Lead Opinion
¶ 1. Thе circuit court granted summary judgment of dismissal to the defendants on the plaintiffs' negligence and nuisance claims.
I. BACKGROUND
¶ 2. This action arises out of a project to design and install a system to lower the water level (the Project) of Shell Lake (the Lake). The Lake is a bowl-shaped lake, covering approximately 2500 acres. It is located entirely within the boundaries of the City of Shell Lake, Wisconsin (the City). There are more than 400 properties abutting the Lake. The plaintiffs and intervening plaintiffs (collectively, plaintiffs) own properties on the Lake.
¶ 3. The surface water elevation of the Lake has fluctuated significantly over the past century. In the most recent several decades, the water level of the Lake has been rising. As a result, in 1977, the City entered into an agreement with the Wisconsin Dеpartment of Natural Resources (DNR) to raise the ordinary high water mark of the Lake. This agreement was developed to aid the City with adoption and administration of a shoreland zoning ordinance, with the understanding that a surface water drain would be installed in order to maintain the water level at or below the ordinary high water mark set by the DNR.
¶ 4. In the meantime, property development surrounding the Lake continued. The water level continued to rise. In 1987-1988, the U.S. Army Corps of Engineers conducted an investigation of the problem and issued a report that suggested plans for water diversion and associated costs. The report showed that the water level had risen in the 1980s and 1990s, and predicted that the water level would continue to rise. It
Realizing the potential for flooding of their properties, area residents continue to be concerned despite the fact that the lake level has dropped during the past year. Accordingly, city officials continue to express a need for the development of mеasures to alleviate the flooding problem.
U.S. Army Corps of Engineers, Reconnaissance Report, Flood Control section 205 at 11 (March 1988 draft).
¶ 5. The 1988 report ultimately concluded:
The level of Shell Lake is presently down from the [] high level of elevation 1221.99 feet msl reached in 1986. However, historical accounts indicate that the lake has the potential for rising to much higher levels. With the return of normal precipitation or precipitation at levels experienced during the period 1977-1986, rising lake levels can once again be expected. Any appreciable rise in the lake level above the high recorded in 1986 could result in catastrophic losses to existing developments.
Id. at 29.
¶ 6. The water level appeared to stabilize in the years immediately following the Army Corps of Engineers report, and plans to install a drain were put on hold. By 1994, the surface water drain that was to have been installed as a result of the 1977 agreement between the DNR and the City was not in place. The DNR investigations of the water level determined that the ordinary high water mark, based on erosion and analyses of vegetation changes, had risen again. Accordingly, the DNR declared an even higher ordinary high water mark. The DNR's report noted thаt a substantial amount of
¶ 7. In 1997, after the water level had reached 1222.24 feet, mean sea level (msl), then a record high, the City petitioned the DNR to divert water into Sawyer Creek. However, the DNR denied the City's permit application because of the expected negative ecological effects the proposed plan would have on Sawyer Creek.
¶ 8. In 2000, the City met with the DNR staff to review several new options for water diversion. In 2001, the City applied to the DNR for a new permit, this time to divert lake water into the Yellow River. The Project involved placing structures on the bed of the Lake and in the Yellow River that would facilitate the diversion. The Project also called for the construction and installation of drainage pipe along an approximately 4.5 mile route from the Lake to the Yellow River. The intent of the Project was to maintain the Lake near the ordinary high water mark set in 1994. The DNR granted the City's petition for the Project. The estimated cost exceeded $1,600,000. The City intended to fund the project, in part, through $650,000 of special assessments on riparian property owners. In the meantime, emergency pumping was undertaken to temporarily lower the water level.
¶ 9. The City contracted with engineer Daniel Kling (Kling) and his company, Envirosystems Consulting Group, Inc. (Envirosystems), for design and engineering; with Advanced Drainage Systems, Inc. (Advanced Drainage) for the supply of pipes; and with Bob Thompson & Sons and Thompson Sand & Gravel (Thompson) for installation and general contractor services.
¶ 10. Envirosystems created the plans and specifications for the Project. The plans called for 24,000 feet of light-weight high-density polyethylene pipe rated to
¶ 11. The Project construction proceeded in the late summer and fall of 2002 when the water level ranged between 1223.91 and 1224.44 feet msl.
