2009 Ohio 1786 | Ohio Ct. App. | 2009
{¶ 2} On January 11, 2007, CAC Building Properties, L.L.C. ("CAC"), filed suit against the city, Terrace Construction Company, Inc. ("Terrace"), and the Vallejo Company ("Vallejo") for their alleged involvement in damages arising from construction failures. On March 13, 2008, CAC filed its first amended complaint asserting inverse condemnation, nuisance, trespass, interference with business relationships, conversion, and negligence. On that same date, the city filed its answer asserting several affirmative defenses, including sovereign immunity.
{¶ 3} On June 11, 2008, the city filed a motion for summary judgment arguing that it is immune from the claims, that it is not primarily or secondarily liable for the damages, and that CAC's inverse condemnation claim is not recognized under Ohio law. On July 15, 2008, Vallejo and Terrace filed motions for partial summary judgment.
{¶ 4} On August 19, 2008, the trial court denied the city's motion for summary judgment, holding that "factual issues remain in dispute on the application of the governmental immunity statutes precluding an entry of summary judgment in favor of the city of Cleveland." The trial court also *5 granted summary judgment in favor of Terrace and Vallejo. On August 22, 2008, the city filed a timely notice of appeal.
{¶ 5} The following facts gave rise to this appeal. In March 2006, the city began construction to prepare for the Euclid Corridor Transportation Project in Cleveland. The city's work included upgrades to utility vaults below Euclid Avenue. The nearby CAC Building had five utility vaults located under Euclid Avenue.
{¶ 6} The city hired Terrace as the contractor for the work to be done in front of the CAC Building. Terrace hired subcontractors, including Vallejo, "to make vault improvements below the sidewalks." These improvements included "constructing underground concrete masonry units ("CMU"), walls to provide for an under-sidewalk access to CAC Building's electrical component service room and electric transformers."
{¶ 7} On March 28 and 29, 2006, Terrace and Vallejo worked on constructing a concrete masonry wall under the CAC Building. On March 29, 2006, the wall collapsed, and the low strength mortar flooded the CAC Building, destroying electrical and mechanical equipment.
{¶ 8} On September 27, 2006, Terrace left the excavations open, which exposed the electrical switchgear. As the result of a thunderstorm, water touched the CAC Building's electrical switchgear and caused an explosion and fire. *6
{¶ 10} "I. The trial court erred when it denied the motion for summary judgment filed on behalf defendant-appellant, the city of Cleveland, with regard to the claim of trespass because the city is immune from this claim pursuant to O.R.C. §
{¶ 11} "II. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland with regard to the claim of interference with business relationships because the city is immune from this claim pursuant to O.R.C. §
{¶ 12} "III. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland with regard to the claim of *7
conversion because the city is immune from this claim pursuant to O.R.C. §
{¶ 13} "IV. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland with regard to the claim of nuisance because the city is immune from this claim pursuant to O.R.C. §
{¶ 14} "V. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland with regard to the claim of negligence because the city is immune from this claim pursuant to O.R.C. §
{¶ 15} Within these assignments of error, the city argues that the trial court erred when it determined that it was not entitled to summary judgment based upon sovereign immunity. We find merit in this argument.
{¶ 17} It is well established that the party seeking summary judgment bears the burden of demonstrating that no issues of material fact exist for trial. Celotex Corp. v. Catrett (1986),
{¶ 18} In Dresher v. Burt,
{¶ 19} This court reviews the lower court's granting of summary judgment de novo. Brown v. Scioto Cty. Commrs. (1993),
{¶ 22} R.C.
{¶ 23} It is undisputed between the parties that the city is a political subdivision. Ordinarily, the city is not liable for damages resulting from the acts of its employees in connection with a governmental or proprietary function; therefore, unless an exception applies, the city is immune.
{¶ 25} Under R.C.
{¶ 26} is not one described in division (C)(1)(a) or (b) of this section and is not one specified in division (C)(2) of this section and *** is one that promotes or preserves the public peace, health, safety, or welfare and that involves activities that are customarily engaged in by nongovernmental persons." (Emphasis added.)
