Lead Opinion
This case requires us to consider the continued viability of our longstanding precedent holding that a watercraft under construction is not a “vessel in navigation” for purposes of the Jones Act. We hold that the Supreme Court’s decision in Stewart v. Dutra Construction Company,
I. Background
In 1996, Plaintiff-Appellee Rocky Cain began working as a driller on a semi-submersible drilling rig in the Gulf of Mexico for Sonat Offshore USA, Inc. Sonat later became part of DefendanL-Appellant Transocean Offshore USA, Inc. On March 1, 2000, Transocean assigned Cain as a toolpusher to the “Cajun Construction Site” in Singapore. Cain worked in Singapore for approximately six months at the PPL Shipyard, where the MW CAJUN EXPRESS was under construction. The CAJUN EXPRESS is a fifth-generation semi-submersible mobile offshore drilling rig designed to drill for oil and gas. Cain was expected to continue working on the CAJUN EXPRESS, or a sister rig, after construction was complete. Cain supervised a drill crew of seven men and was responsible for overseeing safety issues and commissioning the drilling equipment.
Although the rig was capable of self-propulsion, it was not fully capable of operating as a semi-submersible drilling rig. The necessary construction still included installation of vital pipe-handling equipment and “blisters,” which are large steel boxes welded to the rig to increase its buoyancy. Daniel Haslam, a Transocean engineer, testified that when it arrived in the Gulf of Mexico the CAJUN EXPRESS could lay pipe only under limited weather conditions. However, as a fifth generation semi-submersible unit, the most state of the art in the industry, the CAJUN EXPRESS was not designed to operate only under limited conditions. Haslam testified that no drilling contractor would have found the CAJUN EXPRESS fit for the purpose of drilling a deepwater well in the Gulf of Mexico.
On September 10, 2000, Cain was working on board the CAJUN EXPRESS. At that time, the blisters still had not-been installed and the drilling systems had not been commissioned. Cain entered a warehouse located on board the rig to retrieve a part for a member of the drill crew, whereupon he struck his head on a low-hanging light fixture and was injured. A neurosurgeon later examined Cain and recommended that he undergo physical therapy. Cain received physical therapy and continued to work on board the CAJUN EXPRESS. In April or May 2001, the CAJUN EXPRESS was finally completed and began drilling operations in the Gulf of Mexico.
Cain continued to work as a toolpusher on the CAJUN EXPRESS but was subsequently diagnosed with a herniated disc. In September 2001, he discontinued work to undergo a cervical discectomy and fusion. Cain returned to work in December 2001, when Transocean assigned him to a “work hardening” program at the Fontana Center, a facility in Lafayette, Louisiana. While participating in the work hardening program, Cain allegedly experienced elevated blood pressure and suffered additional injuries.
Cain filed suit under the Jones Act, alleging that his injuries were the result of Transocean’s negligence and the unseaworthiness of the CAJUN EXPRESS. He also alleged that Transocean was negligent in assigning him to the work hardening program. Transocean moved for summary judgment, arguing that Cain was not a Jones Act seaman at the time of his injury because the CAJUN EXPRESS was not yet a “vessel in navigation.” The district court denied Transocean’s motion, concluding that the Supreme Court’s decision in Stewart had overruled Fifth Circuit precedent concerning watercraft under construction. The district court held that the CAJUN EXPRESS was a vessel at the time of Cain’s injury because under Stewart it was capable of transporting workers and equipment over water. This court granted Transocean’s petition for leave to appeal the district court’s denial of summary judgment. Fontana Center has not submitted a brief and has not raised any arguments on appeal.
II. Discussion
We review the district court’s denial of summary judgment de novo. Solano v.
Transocean argues on appeal that under our established precedent the CAJUN EXPRESS was not a vessel in navigation, and therefore Cain was not a Jones Act seaman, because the rig was still under construction at the time of Cain’s injury. It further argues that the Supreme Court’s decision in Stewart' has effected no change on our prior case law. We agree with both contentions.
