C.S. Behler, Inc. v. Daly & Zilch, Inc.C.S. Behler, Inc. v. Daly & Zilch, Inc.
—Order insofar as appealed from unanimously reversed on the law without costs, cross motion denied, complaint reinstated, motion granted in part and judgment ordered in accordance with the following Memorandum: Plaintiff commenced this action seeking to recoup $28,399.05 on the bond that discharged its mechanic’s lien. Defendant Walter & SCI Construction (USA), Inc. (Walter & SCI), the general contractor on a public improvement project, subcontracted with defendant Daly & Zilch, Inc. (Daly) for insulation and masonry work, and Daly hired plaintiff to supply certain materials. Plaintiff thereafter informed Walter & SCI that it had not received payment from Daly and, in March 1997, filed a mechanic’s lien in the amount of $28,399.05. When the lien was filed, Walter & SCI had paid only $836,571 of the $896,265 owing to Daly. Prior to March 1997, the remaining balance on
We note that the court properly denied plaintiff’s motion with respect to Daly because Daly had not yet served an answer and thus issue had not been joined (see, CPLR 3212 [a]). The court erred, however, in denying that part of plaintiff’s motion seeking summary judgment on the first cause of action with respect to the remaining defendants. A plaintiff may recover on a bond if it demonstrates that it had a valid mechanic’s lien (see, Worlock Paving Corp. v Camperlino,
We therefore reverse the order insofar as appealed from, deny the cross motion for partial summary judgment, reinstate the complaint, grant plaintiff’s motion against all defendants but Daly insofar as it seeks judgment on the bond that discharged the mechanic’s lien, and order that judgment be entered in plaintiff’s favor in the amount of $28,399.05 together with interest awarded from the date of the commencement of the action (see, CPLR 5001 [a]). (Appeal from Order of Supreme Court, Niagara County, Joslin, J. — Summary Judgment.) Present — Pine, J. P., Wisner, Scudder and Kehoe, JJ.