45 N.J.L. 213 | N.J. | 1883
The opinion of the court was delivered by
The plaintiffs were non prossed at the Circuit in their suit for a balance claimed upon a building contract between the plaintiffs and defendants. The contract made the price, $17,330, payable in eight instalments. It provided that in each payment a certificate should be obtained, signed by P. C. Keeley, architect, and that the eighth payment, being the balance of $4330, was to be paid on the certificate of the architect in three months after the full completion of the entire work. The plaintiffs agreed to well and sufficiently erect and finish all the carpenter-work, joiner-work, carver-work, hardware, glass and glazing required to finish the building in a good, workmanlike and substantial manner, to the satisfaction and under the direction of the said architect, to be testified by a writing or certificate under the hand of the said architect.
The case was withheld from the jury because of the failure of the plaintiffs to show any certificate of the architect, and the absence of any proof sufficient to be submitted to the jury
The rule is entirely settled that under a building contract containing such clauses, the production of the stipulated certificate is a condition precedent to the institution of suit for money payable upon such contract while the provision remains in force. Morgan v. Birnie, 9 Bing. 670.
Where the contract has been performed and the builder has, by fulfilling his contract obligation, become entitled to such certificate, it is a fraud upon him to withhold or refuse it, for which the architect is liable if such refusal be with knowledge that the builder has fully performed his work. And an employer who acts in collusion with such architect in withholding it is subjected to a like liability.
A court of equity will also in such cases afford relief. An employer may demand of his architect faithful performance of the duty assumed by him, to skilfully examine and honestly report upon the contractor’s execution of his contract, and for a false certificate, under which he is made to pay unearned money, may recover his damages from the person so unfaithful to his trust. Such conditions, however, may be waived by him in whose interest they are engrafted in the contract either by express words, relieving the builder therefrom, or waiver may be inferred from such acts, conduct or declarations of the employer as are inconsistent with the 'purpose of exacting performance, and the question of waiver is one of fact for the jury. The plaintiffs, on the trial of tiie cause, produced no certificate whatever of the architect, and they made no attempt to show that the defendant, or any agent of the defendant, had expressly dispensed with its production. It was shown that the first seven payments had been made to the plaintiffs without the presentation of any certificate, and it is contended by the plaintiff that this, coupled with other"circumstances attending the dealings of the parties in respect to the payment of the last instalment, was evidence from which a jury would have been justified in finding a waiver of the condition annexed to the last payment. The circumstance
Such certificate was not produced at the trial, and the
The course pursued at the trial in non-suiting the plaintiffs was a proper one, and the rule should be discharged, with costs.