Rocky H. CAIN, Plaintiff-Appellee, v. TRANSOCEAN OFFSHORE USA, INC.; Sedco Forex Corp., Defendants-Third Party Plaintiffs-Appellants, v. Fontana Center LLC, Third Party Defendant-Appellee.
No. 05-30963.
United States Court of Appeals, Fifth Circuit.
Feb. 21, 2008.
518 F.3d 295
Even were we to recognize the inherent authority of the district court to issue a stay, DEI does not present the same “prudential” case that existed in Berg. While DEI has outstanding arbitration claims against Wartsila, it has presented no evidence of Wartsila‘s insolvence or that DEI will have trouble recovering on its claims. Further, in Berg, the First Circuit noted that the arbitration panel prevented Hewlett-Packard from asserting its claims in the same arbitration. Id. at 105. In this case, DEI unilaterally withdrew its claims in order to reserve them for a later proceeding. Therefore, the district court did not abuse its discretion in refusing to grant DEI‘s motion for stay of enforcement on the grounds laid out in Hewlett-Packard v. Berg.
IV
The district court properly interpreted the tribunal‘s award when it determined that the award contemplated summary confirmation and enforcement by the court. The district court did not abuse its discretion in denying DEI‘s request for a stay of enforcement. Accordingly, we AFFIRM the judgment of the district court.
Hal C. Welch, Lemle & Kelleher, New Orleans, LA, for Transocean Offshore USA, Inc. and Sedco Forex Corp.
Daniel A. Reed, Seale, Smith, Zuber & Barnette, Baton Rouge, LA, for Fontana Ctr. LLC.
Before KING, GARZA and OWEN, Circuit Judges.
KING, Circuit Judge:
This case requires us to consider the continued viability of our longstanding precedent holding that a watercraft under construction is not a “vessel in navigation” for purposes of the
I. Background
In 1996, Plaintiff-Appellee Rocky Cain began working as a driller on a semi-submersible drilling rig in the Gulf of Mexico for Sonat Offshore USA, Inc. Sonat later became part of Defendant-Appellant Transocean Offshore USA, Inc. On March 1, 2000, Transocean assigned Cain as a toolpusher to the “Cajun Construction Site” in Singapore. Cain worked in Singapore for approximately six months at the PPL Shipyard, where the M/V CAJUN EXPRESS was under construction. The CAJUN EXPRESS is a fifth-generation semi-submersible mobile offshore drilling rig designed to drill for oil and gas. Cain was expected to continue working on the CAJUN EXPRESS, or a sister rig, after construction was complete. Cain supervised a drill crew of seven men and was responsible for overseeing safety issues and commissioning the drilling equipment.
Although the rig was capable of self-propulsion, it was not fully capable of operating as a semi-submersible drilling rig. The necessary construction still included installation of vital pipe-handling equipment and “blisters,” which are large steel boxes welded to the rig to increase its buoyancy. Daniel Haslam, a Transocean engineer, testified that when it arrived in the Gulf of Mexico the CAJUN EXPRESS could lay pipe only under limited weather conditions. However, as a fifth generation semi-submersible unit, the most state of the art in the industry, the CAJUN EXPRESS was not designed to operate only under limited conditions. Haslam testified that no drilling contractor would have found the CAJUN EXPRESS fit for the purpose of drilling a deepwater well in the Gulf of Mexico.
On September 10, 2000, Cain was working on board the CAJUN EXPRESS. At that time, the blisters still had not been installed and the drilling systems had not been commissioned. Cain entered a warehouse located on board the rig to retrieve a part for a member of the drill crew, whereupon he struck his head on a low-hanging light fixture and was injured. A neurosurgeon later examined Cain and recommended that he undergo physical therapy. Cain received physical therapy and continued to work on board the CAJUN EXPRESS. In April or May 2001, the CAJUN EXPRESS was finally completed and began drilling operations in the Gulf of Mexico.
Cain continued to work as a toolpusher on the CAJUN EXPRESS but was subsequently diagnosed with a herniated disc. In September 2001, he discontinued work to undergo a cervical discectomy and fusion. Cain returned to work in December 2001, when Transocean assigned him to a “work hardening” program at the Fontana Center, a facility in Lafayette, Louisiana. While participating in the work hardening program, Cain allegedly experienced elevated blood pressure and suffered additional injuries.
Cain filed suit under the
II. Discussion
We review the district court‘s denial of summary judgment de novo. Solano v. Gulf King 55, 212 F.3d 902, 905 (5th Cir. 2000).
Transocean argues on appeal that under our established precedent the CAJUN EXPRESS was not a vessel in navigation, and therefore Cain was not a Jones Act seaman, because the rig was still under construction at the time of Cain‘s injury. It further argues that the Supreme Court‘s decision in Stewart has effected no change on our prior case law. We agree with both contentions.
