153 Mass. 517 | Mass. | 1891
It is well established law, that, where one contracts to furnish labor and materials, and construct a chattel or build a house on land of another, he will not ordinarily be excused from performance of his contract by the destruction of the chattel or building, without his fault, before the time fixed for the delivery of it. Adams v. Nichols, 19 Pick. 275. Wells v. Calnan, 107 Mass. 514. Dermott v. Jones, 2 Wall. 1. School Trustees of Trenton v. Bennett, 3 Dutcher, 513. Tompkins v. Dudley, 25 N. Y. 272. It is equally well settled, that when work is to be done under a contract on a chattel or building which is not wholly the property of the contractor, or for which ne is not solely accountable, as where repairs are to be made on the property of another, the agreement on both sides is upon the implied condition that the chattel or building shall continue in existence, and the destruction of it without the fault of either of the parties will excuse performance of the contra<jt, and leave no right of recovery of damages in favor of either against the other. Taylor v. Caldwell, 3 B. & S. 826. Lord v. Wheeler, 1 Gray, 282. Gilbert & Barker Manuf. Co. v. Butler, 146 Mass. 82. Eliot National Bank v. Beal, 141 Mass. 566, and cases there cited. Dexter v. Norton, 47 N. Y. 62. Walker v. Tucker, 70 Ill. 527. In such cases, from the very nature of the agreement as applied to the subject matter, it is manifest that, while noth
The fundamental question in the present case is, What is the true interpretation of the contract? Was the house while in the process of erection to be in the control and at the sole risk of the defendant, or was the plaintiff to have a like interest, as the builder of a part of it ? Was the defendant’s undertaking to go on and build and deliver such a house as the contract called for, even if he should be obliged again and again to begin anew on account of the repeated destruction of a partly completed building by inevitable .accident, or did his contract relate to one building only, so that it would be at an end if the building, when nearly completed, should perish without his fault ? It is to be noticed that his agreement was not to build a house, furnishing all the labor and materials therefor. His contract was of a very different kind. The specifications are incorporated into it, and it appears that it was an agreement to contribute certain labor and materials towards the erection of a house on land of the plaintiff, towards the erection of which the plaintiff himself was to contribute other labor and materials, which contributions would together make a completed house. The grading, excavating, stone-work, brick-work, painting, and plumbing were to be done by the plaintiff.
Immediately before the fire, when the house was nearly completed, the defendant’s contract, so far as it remained unperformed, was to finish a house on the plaintiff’s land, which had been constructed from materials and by labor furnished in • part by the plaintiff and in part by himself. He was no more responsible that the house should continue in existence than the plaintiff was. Looking at the situation of the parties at that time, it was like a contract to make repairs on the house of another. His undertaking and duty to go on and finish the work was upon an implied condition that the house, the product of their joint contributions, should remain in existence. The destruction of it by fire discharged him from his contract. The
It seems very clear that, after the building was burned, and just before the day fixed for the completion of the contract, the defendant could not have compelled the plaintiff to do the grading, excavating, stone-work, brick-work, painting, and plumbing for another house of the same bind. The plaintiff might have answered, “ I do not desire to build another house which cannot be completed until long after the date at which I wished to use my house. My contract related to one house. Since that has been destroyed without my fault, I am under no further obligation.” If the plaintiff could successfully have made this answer to a demand by the defendant that he should do his part towards the erection of a second building, then certainly the defendant can prevail on a similar answer in the present suit. In other words, looking at the contract from the plaintiff's position, it seems manifest that he did not agree to furnish the work and materials required of him by the specifications for more than one house, and if that was destroyed by inevitable accident, just before its completion, he was not bound to build another, or to do anything further under his contract. If the plaintiff was not obliged to make his contribution of work and materials towards the building of a second house, neither was the defendant. The agreement of each to complete the performance of the contract after a building, the product of their joint contributions, had been partly erected, was on an implied condition that the building should continue in existence. Neither can recover anything of the other under the contract, for neither has performed the contract so that its stipulations can be availed of. The case of Cook v. McCabe, 53 Wis. 250, was very similar in its facts to the one at bar, and identical with it in principle. There the court, in an elaborate opinion, after a full consideration of the authorities, held that the contractor could recover of the owner a pro rata share of the contract price for the work performed and the materials furnished before the fire. Clark v. Franklin, 7 Leigh, 1, is of similar purport.
What are the rights of the parties in regard to what has been done in part performance of a contract in which there is an implied condition that the subject to which the contract relates
In this country, where one is to make repairs on a house of another under a special contract, or is to furnish a part of the work and materials used in the erection of a house, and his contract becomes impossible of performance on account of the destruction of the house, the rule is uniform, so far as the authorities have come to our attention, that he may recover for what he has done or furnished. In Cleary v. Sohier, 120 Mass. 210, the plaintiff made a contract to lath and plaster a certain building for forty cents per square yard. The building was destroyed by a fire which was an unavoidable casualty. The
The only question that remains in the present case is one of pleading. The defendant is entitled to be compensated at the contract price for all he did before the fire. The plaintiff is to be allowed for all his payments. If the payments are to be treated merely as advancements on account of a single entire
We are of opinion that the consideration which the defendant was to receive was an entire sum for the performance of the contract, and that the payments made were merely advances on account of it, and that, on his failure to perform the contract, there was a failure of consideration which gave the plaintiff a right to sue for money had and received, and that the like failure of consideration on the other side gave the defendant a right to sue on an implied assumpsit for work done and materials found.
The $38 due from the defendant to the plaintiff cannot be recovered in this action. The report and the pleadings show that the suit was brought under an assignment for the benefit of the insurers, to recover damages for a breach of the contract for the erection of the building, and not to recover the value of the shingles or weights carried away from the ruins.
According to the terms of the report, the ruling being wrong, such order may be made as this court shall direct. A majority of the court are of opinion that the verdict should be set aside, and the defendant be given leave to file a declaration in set-off, if he is so advised, on such terms as the Superior Court deems reasonable.
Verdict set aside.