109 N.Y. 291 | NY | 1888
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *293
We are unable to deny the force of several propositions relied upon by the appellant. By the terms of the contract the chief engineer of the Construction Company was made the arbitrator between the parties to settle all differences arising out of the contract, to estimate the quantities and amounts of the several kinds of work and make monthly certificates for the same, reserving ten per cent thereof. The final payment to be made was provided for in these words: "But in case of the full completion of said work by the party of the first part, then, and upon the final estimate thereof by the said chief engineer, the said party of the second part agrees to pay, within ten days, to the party of the first part, the full amount then due, including the reserve of ten per cent." Under this provision the certificate of the engineer became a condition precedent to the plaintiff's right of action. The chosen arbitrator was to fix the amount of the final payment and the same was to become due in ten days after such final estimate was made. The provision comes clearly within the rule which makes such certificate a condition precedent to the right of recovery. (Pres't, etc., D. H. CanalCo. v. Pa. Coal Co.,
This doctrine proceeds upon an erroneous view of the rights of the parties. The action was not brought upon a quantum meruit,
upon the ground that the contract had been rescinded and no longer subsisted, or to rescind or annul it. On the contrary, it was brought to enforce it and necessarily affirmed it. (Quinn
v. Van Pelt,
The judgment should be reversed and a new trial granted, costs to abide the event.
All concur.
Judgment reversed. *297