¶ 12. While the attempted repair was underway, the City hired an engineering firm to investigate the Project and to propose solutions. The resulting report concluded that the pipeline's failure stemmed from design and material defects, failure to test the materials and problems with installation. The report suggested several alternative solutions to appropriately accommodate the water pressure, including reconstruction of the pipeline, the use of new types of piping made of different materials, and the insertion of a "slip-line" within the existing pipe.
¶ 13. The City ultimately chose to insert a slip-line of solid wall 80 psi pipe. By March 2004, after the new system of pipe had been in place and iunctioning for several months, the water level had receded to 1222.18 feet msl.
¶ 15. The plaintiffs moved for class certification, pursuant to Wis. Stat. § 803.08, and the defendants moved to change venue, pursuant to Wis. Stat. § 801.52. On October 14,2003, the circuit court denied the request to certify and changed the venue to Burnett County. It also dismissed the City from the lawsuit.
¶ 16. The court of appeals affirmed the circuit court. Butler v. Advanced Drainage Sys., Inc.,
II. DISCUSSION
A. Standard of Review
¶ 17. This case requires us to review summary judgment dismissing the plaintiffs' claims against the defendants. Whether summary judgment was properly
B. Summary Judgment Principles
¶ 18. Every decision on a motion for summary judgment begins with a review of the complaint to determine whether, on its face, it states a claim for relief. Hoida, Inc. v. M&I Midstate Bank,
C. Public Policy Factors
¶ 19. When liability fоr negligence is established, we may preclude liability based on public policy factors. Coffey v. City of Milwaukee,
¶ 20. We have cautioned against applying public policy factors to preclude liability where the facts are too complicated and warrant development of the factual
D. Public Policy Application
¶ 21. Here, the complaint states a claim for relief and the answer joins issue. The relevant facts relating to the attempted water abatement are not disputed. They show that the City contracted with the defendants to lower the water level in the Lake and that the defendants' efforts were not successful. Therefore, we conclude that the facts of record are sufficiently developed for us to undertake a public policy analysis. When we do so, "we assume there is negligence and that the negligence was a cause of the injury, but for reasons of public policy, we prevent the claim from proceeding."
¶ 23. In Rockweit, we determined, based on public policy, that a friend who visited a family around a campfire and was the last to leave the campfire could not be held liable for injuries sustained by a young child, who later fell into the un-extinguished fire's hot coals. In explaining our decision, we noted that the child's injuries could have occurred in exactly the same manner even if the friend had not been present at the campground. Id. at 428. We also noted that the child's parents were aware of the open hazard the fire's coals presented, yet they had not secured the child's safety. Id. We concluded that if liability could be imposed on the visiting friend for failing to extinguish the campfire, there would be no sensible or just stopping point as to whom could be held liable for a known hazard. Id. at 428-29. We noted the appropriateness of the question asked by the court of appeals:
. . . [Wjhen it comes to fires ... is it the last adult to leave, the last person to put a log in the fire? Or is it the owner of the campsite? Or the person who started the campfire?
Id. at 428.
¶ 25. If we were to permit liability against the defendants before us, we would be opening the door to property owners' claims against any contractor who contracts with a municipality to remediate a naturally occurring hazard, when the contractor fails to completely abate the hazard's effects. This broad exposure to liability would chill municipalities' efforts in attempting abatement projects. It could also chill contractors from bidding on those types of municipal projects; where in addition to being subject to a breach of contract action by the municipality
¶ 27. As in Rockweit, we conclude that to open the door for this type of claim would be to enter a field with no just or sensible stopping point. Therefore, we conclude that the defendants may not be held liable for their unsatisfactory abatement efforts and the dismissal of the plaintiffs' negligence claim was proper.
E. Nuisance
¶ 28. The plaintiffs also bring a nuisance claim against the defendants. "Liability for a nuisance may be based upon either intentional or negligent conduct" and may be grounded in either creating or maintaining a nuisance. Milwaukee Metro,
¶ 29. When we review an alleged nuisance claim, our first step is to determine whether nuisance exists. Physicians Plus Ins. Corp. v. Midwest Mut. Ins. Co.,
¶ 30. The plaintiffs' complaint does not label their claim as one for a private or a public nuisance. However, it does refer to the use and enjoyment of their private property, implying that it is a private nuisance claim. The plaintiffs use the same conduct as the basis for their nuisance claim, as they employed for their negligence claim. When a nuisancе claim is predicated on negligent acts, it is necessary for the court to separately analyze the nuisance claim for relief from the negli
¶ 31. In Physicians Plus, we held that due to the analogous relationship between negligence and nuisance, liability for maintaining a public nuisance can be limited on public policy grounds traditionally used to preclude liability for general negligence claims. Physicians Plus,
Since all the underlying rules of negligence are applicable to a claim of nuisance based on negligence, logically then, the prerequisites for liability should not vary depending upon whether the interest invaded by the defendant's negligent conduct is public or private.
