The plaintiff-contractor appeals from the trial court’s decree ordering specific per *392 formance of a contract for the construction and sale of a home. We affirm.
In this court-tried case, the court held the plaintiff had breached the contract by assessing charges not in accord with those in the contract. The court found that as a result of this breach the defendant-buyers lost a commitment from a lending institution for a home loan with a 9% annual interest rate. Further, the court found that 12% was the most favorable interest rate available to defendants at the time of the trial. The court ordered the parties to specifically perform the contract and allowed them various credits and charges, including a $6100.00 credit to defendants to offset the increased interest rate.
On appeal, plaintiff acknowledges that a court sitting in equity has the discretion to award damages for losses proximately caused by a breach of a contract in addition to ordering specific performance of the contract.
Metropolitan St. Louis Sewer District v. Zykan,
The decree of the trial court should be affirmed if it is supported by substantial evidence, is not against the weight of the evidence, and neither erroneously states nor applies the law.
Murphy v. Carron,
The rules regarding the measure of damages in contract cases are well settled. The non-breaching party may recover “the amount which will compensate [him] for the loss which a fulfillment of the contract would have prevented or the breach of it has entailed .... [T]he person injured is, as far as is possible to do so by a monetary award, to be placed in the position he would have been in had the contract been performed.”
Boten v. Brecklein,
We believe the law permits a credit for the increased cost of a loan in a case such as this. Apparently, no Missouri court has directly confronted the issue of whether to compensate the non-breaching party for an increase in interest rates in addition to granting specific performance. However, courts in other jurisdictions have considered cases nearly identical to this one and have held losses caused by an increase in interest rates during a breach are compensable.
See Godwin v. Lindbert,
Further, Missouri courts have permitted the recovery of interest expenses and loan fees as actual damages.
Herbert & Brooner Construction Co. v. Golden,
In support of its argument that the loss defendants suffered by reason of the increase in the interest rate is too remote to
*393
be compensable, plaintiff cites
Dunning v. Alfred H. Mayer Company,
Dunning not only does not support plaintiffs position but, in fact, supports defendants’. We did not hold that losses caused by increased interest rates are not recoverable in a suit for specific performance. Rather, we held that because the buyers were in no way committed to taking a loan at the higher interest rate, they would suffer no actual loss as a result of the increased interest rates. In this case the buyers will be required to obtain a loan at the higher interest rate because the trial court has ordered specific performance of the contract, and they will suffer a real loss as a result of the increased interest rates.
Having determined that such a credit is permitted under the law, we now consider whether defendants carried their burden of proving that plaintiff’s breach proximately caused them to lose the loan commitment.
The court held that the plaintiff breached the contract by assessing charges not in accord with those in the contract, and plaintiff does not challenge that holding. Both parties testified that a dispute arose regarding the charges and that the dispute delayed completion of the contract. Officers of the savings and loan testified that the savings and loan was committed to making a 9% loan to defendants and that it held that commitment open for almost a year. One of the officers testified that, before it cancelled the loan commitment, the savings and loan inquired of defendants whether they had resolved the dispute regarding the charges. The parties had not resolved the dispute, and the savings and loan cancelled the loan commitment. This constitutes substantial evidence to support the trial court’s finding that the plaintiff’s breach proximately caused defendants’ loss of the 9% loan.
Judgment affirmed.
