was obtained from well No. 7 and that the burden was on the plaintiff to establish completion of the well, this instruction could only tend to confuse the jury. The question as to whose duty it was by custom or otherwise to test the well was not properly involved in the case. The effect of the instruction must have been to suggest to the jury that it was unnecessary for plaintiff to give evidence of a test of the well in order to recover.
The judgment and order are reversed.
Sloss, J., Melvin, J., Richards, J., pro tem., Shaw, J., Victor E. Shaw, J., pro tem., and Angellotti, C. J., concurred. *347