{¶ 27} Under R.C.
{¶ 28} The city argues that the R.C.
{¶ 29} CAC argues that the city was engaged in the maintenance of a utility (a proprietary function under R.C.
{¶ 30} The city relies on Music Centers, Inc. v. Cuyahoga Falls, Ninth Dist. No. 21802,
{¶ 31} We find that Music Centers is directly on point. The city has shown that the problem with the utility occurred during a public improvement project and/or a road or sidewalk repair, both of which are governmental functions. In fact, CAC managing member, Robert Munson, testified via deposition that "the Euclid Corridor project and the related vault work under and attached to [the building] was part of a project to maintain, repair, or construct roads, streets, or sidewalks." Mr. Munson also testified that he agreed the work "involved construction of a public improvement." Further, another CAC representative, Thomas Munson, testified that he believed that the city's goal was to "construct a public improvement."
{¶ 32} Finally, in its first amended complaint, CAC stated "the city began construction and improvements to prepare for a public transportation project known as the `Euclid Corridor Project.' *** The city hired Terrace as a Prime Contractor for a portion of this work in front of the CAC Building. *** Among other things, Terrace began certain `vault improvements' below the sidewalks in front of the CAC Building."
{¶ 33} The fact that a utility may have been involved in this project does not transform the public improvement project into a utility venture. As discussed above, in support of its motion for summary judgment, the city provided evidence that the vault work was related to the Euclid Corridor Project. CAC has not presented any evidence to refute that contention. Because the *14 vault work was related to the Euclid Corridor Project, it must be considered a governmental function pursuant to Music Centers, supra.
{¶ 34} Accordingly, the city is not liable under the R.C.
{¶ 36} Accordingly, the city's first five assignments of error are sustained.
{¶ 37} As discussed above, the city's remaining assignments of error are not properly before us; therefore we do not address them.
{¶ 38} Judgment reversed and remanded.
This cause is reversed and remanded to the lower court for further proceedings consistent with this opinion.
It is ordered that appellants recover of said appellee costs herein taxed.
The court finds there were reasonable grounds for this appeal. *15
It is ordered that a special mandate issue out of this court directing the common pleas court to carry this judgment into execution.
A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the Rules of Appellate Procedure.
CHRISTINE T. McMONAGLE, P.J., and MELODY J. STEWART, J., CONCUR.
VI. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland, because the city is not primarily or secondarily liable for the claim of trespass presented by plaintiff-appellee, CAC Building Properties, LLC.
VII. The trial court erred when it denied the motion for summary judgment filed on behalf of the city of Cleveland, because the city is not primarily or secondarily liable for the claim of interference with business relationships presented by plaintiff-appellee, CAC Building Properties, LLC.
VIII. The trial court erred when it denied the motion for summary judgment filed on behalf of the defendant-appellant, City of Cleveland, because the city is not primarily or secondarily liable for the claim of conversion presented by plaintiff-appellee, CAC Building Properties, LLC.
IX. The trial court erred when it denied the motion for summary judgment filed on behalf of defendant-appellant, the city of Cleveland, because the city is not primarily or secondarily liable for the claim of nuisance presented by plaintiff-appellee, CAC Building Properties, LLC.
X. The trial court erred when it denied the motion for summary judgment filed on behalf of defendant-appellant, the city of Cleveland, because the city is *16 not primarily or secondarily liable for the claim of negligence presented by plaintiff-appellee, CAC Building Properties, LLC.
XI. The trial court erred when it denied the motion for summary judgment filed on behalf of defendant-appellant, the city of Cleveland, because the city is not primarily or secondarily liable for the claim for punitive damages presented by plaintiff-appellee, CAC Building Properties, LLC.
XII. The trial court erred when it denied the motion for summary judgment filed on behalf of defendant-appellant, the city of Cleveland, where the motion established the claim for inverse condemnation is not a direct action recognized by Ohio courts, and was not properly before the trial court.