45 Iowa 79 | Iowa | 1876
The evidence shows that by the last day'of August, 1872, the road was ironed to the Elkport depot, which was a little more than three-fourths of a mile from the Elk-port post office, and that a construction train ran over it on that day; that on the 1st day of September a passenger train ran to within about 200 yards of the depot, but it does not appear whether it ran within a mile of the Elkport post office or not. The evidence further shows that afterwards neither freight nor passenger trains were run for a considerable time, but that a mixed train, which was essentially a construction train, was run for the purpose of hauling- timber to build a bridge, and to accommodate what travel there was. After about ten days the construction train was taken off, and a tri-weekly freight train with a, caboose attached was run. The depot was only partially built on the 1st day of September, but was completed by the last of September.'
Whatever doubt there is about the case arises upon the question as to whether the road was running by the first day of September, 1872, to within a mile of the Elkport post office, within the meaning of the contract.
'' An unmixed construction train was running earlier than ‘that, but we do not think that the running of that train was a performance of the contract. The defendant was not inter 7 ested in the running of a train that was used simply in the
In our opinion the road was running to the depot, within the meaning of the contract, by the 1st day of September, and the plaintiff was. entitled to recover.
Reversed.