A. “Seaman” status and our established 'precedent
We begin by describing two of the principal remedies available to injured workers who ply their trade in connection with the sea: the Jones Act and the Longshore Harbor Workers’ Compensation Act (“LHWCA”). The two Acts are mutually exclusive compensation regimes. Becker v. Tidewater, Inc.,
The LHWCA provides the exclusive remedy to land-based workers who fall within its provisions. Id. at 355,
Under the Jones Act, a “seaman” is a term of art for an employee whose duties “contribute to the function of the vessel or to the accomplishment of its mission” and who has “a connection to a vessel in navigation (or to an identifiable group of such vessels) that is substantial in terms of both its duration and its nature.” Chan-dris,
We have long held that the Jones Act analysis requires a watercraft to be “in navigation,” and we have drawn a distinction between completed crafts and crafts that are under construction. A maritime worker “assisting in the building and ultimate commissioning of a launched but uncompleted vessel floating or maneuvering in navigable waters is not a seaman within the meaning of the Jones Act, because his vessel is not yet an instrumentality of commerce — private or public — and is therefore not ‘in navigation.’ ” Williams v. Avondale Shipyards, Inc.,
Similarly, in Garret, we held that an offshore drilling rig was not a vessel in navigation because, at the time of the plaintiffs injury, the structure was still undergoing final construction to make it operational as an oil and gas drilling rig.
In the instant case, the CAJUN EXPRESS was still under construction at the time of Cain’s injury. Although the rig was capable of self-propulsion and had run some test pipe, it lacked vital equipment to make it fully operational as an oil and gas drilling rig. Indeed, as Daniel Haslam testified, no drilling contractor would have found the CAJUN EXPRESS fit to drill a deepwater well in the Gulf of Mexico. The CAJUN EXPRESS was not finally completed and placed into service until April or May 2001, after Cain was injured. Thus, under established Fifth Circuit precedent, the CAJUN EXPRESS was not a vessel in navigation and Cain was not a Jones Act seaman.
B. Stewart
We now turn to the Supreme Court’s decision in Stewart v. Dutra Construction Company. In Stewart, the Court addressed whether a dredge known as the SUPER SCOOP was a vessel under the LHWCA.
The SUPER SCOOP was a floating platform with a clamshell bucket suspended beneath the water used to remove silt from the ocean floor. Stewart,
The First Circuit applied its test for vessel status found in DiGiovanni v. Traylor Bros.,
The Supreme Court rejected the First Circuit’s test for vessel status, concluding that although Congress did not define “vessel” in the LHWCA or the Jones Act, it had already defined “vessel” elsewhere at the time both acts were passed. Id. at 487-88,
Relying on § 3, the Court held that a vessel “is any watercraft practically capable of maritime transportation, regardless of its primary purpose or state of transit at a particular moment.” Id. at 497,
With respect to the requirement that a vessel be “in navigation,” the Court clarified that the requirement was meant to show only that structures could lose their vessel status if they are withdrawn from the water for extended periods. Id. at 496,
C. Stewart and vessels-to-be
The district court held that the CAJUN EXPRESS was a vessel under Stewart because not only was it capable of transportation but it had also transported workers and equipment from Singapore to the Gulf of Mexico. We disagree, however, that Stewart was intended to apply to watercraft that are still under construction. “[W]e cannot overrule the decision of a prior panel unless such overruling is unequivocally directed by controlling Supreme Court precedent.” United States v. Zuniga-Salinas,
The language in Stewart is admittedly broad, and we have recognized that the Court’s decision significantly enlarges the types of unconventional and special purpose watercraft that now must be considered vessels that might not have met the test before Stewart. See Holmes,
Stewart examined an already-completed structure in use for its intended purpose. Stewart did not concern what to do with ships and other structures under construction, and so the Court did not address whether § 3’s definition of vessel applies to incomplete structures that may be in a dry dock or a floating shipyard. In other words, Stewart did not consider whether
