C. T. Fitts & Co. v. Reinhart

102 Iowa 311 | Iowa | 1897

Ladd, J.

1 The plaintiff entered into a written contract with the defendant to furnish labor and material necessary for the construction of a steam-heating plant in the Reinhart Flats, in Sioux City, according to certain plans and specifications. The contract provides: “All work to be done under the supervision and to the satisfaction of said architect (acting as said owner’s agent). * * * The last and final payment to be made within ten days after all work is completed, * * * provided that for all payments a certificate shall be obtained from and signed by said architect.” No certificate was furnished, and the defendant claims that, for this reason, the action cannot be maintained. He relies on McNamara v. Harrison, 81 Iowa 486 (46 N. W. Rep. 976), where it is held that parties may bind themselves to make payment on the certificate or estimate of some third person, such as an engineer or architect; and unless there be some good reason why it is not furnished, no action can be maintained. The evidence in this case furnishes a very good excuse for not obtaining the required certificate. Before the plant was completed, the defendant dispensed with *313the services of his architect, and directed his engineer to see that it was put in right. By the terms of the contract, the architect was to act as his agent in superintending the work, and in making the certificates upon which payments might be made. Certainly, after his discharge, the defendant would not be bound by anything he might do. If so, then the plaintiff was relieved from the conditions of the contract requiring the approval of this architect and his certificate before payment.

2 3 II. The contract required the plaintiff to furnish a steam-heating and power plant, in strict accordance with the plans and specifications. This was not done. That some of the work performed and materials furnished were as expensive as that agreed does not always answer the objection to a failure to comply with the terms of the contract. One main and some of the pipes were too small. Many valves required were omitted, and the ceiling plates were not as agreed. The tank was necessarily smaller than called for, but a proper discount was allowed on this. The evidence, however, fails to show the cost of procuring and placing larger pipes and main, necessary valves, and changing the ceiling plates. True, estimates were given of the cost of making the plant comply with the contract, but these were on the basis of so changing the system as to connect all pipes with the mains from the top, instead of the side. The defendant, at considerable cost, had it so changed, and some other defects remedied. Much evidence was introduced on the question as to whether a top or a side connection is preferable. We need not determine, if we could, which method is best. The defendant made no objection to the side "connection, nor did his architect or engineer, until the work was done and all pipes laid. Had he desired the other method, he should have so indicated in time *314to enable plaintiff to comply with his wishes. That adopted is approved by many experts, and believed by the plaintiff to be preferable. As the cost of making such changes and furnishing such material as defendant was entitled to is not shown, damages cannot be allowed on the counter-claim.

III. An engine was purchased at the agreed price of three hundred and seventyrfive dollars, and after-wards a larger one ordered. The defendant claims the last one was not to exceed in cost the sum of fifty dollars more than that first bought, while the plaintiff says he was to receive the market price. The evidence is conflicting, but we think the circumstauces sustain the contention of the defendant. It is insisted the engine was guaranteed to do the work for which it was purchased, and failed to do so. This need not be considered, as the damages occasioned by such failure have not been proven. Threshing Machine Co. v. Haven, 65 Iowa, 359 (21 N. W. Rep. 677).

IY. There are other items set out in the petition for which recovery is claimed, but no evidence was introduced tending to show that its articles were ever sold or delivered to the defendant. The contract price for the plant was four thousand, five hundred and sixty-five dollars, and the price allowed for the engine four hundred and twenty-five dollars. From these must be deducted the two thousand five hundred dollars paid, and the sixty dollar reduction on the tank, leaving the sum of two thousand four hundred and thirty dollars owing plaintiff, with interest at six per cent, per annum from February 23, 1893. What has been said indicates that the costs on the counter-claim were properly taxed to the defendant by the district court. The costs in this court will be taxed to the plaintiff, — Modified and affirmed,