135 Mich. 295 | Mich. | 1903
Early in 1902 one Robert Armstrong built a hall or auditorium for defendant. On the completion of his work, August 5, 1902, there was a balance due on his contract of $77.55. On August 11, 1902, Armstrong’s two sons, Pred and Hector, filed claims for liens against said building for labor performed by them as employes of their father. The aggregate amount of these two claims was $106.22. December 23, 1902, Armstrong and his two sons each assigned their several claims above mentioned to plaintiff, and on the following day this suit at law was commenced, which resulted in the court below in a judgment for said balance in favor of plaintiff.
It is contended that the existence of the liens of the two Armstrong boys on defendant’s property was a complete answer to plaintiff’s claim. In considering this contention, it should be borne in mind that when this suit was commenced the liens of the two boys, assigned to plaintiff, were the only liens on récord, and that the time to file liens had elapsed. It is not claimed, as manifestly it could not be, that plaintiff can maintain this suit as assignee of the lien claimants. Those claims can be enforced only in equity. Plaintiff’s right to recover at law the balance due on the contract rests upon the assignment of the principal
Nor was it necessary, as contended by defendant, that the liens should be discharged before the suit was commenced. It is true that the payment of the balance, whether before or after judgment, will entitle the defendant to such discharge; and, if that right were denied,— as it is not in this case, for the liens were discharged before judgment, — the law furnishes an adequate remedy. See section 10732, 3 Comp. Laws.
The defendant contends that there was no evidence tending to prove the service of notice containing names of laborers and subcontractors, as required by section 10713, 3 Comp. Laws. It is a sufficient answer to this contention to say that we think there was such evidence.
Defendant also contends that the service of the notice was insufficient because made by an agent who received his authority, not from the contractor, but from his attorney, who drafted the notice. The action of the attorney in directing the service was within the scope of his authority.
No other objection demands discussion.
The judgment of the court below is affirmed, with costs.