Milwaukee Metro,
¶ 32. The plaintiffs assume the existence of a nuisance when they claim that the use and enjoyment of their property is invaded by the flooding waters of the Lake. They also assert that a cause of this invasion is the defendants' unsuccessful abatement actions. However, there is no dispute that the defendants did nothing to cause the Lake's rising water level; the plaintiffs claim against the defendants because they did not succeed in causing the water level to recede. There
¶ 33. We have explained that cause-in-fact (a substantial factor) and the public policy factors are both used when we determine liability. Fandrey v. Am. Family Mut. Ins. Co.,
Even though a jury has found negligence and that such negligence was a "cause" (or substantial factor) in producing a plaintiffs damages, liability may be denied under factors that we have termed public policy considerations.
Id. (quoting Beacon Bowl, Inc. v. Wis. Elec. Power Co.,
¶ 34. We have concluded, as a matter of law, that the plaintiffs' negligence claim should not go forward because to permit the claim would enter a field with no just or reasonable stopping point. When we did so, we were deciding that as a matter of law, the defendants' actions were not sufficient to support liability for the plaintiffs' damage. See Fandrey,
¶ 35. Accordingly, we conclude that the court of appeals correctly affirmed the circuit court's grant of summary judgment in favor of the defendants, although we base our holding on different reasoning than the court of appeals employed.
III. CONCLUSION
¶ 36. We conclude that the plaintiffs' negligence and nuisance claims are precluded by public policy, and were properly dismissed. Therefore, we affirm the court of appeals, albeit on different grounds than that employed by the court of appeals.
By the Court. — The decision of the court of appeals is affirmed.
Notes
Judge Norman L. Yackel presided in the Washburn County Circuit Court.
According to the Army Corps of Engineers Report, the highest recorded water level was 1228.55 feet msl in 1900.
Cincinnati Insurance Company and Gulf Underwriters Insurance Company are named as intervening defendants.
The complaint also asserted an inverse condemnation claim and claims for declaratory and injunctive relief, which are not before us.
The decision to dismiss all claims against the City has not been appealed.
Restatement (Second) of Torts § 324A (1965) provides;
One who undertakes, gratuitously or for consideration, to render services to another which he should recognize as necessary for the protection of a third person or his things, is subject to liability to the third person for physical harm resulting from his failure to exercise reasonable care to protect his undertaking, if
(a) his failure to exercise reasonable care increases the risk of such harm, or
(b) he has undertaken to perform a duty owed by the other to the third person, or
(c) the harm is suffered because of rebanee of the other or the third person upon the undertaking.
The dissent takes issue with applying a public policy analysis when causation and damages remain. Dissent, ¶ 84.
Here, the contractors were sued by the City for breach of contract, and the suit was settled to the satisfaction of the City of Shell Lake. Therefore, the contractors have not escaped liability for failing to create and install a system to lower the water level in the Lake.
Concurrence Opinion
¶ 37. (concurring). The majority opinion, which I authored and join, affirms the court of appeals decision that in turn affirmed the circuit court's grant of summary judgment dismissing plaintiffs' claims. The court of appeals based its decision on the applicatiоn of Restatement (Second) of Torts § 324A (1965), after concluding that § 324A is the appropriate framework for analyzing the plaintiffs' negligence claims. Butler v. Advanced Drainage Sys., Inc.,
¶ 38. The majority has chosen to deny liability based on a public policy factor. When we employ public policy factors to preclude liability, we engage in judicial line-drawing wherein we conclude there is the lack of sufficient cause to hold a defendant liable. Fandrey v.
I. BACKGROUND
¶ 39. The court of appeals concluded that the Restatement (Second) of Torts § 324A was the appropriate framework for analyzing the plaintiffs' nеgligence claims. Butler,
II. DISCUSSION
A. Standard of Review
¶ 40. This case requires us to review summary judgment dismissing the plaintiffs' claims against the
B. The Negligence Claim
¶ 41. The plaintiffs' negligence claim can be analyzed within the framework set out in the Restatement (Second) of Torts § 324A or under the usual four-element negligence test. The court of appeals relied on § 324A, and the circuit court applied the four-element test. I conclude that the test set out in § 324A provides the better framework.