Other courts have similarly concluded that an incomplete structure that has not been put into navigation as an instrument of commerce is not a vessel. See Caruso v. Sterling Yacht & Shipbuilders, Inc.,
That is not to say that only commercial structures may become vessels and implicate admiralty jurisdiction. See, e.g., Sisson v. Ruby,
We further think the preclusion from vessel status of crafts still under construction serves several important goals and is consistent with the concern for avoiding uncertainties and possible oscillation in
Our cases show that shipbuilders frequently begin the construction process in a shipyard at one location and then transport the partially completed craft to another location to finish the construction process. See, e.g., Garret,
That interest is hindered with respect to the construction of watercraft because there will be many points along the continuum of a ship’s construction at which one could rationally argue it is “practically capable” of transportation and therefore a vessel. For example, a structure might become a vessel when it is merely capable of floatation but is still in dry dock; when it can be merely towed or pushed; when the navigation or propulsion systems are installed; when it has been inspected and commissioned; when it has been accepted for delivery; when a crew has been assigned; or when it is actually put to use. Our prior cases settle this uncertainty by asking whether the craft is complete. We continue to believe that “[f]or there to be a seaman, there must first be a ship,” but “an incompleted vessel not yet delivered by the builder is not such a ship.” Williams,
The difficulty of applying Stewart to vessels under construction may be seen with respect to the CAJUN EXPRESS. The testimony showed that the rig lacked vital equipment for its operations and that no drilling contractor would have found the CAJUN EXPRESS acceptable for duty in the Gulf of Mexico. It strains reason to say that a craft upon the water that is under construction and is not fit for service is practically capable of transportation.
Moreover, mobile offshore drilling units like the CAJUN EXPRESS are subject to extensive Coast Guard regulations. See 46 C.F.R. §§ 107-09. Before operations begin the unit must receive an Original Certificate of Inspection certifying that it complies with all Coast Guard requirements, including regulations governing lifesaving and firefighting equipment. Id.
In short, although Stewart instructs that the “in navigation” requirement “is relevant to whether the craft is ‘used, or capable of being used’ for maritime transportation,”
III. Conclusion
The district court’s denial of Trans-ocean’s motion for summary judgment is REVERSED and the case is REMANDED to the district court for further proceedings consistent with this opinion. Costs shall be borne by Cain.
Notes
. We do not hold that a watercraft that has not been certified by the Coast Guard can never be considered a vessel. See Holmes,
. We note that in the district court Cain argued that even if the CAJUN EXPRESS was not a vessel he was a Jones Act seaman based on his overall employment because he was a seaman before joining the CAJUN EXPRESS and his essential duties never changed. The district court did not reach this issue because it concluded that the CAJUN EXPRESS was a vessel. The parties have not briefed the issue to us, and we express no opinion on its merit. We merely note its existence and point out that it remains unresolved in the district court. Further, Cain’s claims with respect to his alleged injuries at the Fontana Center are unresolved.
Dissenting Opinion
dissenting:
This is a very difficult case, in my view. The panel’s opinion sets forth cogent arguments as to why there should be a bright-line rule as to when a vessel under construction becomes a “vessel in navigation” for purposes of determining whether an injured worker was a “seaman” within the meaning of the Jones Act. However, the language used by the United States Supreme Court in Stewart v. Dutra Construction Company
There are undoubtedly conceptual difficulties in applying the principle that a “contrivance” becomes a vessel in navigation when it is a “watercraft practically capable of maritime transportation, regardless of its primary purpose or state of
In spite of the certainty and predictability that the panel’s decision would bring in many if not most scenarios involving vessels under construction, the CAJUN EXPRESS appears to have all the attributes that the Supreme Court ascribed to a “vessel” in Stewart. I therefore, very respectfully, dissent.
.
. Id. at 497,