A. “Seaman” status and our established precedent
We begin by describing two of the principal remedies available to injured workers who ply their trade in connection with the sea: the
The LHWCA provides the exclusive remedy to land-based workers who fall within its provisions. Id. at 355, 115 S.Ct. 2172. It specifically excludes from its coverage “a master or member of a crew of any vessel.”
Under the Jones Act, a “seaman” is a term of art for an employee whose duties “contribut[e] to the function of the vessel or to the accomplishment of its mission” and who has “a connection to a vessel in navigation (or to an identifiable group of such vessels) that is substantial in terms of both its duration and its nature.” Chandris, 515 U.S. at 368, 115 S.Ct. 2172 (internal quotation marks and citation omitted); see also Garret v. Dean Shank Drilling Co., 799 F.2d 1007, 1009 (5th Cir. 1986) (“The worker is a seaman if he is assigned permanently to a vessel in navigation or performs a substantial part of his work on the vessel, contributing to the function of the vessel or to the accomplishment of its mission.“). The existence of a “vessel” is thus crucial to determining seaman status under the Jones Act. Holmes v. Atl. Sounding Co., 437 F.3d 441, 446 (5th Cir. 2006).
We have long held that the Jones Act analysis requires a watercraft to be “in navigation,” and we have drawn a distinction between completed crafts and crafts that are under construction. A maritime worker “assisting in the building and ultimate commissioning of a launched but uncompleted vessel floating or maneuvering in navigable waters is not a seaman within the meaning of the Jones Act, because his vessel is not yet an instrumentality of commerce—private or public—and is therefore not ‘in navigation.‘” Williams v. Avondale Shipyards, Inc., 452 F.2d 955, 958 (5th Cir. 1971).
Similarly, in Garret, we held that an offshore drilling rig was not a vessel in navigation because, at the time of the plaintiff‘s injury, the structure was still undergoing final construction to make it operational as an oil and gas drilling rig. 799 F.2d at 1009. We noted that the structure had never been engaged as an instrument of commerce and held that a “nonmerchant vessel is in navigation if it is engaged in its expected duties on navigable waters.” Id.
In the instant case, the CAJUN EXPRESS was still under construction at the time of Cain‘s injury. Although the rig was capable of self-propulsion and had run some test pipe, it lacked vital equipment to make it fully operational as an oil and gas drilling rig. Indeed, as Daniel Haslam testified, no drilling contractor would have found the CAJUN EXPRESS fit to drill a deepwater well in the Gulf of Mexico. The CAJUN EXPRESS was not finally completed and placed into service until April or May 2001, after Cain was injured. Thus, under established Fifth Circuit precedent, the CAJUN EXPRESS was not a vessel in navigation and Cain was not a Jones Act seaman.
B. Stewart
We now turn to the Supreme Court‘s decision in Stewart v. Dutra Construction Company. In Stewart, the Court addressed whether a dredge known as the SUPER SCOOP was a vessel under the LHWCA. 543 U.S. at 484, 125 S.Ct. 1118. Although the case specifically concerned the LHWCA, we have recognized that Stewart‘s analysis of the term “vessel” applies equally to the LHWCA and to the Jones Act. Holmes, 437 F.3d at 448.
The SUPER SCOOP was a floating platform with a clamshell bucket suspended beneath the water used to remove silt from the ocean floor. Stewart, 543 U.S. at 484, 125 S.Ct. 1118. The dredge was engaged in digging a trench beneath Boston Harbor as part of the “Big Dig” project. Id. It had limited means of self-propulsion and was typically moved by tugboat, but it could move short distances by manipulating its anchors and cables. Id.
The First Circuit applied its test for vessel status found in DiGiovanni v. Traylor Bros., 959 F.2d 1119, 1123 (1st Cir. 1992) (en banc), which had held that “if a barge ... or other float‘s purpose or primary business is not navigation or commerce, then workers assigned thereto for its shore enterprise are to be considered seamen only when it is in actual navigation or transit at the time of the plaintiff‘s injury.” Id. at 485-86, 125 S.Ct. 1118 (internal quotation marks omitted). The First Circuit held that the SUPER SCOOP was not a vessel because any navigation was incidental to the craft‘s primary function of construction. Id. at 486, 125 S.Ct. 1118. It also found significant the dredge‘s stationary position at the time of the plaintiff‘s injury. Id.