1. Restatement (Second) of Torts § 324A
¶ 42. The court of appeals concluded that § 324A of Restatement (Second) of Torts provided the proper framework in which to analyze this tort claim that arose out of a breach of contract between the defendants and the city. Butler,
One who undertakes, gratuitously or for consideration, to render services to another which he should recognize as necessary for the protection of a third person or his things, is subject to liability to the third person for physical harm resulting from his failure to exercise reasonable care to protect his undertaking, if
(a) his failure to exercise reasonable care increases the risk of such harm, or
(b) he has undertaken to perform a duty owed by the other to the third person, or
*423 (c) the harm is suffered because of reliance of the other or the third person upon the undertaking.
¶ 43. In Miller v. Bristol-Myers Co.,
¶ 44. Wisconsin has a long history of attempting to maintain the distinction between contract and tort claims. Landwehr v. Citizens Trust Co.,
¶ 45. The use of § 324A by Wisconsin courts appears in our attempts to sort out when circumstances that began with an undertaking of some sort, either gratuitous or for pay, could give rise to a tort. For example, in American Mutual Liability Insurance Co. v. St. Paul Fire & Marine Insurance Co.,
¶ 46. A similar § 324A approach is found in the analysis of the claims in Miller. There, we used § 324A to determine whether a parent company that gave day-to-day advice to a subsidiary corporation on safety issues was liable in tort to the employees of the subsidiary who were harmed because the subsidiary company took the advice of the parent company. Miller,
Section 324A establishes when an assumption of duty arises and the grounds for liability thereunder. The*425 introductory portion establishes when an assumption of duty arises. The elements for an assumption of duty to arise are that the actor must: (1) undertake to render services, (2) to another, (3) which such actor should recognize as necessary for the protection of a third person.
Id. We noted that once it has been shown that a defendant assumed a duty with regard to another, "the remaining portion of the introduction and subsections (a), (b), and (c) [of § 324A], establish when liability for assuming such a duty arises." Id. at 884.
¶ 47. In Gritzner v. Michael R.,
¶ 48. In Stephenson v. Universal Metrics, Inc.,
¶ 49. Our use of § 324A comports with general negligence principles because it does not preclude a tort claim where one would otherwise exist. Rather, it assists in maintaining an analysis that preserves the differences between contract and tort claims, while recognizing that some factual circumstances can give rise to both types of claims.
2. The application of § 324A
¶ 50. In the case now before us, none of the defendants had an obligation to enter into a contraсt with the City. None had any obligation to attempt to correct the Lake's flooding problem. They are sued by the plaintiffs solely because they contracted with the City to construct a system to reduce naturally occurring flooding and the system they constructed failed to do so. Therefore, the defendants have undertaken to render services that they should recognize as necessary to protect the property owners at the Lake's edge. Accordingly, they come within the ambit of the introductory paragraph of § 324A. They are liable to the property owners if the conditions contained in one of the three
¶ 51. Subsection (a) involves increased risk of harm.
¶ 52. Subsection (b) requires that the defendants perform a duty owed by another.
¶ 53. Subsection (c) requires a finding of harm due to reliance.
¶ 54. In addition, the City claims to have suffered no "harm" because of the defendants' unsuccessful efforts.
III. CONCLUSION
¶ 55. The majority has chosen to deny liability based on a public policy factor. When we employ public policy factors to preclude liability, we engage in judicial line-drawing wherein we conclude there is the lack of a sufficient legal cause to hold a defendant liable. Fandrey,
Restatement of the Law Third, Torts: Liability for Physical Harm, Proposed Final Draft No. 1 (Apr. 6, 2005), renumbered § 324A to § 43 and revised the introductory paragraph as:
An actor who undertakes to render services to another that the actor knows or should know reduce the risk of physical harm to which a third person is exposed has a duty of reasonable care to the third person in conducting the undertaking if:
(a) the failure to exercise reasonable care increases the risk of harm beyond that which existed without the undertaking,
(b) the actor has undertaken to perform a duty owed by the other to the third person, or
(c) the person to whom the services are rendered, the third party, or another relies on the actor's exercising reasonable care in the undertaking.
Section 324A(a) provides: "his failure to exercise reasonable care increases the risk of such harm."
