The General Services Administration Board of Contract Appeals (Board) declined to suspend defendant Secretary of the Army’s (Army) contract with intervenor VSE Corporation (VSE), even though the Board found that the contract violated regulations because the Army had failed to obtain a prior delegation of procurement authority (DPA).
Protest of CACI, Inc.,
No. 11523-P,
BACKGROUND AND PROCEDURAL HISTORY
The Department of the Army, U.S. Army Troop Support Command, solicited bids on April 1, 1991 for providing engineering services and data рrocessing support services to Belvoir Research, Development and Engineering Center. Appellant CACI and in-tervenor VSE were among the companies that submitted bids in response. The con *1234 tract was awаrded to VSE on September 30, 1991, and CACI filed a protest with the Board on October 15, 1991. The protest had four counts: Count I alleged that the Army had violated Federal Information Resources Management Regulations, 41 C.F.R. subpart 201-23.1 (1990), by fаiling to obtain a DPA from the Administrator of General Services Administration (GSA)'before proceeding with the acquisition; Count II attacked the adequacy of the Army’s discussions with bidders; Count III alleged that agency actions may have given VSE. an improper advantage; and Count IV alleged that the Army’s evaluation of the proposals was improper.
CACI moved for summary relief on Count I, requesting an order suspending the procurement until the Army obtained a DPA. On November 15, 1991, the Board denied the relief sought. The Board found no factual dispute concerning the lack of the required DPA: “The Army candidly acknowledges that it did not obtain one, although it was required to do so ...” The Bоard declined, however, to suspend contract performance (by suspending GSA’s procurement authority) until the Army obtained a DPA, because a suspension of VSE’s on-going services would be disruptive and detrimental to the Army’s mission. In a separate opinion on the same date, the Board denied the Army’s motion to dismiss Counts II and III (as failing to state a valid basis of protest) and Count IV (as untimely because CACI should have known the basis for the count earlier).
In its December 19,1991 final decision on the merits, the Board again refused to suspend the contract, because the Army needed thé services on an on-going basis and had taken necessary steps to obtain а DPA with dispatch. CACI appealed to this court.
DISCUSSION
The Board’s decision on a question of law is not final or conclusive, although its decision on a question of fact is final unless fraudulent, arbitrary, capricious, so grossly errоneous as to necessarily imply bad faith, or unsupported by substantial evidence. 41 U.S.C. § 609(b).
The two issues before us are purely legal in nature and thus freely reviewable: (1) for purposes of decision, may we disregard the Army’s сoncession to the Board that a DPA was required for the contract, and (2) does the Army’s failure to obtain a DPA before contracting for VSE’s services render the contract void?
A.
The Army asks us to disregard its earlier cоncession that a DPA was required, because the Army’s former position resulted from a misinterpretation of the applicable regulations. The 1991 regulations required acquisition-specific DPAs for all automatic dаta processing (ADP) services (now called federal information processing (FIP) services), both support-type and non-support-type, with value exceeding $2.5 million. 41 C.F.R. § 201-20.305-1 (1991). This regulation was effective April 29, 1991. 55 Fed.Reg. 53,386 (199.0); 56 Fed.Reg. 4,948 (1991). Under these regulations the Army would have been required to obtain a DPA for the contract in question because the expected cost of the services was $3 million (according to Solicitation Sec. H.15). Under thе 1990 regulations, specific DPAs were required for ADP nonswpport services contracts with value exceeding $2 million. 41 C.F.R. § 201-23.-104-5 (1990). A 1990 regulation, however, gave agencies blanket procurement authority to contract for ADP support services, regardless of cost, without prior approval. 41 C.F.R. § 201-23.104-6 (1990). This regulation was effective October 1, 1990. 55 Fed.Reg. 30,702 (1990); 55 Fed.Reg. 34,719 (1990).