The Supreme Court rejected the First Circuit‘s test for vessel status, concluding that although Congress did not define “vessel” in the LHWCA or the Jones Act, it had already defined “vessel” elsewhere at the time both acts were passed. Id. at 487-88, 125 S.Ct. 1118. Specifically, under
Relying on
With respect to the requirement that a vessel be “in navigation,” the Court clarified that the requirement was meant to show only that structures could lose their vessel status if they are withdrawn from the water for extended periods. Id. at 496, 125 S.Ct. 1118. The “in navigation” requirement does not stand apart from
C. Stewart and vessels-to-be
The district court held that the CAJUN EXPRESS was a vessel under Stewart because not only was it capable of transportation but it had also transported workers and equipment from Singapore to the Gulf of Mexico. We disagree, however, that Stewart was intended to apply to watercraft that are still under construction. “[W]e cannot overrule the decision of a prior panel unless such overruling is unequivocally directed by controlling Supreme Court precedent.” United States v. Zuniga-Salinas, 945 F.2d 1302, 1306 (5th Cir.1991) (emphasis added). We conclude that our well-settled body of law in this area has not been effectively overruled.
The language in Stewart is admittedly broad, and we have recognized that the Court‘s decision significantly enlarges the types of unconventional and special purpose watercraft that now must be considered vessels that might not have met the test before Stewart. See Holmes, 437 F.3d at 448. Stewart began, however, by framing the issue before it narrowly: “whether a dredge is a ‘vessel’ under [the LHWCA].” Stewart, 543 U.S. at 484, 125 S.Ct. 1118. The Court decided that specific question, concluding that the First Circuit‘s focus on an existing craft‘s purpose and movement was inconsistent with the text of
Stewart examined an already-completed structure in use for its intended purpose. Stewart did not concern what to do with ships and other structures under construction, and so the Court did not address whether
Other courts have similarly concluded that an incomplete structure that has not been put into navigation as an instrument of commerce is not a vessel. See Caruso v. Sterling Yacht & Shipbuilders, Inc., 828 F.2d 14, 15-16 (11th Cir.1987); Frankel v. Bethlehem-Fairfield Shipyard, Inc., 132 F.2d 634, 635-36 (4th Cir.1942). Moreover, courts have historically spoken of navigation in tandem with commerce. See, e.g., The Robert W. Parsons, 191 U.S. 17, 31, 24 S.Ct. 8, 48 L.Ed. 73 (1903) (holding that a barge drawn by horses in the Erie Canal was a vessel because “[s]o long as the vessel is engaged in commerce and navigation it is difficult to see how the jurisdiction of admiralty is affected by its means of propulsion“); Cope v. Vallette Dry-Dock Co., 119 U.S. 625, 627-28, 7 S.Ct. 336, 30 L.Ed. 501 (1887) (noting that “[a] ship or vessel, used for navigation and commerce, though lying at a wharf, and temporarily made fast thereto, as well as her furniture and cargo, are maritime subjects“); People‘s Ferry Co. of Boston v. Beers, 61 U.S. 393, 401, 20 How. 393, 15 L.Ed. 961 (1857) (“[T]he admiralty courts now exercise jurisdiction over rivers and inland waters, wherever navigation is or may be carried on, and extends to almost every description of vessel which may be employed in transporting our products to market .... The admiralty jurisdiction, in cases of contract, depends primarily upon the nature of the contract, and is limited to contracts, claims, and services, purely maritime, and touching rights and duties appertaining to commerce and navigation.“).
That is not to say that only commercial structures may become vessels and implicate admiralty jurisdiction. See, e.g., Sisson v. Ruby, 497 U.S. 358, 363-67, 110 S.Ct. 2892, 111 L.Ed.2d 292 (1990) (admiralty jurisdiction in tort requires inter alia that an incident have a potentially disruptive effect on maritime commerce and be substantially related to maritime activity, such as navigation, but the tortfeasor‘s activity may be commercial or noncommercial). Rather, our precedent is not inconsistent with the historical perspective that vessels under construction are treated differently from completed vessels. See The Francis McDonald, 254 U.S. 242, 243-44, 41 S.Ct. 65, 65 L.Ed. 245 (1920) (holding in a contract case that shipbuilding has been considered a nonmaritime activity, whether or not the incomplete ship has been launched). We have previously noted “the historical tradition that vessels under construction give rise to neither a maritime contract nor a maritime tort.” Williams, 452 F.2d at 958 n. 5; see also Alfred v. MV Margaret Lykes, 398 F.2d 684, 685 (5th Cir.1968) (holding that an employee may not maintain a tort action against his employer for an injury sustained on a vessel that has been launched but not fully completed or commissioned). We do not read Stewart to change this body of law, so that a structure under construction remains a non-vessel until it is complete and ready for duty upon the sea.