Section 324A(b) provides: "he has undertaken to perform а duty owed by the other to the third person."
Section 324A(c) provides: "the harm is suffered because of rebanee of the other or the third person upon the undertaking."
This is likely true because the City sued the defendants for breach of contract and a settlement was achieved that was satisfactory to the City.
Dissenting Opinion
¶ 56. (dissenting). This court has repeatedly explained that only in those cases where the facts are simple to ascertain and the public policy questions have been fully presented may a court review public policy and preclude liability before trial. Gritzner v. Michael R.,
¶ 57. Thus, the better practice is generally to submit a case to the jury before determining whether public policy factors should preclude liability. Smaxwell v. Bayard,
¶ 58. "The court has stated the[] public policy considerations that may preclude liability in capsule form as follows: When it would shock the conscience of society to impose liability, the courts may hold as a matter of law that there is no liability." Bowen,
¶ 59. The majority's conscience is easily shocked.
¶ 60. I dissent for three reasons. First, I would follow the better practice and decline to apply the public policy factors on the summary judgment record before us. Second, even if I were to attempt an application of the factors on the present record, that application would not justify limiting liability at this stage of proceedings. Third, I write to observe that this case illustrates why there is often an uncomfortable fit between summary judgment methodology and application of the public policy factors.
HH
¶ 61. In order to determine whether liability for negligence should be limited, Wisconsin courts apply six public policy factors. The courts are to ask whether:
*431 (1) the injury is too remote from the negligence; (2) the injury is too wholly out of proportion to the tortfeasor's culpability; (3) in retrospect it appears too highly extraordinary that the negligence should have resulted in the harm; (4) allowing recovery would place too unreasonable a burden on the tortfeasor; (5) allowing recovery would be too likely to open the way for fraudulent claims; [or] (6) allowing recovery would enter a field that has no sensible or just stopping point.
See, e.g., Gritzner,
¶ 62. The majority ignores the better practice and applies only one of the six public policy factors to preclude liability for negligence. It does so on summary judgment even though the facts are not yet well developed and not simple to ascertain. The majority thereby cuts off the potential for liability before the public policy questions this case might raise are even fully presented.
¶ 63. Given that it is too early to effectively apply the public policy factors, I am not surprised that the majority's analysis of public policy amounts to essentially no analysis whatsoever.
¶ 64. The reader can decide whether the majority's public policy "analysis" is convincing to anyone other than the majority. In order to assist the reader, I will summarize the majority's analysis. This is easily done because its entire analysis consists of six paragraphs amounting to two reasons for its conclusion to limit liability for negligence: (1) its assertion that this case is similar to Rockweit v. Senecal,
¶ 65. The majority's assertion that this case is similar to Rockweit is curious. Why? Because Rockweit was a case in which the court followed the better practice, applying the public policy factors after the facts were fully developed at a jury trial. Rockweit,
¶ 66. There is no shortage of cases in which this court has declined to apply the public policy factors to preclude liability before a case has been tried. See, e.g., Alvarado v. Sersch,
¶ 67. Why does the majority fail to discuss any of these cases?
¶ 68. As for the majority's two-paragraph discussion of one of the six public policy factors, it is wholly unpersuasive. I begin by quoting the majority's central rationale, and then explain why it is so unconvincing:
If we were to permit liability against the defendants before us, we would be opening the door to property owners' claims against any contractor who contracts with a municipality to remediate a naturally occurring hazard, when the contractor fails to completely abate the hazard's effects. This broad exposure to Lability would chill municipalities' efforts in at*433 tempting abatement projects. It could also chill contractors from bidding on those types of municipal projects; where in addition to being subject to a breach of contract action by the municipality for not performing as they had contracted to perform, the contractors would be subject to litigation by any property owner who would have benefited from a successfully performed municipal contract.
Majority op., ¶ 25.
¶ 69. There are at least three reasons why the majority's application of this public policy factor is unconvincing.
¶ 70. First, the majority comes perilously close to setting forth a blanket rule of immunity from liability for all contractors that contract with municipalities. It is difficult to imagine how the majority's reasoning can be limited in any principled manner to contractors who contract with municipalities "to remediate a naturally occurring hazard." Id. Are contractors who contract with municipalities for purposes other than remediation of a "naturally occurring hazard" really situated any differently under the majority's rationale? I am concerned that there are ramifications to the majority's cursory analysis that may reverberate well beyond the facts of this case to provide immunity where none previously existed.