The Army and VSE now argue that the Army had blanket procurement authority for its contract with VSE because first, the 1990 regulations were still in effect when the bid solicitation was published on April 1, 1991, and second, the contract was for ADP support services. The Army thus asserts that it should not be bound by its earlier mistaken interpretation of the law.
*1235 CACI argues that, since the existence of a blanket procurement authority depends on whether the contract was for ADP support services or non-support services, and since this is an issue that the Army did not raise below, the Army has waived the issue. Thus, says CACI, the Army must be bound by its concession that a DPA was required.
The Army admitted to the Board that a DPA was required but had not been obtained. It is too late now for the Army to change its position and thereby assert for the first time on appeal a point which it did not raise before the Board. Because of the Army’s admission, the Board made no factual findings or conclusions on the issue of a blanket procurement authority. The proper timе for the Army to have raised this issue, which turns on underlying factual questions, was before the Board; it would be unfair to appellant and would disrupt the orderly conduct of litigation if we allowed the Army to change its position at this stage.
See Jamesbury Corp. v. Litton Indus. Prods., Inc.,
B.
40 U.S.C. § 759 vests in the GSA Administrator exclusivе authority to provide for the purchase, lease and maintenance of ADP equipment.
Contel Fed. Sys., Inc.,
No. 11060-P, 91-2 B.C.A. (CCH) ¶ 23,764 at 119,035,
CACI arguеs that because the Army had no delegation of procurement authority from GSA, the Army had no actual authority to contract with VSE, and therefore the contract is void. VSE argues that the contract is not void becаuse CACI has not shown the plain illegality required by
John Reiner & Co. v. United States,
The issue is one that this court has not directly addressed before. 1 In Reiner, the Court of Claims held that:
In testing the enforceability of an award made by the Government, where a problem of the validity of the invitatiоn or the responsiveness of the accepted bid arises after the award, the court should ordinarily impose the binding stamp of nullity only when the illegality is plain. If the contracting officer has viewed the award as lаwful, and it is reasonable to take that position under the legislation and regulations, the court should normally follow suit.
Id.
at 440. The court subsequently explained that plain illegality exists when “we find the illegality in the award to be plаin on the face of the statute and the regulations.... Where illegality is clear, we have no choice but to hold the award and contract to be invalid.”
Schoenbrod v. United States,
*1236
In
Protest of Computervision Corp.,
No. 8709-P, 87-
As the Claims Court has said:
It is a well recognized principle of procurement law that the contracting officer, as agent of the executive depаrtment, has only that authority actually conferred upon him by statute or regulation. If, by ignoring statutory and regulatory requirements, he exceeds his actual authority, the Government is not es-topped to deny the limitations on his authority, even though the private contractor may have relief on the contracting officer’s apparent authority to his detriment, for the contractor is charged with notice of all statutory and regulatory limitations.
Prestex, Inc. v. United States,
The government “is not bound by its agents acting beyond their authority and contrary to regulation.”
Urban Data Sys., Inc. v. United States,
We note that 40 U.S.C. § 759(f)(5)(B) gives the Bоard discretion to suspend, revoke, or revise an ADP services contract by suspending, revoking, or revising the Administrator’s procurement authority:
If the board determines that a challenged agency action violatеs a statute or regulation or the conditions of any delegation of procurement authority issued pursuant to this section, the board may suspend, revoke, or revise the procurement authority of the Administrator оr the Administrator’s delegation of procurement authority applicable to the challenged procurement.
However, the language of this provision does not permit the Board to ratify a contraсt that an agency had no authority to create initially. If the language is clear, the plain meaning of the statute will be regarded as conclusive.
See Sullivan v. Stroop,
Thus, because the Army lacked procurement authority to contract with VSE and the Board has no power to ratify the contract or otherwise cure this fatal defect, we find that the contract is void. This does not mean that minor deviations from the applicable regulatiоns will automatically render a contract void.
Cf. Andersen Consulting v. United States,
CONCLUSION
The decision of the Board is
REVERSED.
Notes
.
But see United States v. Amdahl Corp.,