We further think the preclusion from vessel status of crafts still under construction serves several important goals and is consistent with the concern for avoiding uncertainties and possible oscillation in
Our cases show that shipbuilders frequently begin the construction process in a shipyard at one location and then transport the partially completed craft to another location to finish the construction process. See, e.g., Garret, 799 F.2d at 1008 (barge hull transported by tug from shipyard in Houma, Louisiana, to Harvey, Louisiana, for completion of superstructure); Fredieu v. Rowan Cos., Inc., 738 F.2d 651, 652 (5th Cir.1984) (ship partially constructed in Vicksburg, Mississippi, towed to Belle Chasse, Louisiana); Hollister v. Luke Constr. Co., 517 F.2d 920, 921 (5th Cir.1975) (barge towed from Harvey, Louisiana, to Houma, Louisiana to complete drilling rig). Along the way, hundreds of employees work to complete these partially-built structures. The CAJUN EXPRESS had over 200 men working on its completion. Stewart‘s application to these vessels-to-be could have the consequence of creating vessels out of partial structures and transforming many land-based ship construction workers into Jones Act seaman, at least while they work in the service of the ship. At a minimum, it would unnecessarily expand the labyrinth that has developed in the case law concerning seaman status by requiring fact-intensive inquiries in the district courts into the relationship between such workers and the intended vessel. Cf. Chandris, 515 U.S. at 356, 115 S.Ct. 2172 (“We have made a labyrinth and got lost in it.” (internal quotation marks and citation omitted)). Marine employers (and their insurers) and employees, however, have an interest “in being able to predict who will be covered by the Jones Act ... before a particular workday begins.” Id. at 363, 115 S.Ct. 2172.
That interest is hindered with respect to the construction of watercraft because there will be many points along the continuum of a ship‘s construction at which one could rationally argue it is “practically capable” of transportation and therefore a vessel. For example, a structure might become a vessel when it is merely capable of floatation but is still in dry dock; when it can be merely towed or pushed; when the navigation or propulsion systems are installed; when it has been inspected and commissioned; when it has been accepted for delivery; when a crew has been assigned; or when it is actually put to use. Our prior cases settle this uncertainty by asking whether the craft is complete. We continue to believe that “[f]or there to be a seaman, there must first be a ship,” but “an incompleted vessel not yet delivered by the builder is not such a ship.” Williams, 452 F.2d at 958.
The difficulty of applying Stewart to vessels under construction may be seen with respect to the CAJUN EXPRESS. The testimony showed that the rig lacked vital equipment for its operations and that no drilling contractor would have found the CAJUN EXPRESS acceptable for duty in the Gulf of Mexico. It strains reason to say that a craft upon the water that is under construction and is not fit for service is practically capable of transportation.
Moreover, mobile offshore drilling units like the CAJUN EXPRESS are subject to extensive Coast Guard regulations. See
In short, although Stewart instructs that the “in navigation” requirement “is relevant to whether the craft is ‘used, or capable of being used’ for maritime transportation,” 543 U.S. at 496, 125 S.Ct. 1118, that instruction does not consider in the first instance when a vessel-to-be becomes a vessel. We view that issue as a separate question from whether an unconventional watercraft is a vessel. We therefore hold that Stewart does not require us to modify our precedent regarding the vessel status of incomplete watercraft. As such, the CAJUN EXPRESS was not a “vessel in navigation,” and Cain was not a Jones Act seaman. Cain was thus not entitled to relief under the Jones Act for his September 10, 2000, injury.2
III. Conclusion
The district court‘s denial of Transocean‘s motion for summary judgment is REVERSED and the case is REMANDED to the district court for further proceedings consistent with this opinion. Costs shall be borne by Cain.
OWEN, Circuit Judge, dissenting:
This is a very difficult case, in my view. The panel‘s opinion sets forth cogent arguments as to why there should be a bright-line rule as to when a vessel under construction becomes a “vessel in navigation” for purposes of determining whether an injured worker was a “seaman” within the meaning of the Jones Act. However, the language used by the United States Supreme Court in Stewart v. Dutra Construction Company1 is broad and seems to require us to conclude that the CAJUN EXPRESS is a contrivance that is capable of being used as a means of transportation on water since the CAJUN EXPRESS did in fact transport Cain and others across an ocean.
There are undoubtedly conceptual difficulties in applying the principle that a “contrivance” becomes a vessel in navigation when it is a “watercraft practically capable of maritime transportation, regardless of its primary purpose or state of
In spite of the certainty and predictability that the panel‘s decision would bring in many if not most scenarios involving vessels under construction, the CAJUN EXPRESS appears to have all the attributes that the Supreme Court ascribed to a “vessel” in Stewart. I therefore, very respectfully, dissent.
Cynthia M. DAVIS, Plaintiff-Appellee, v. Michael McKINNEY, M.D., Being Sued Individually and In His Official Capacity; and Charles G. Chaffin, Being Sued Individually and In His Official Capacity, Defendants-Appellants.
No. 07-20184.
United States Court of Appeals, Fifth Circuit.
Feb. 21, 2008.