¶ 71. Second, the blanket rule of immunity that the majority comes close to adopting seems to render superfluous case law providing that private contractors who contract with the government may be entitled to
¶ 72. Under Lyons, an independent contractor who follows governmental directives can be entitled to immunity when:
(1) the governmental authority approved reasonably precise specifications;
(2) the contractor's actions conformed to those specifications; and
(3) the contractor warned the supervising governmental authority about the possible dangers associated with those specifications that were known to the contractor but not to the governmental officials.
Lyons,
¶ 73. The majority fails to explain how its opinion squares with the Lyons rule. Indeed, it fails to even acknowledge that the Lyons rule exists. Is it sub silentio overruling Lyons ?
¶ 74. Third, the majority cites no facts of record for its speculative assertion that imposing liability here would chill municipalities' efforts in attempting abatement projects and would chill contractors from bidding on those types of projects. Just as likely, imposing liability would chill tortious conduct.
HH 1 — I
¶ 76. To the extent possible on the limited record before us, I now turn to address the public policy factors that the majority ignores. To the extent those factors can be applied on the present record, they do not justify limiting liability.
¶ 77. Whether the injury is too remote from the negligence and whether in retrospect it appears too highly extraordinary that the negligence should have resulted in the harm. The application of each of these two fаctors weighs in favor of liability. There can be no real dispute that everyone involved was keenly aware of what would happen if the defendants negligently failed to perform their contract obligations. The lake would continue to rise resulting in damages to surrounding landowners. It is not highly extraordinary that the defendants' negligence in designing or constructing the drainage system in this case would result in property damage to the landowners.
¶ 78. Whether the injury is too wholly out of proportion to the tortfeasor's culpability and whether allowing recovery would place too unreasonable a burden on the tortfeasor. It is too early in this litigation to apply these factors in any meaningful sense because the extent of the damages to the property owners remains unknown. Also unknown at this stage in the proceedings is how comparative negligence principles may affect the extent of any liability burden on the defendants. See Stewart,
¶ 79. Whether allowing recovery would he too likely to open the way for fraudulent claims. The majority recites no facts of record suggesting that to allow recovery in this case would likely open the way for fraudulent claims. This is because there are no such facts. Given the facts that we know, it is difficult to conceive how allowing recovery would be too likely to open the way for fraudulent claims.
¶ 80. Having addressed all six public policy factors to the extent possible on the limited record before us, I conclude that their application does not justify limiting liability at this stage of the proceedings. Rather, the case before us is one where "[a] trial court or jury finding as to actual negligence, damage and the causal relationship between them would be material and helpful in evaluating the public policy considerations." Coffey,
l — l H-< 1 — 1
¶ 81. Finally, I write because this case illustrates why there will often be an uncomfortable fit between summary judgment methodology and application of the public policy factors. This uncomfortable fit further highlights why it is typically ill-advised to limit liability using those factors at the summary judgment stage of proceedings.
¶ 82. As the majority knows, the cardinal principles of summary judgment methodology include that "[sjummary judgment should not be granted, unless the facts presented conclusively show that the plaintiffs
¶ 83. The outcome of this case would be different if the majority were actually to apply these cardinal summary judgment principles. Instead, the majority stops with rote recitation of summary judgment principles. See majority op., ¶ 18.
¶ 84. The majority assures the reader that the "relevant facts relating to thé attempted water abatement are not disputed." Id., ¶ 21. It also assures the reader that "the facts of record are sufficiently developed ... to undertake a public policy analysis." Id. How can the majority make these assurances when facts material to cause, damages, and a meaningful application of the public policy factors remain disputed in this case?
¶ 85. The parties dispute whether the defendants' negligence was a cause of the landowners' damages. The engineering firm hired by the City to investigate the failed drainage project concluded that the pipeline failure stemmed from design and material defects along with failure to test the materials.
¶ 86. The defendants in this case undertook to control the lake's water level. The landowners maintain that if the defendants had exercised ordinary care in the design and testing of the pipeline, then the water level would have receded. They assert that the defendants'
¶ 87. The uncomfortable fit is further illustrated by the rationale focusing on cause (a substantial factor) employed by the majority. In essence, the majority's position is that the defendants' negligence did not cause any injury because it would have happened anyway. See id., ¶ 24 ("[i]t is probable that absent any act by the defendants, the plaintiffs, nevertheless, would have suffered damages.").
¶ 88. The majority takes the plaintiffs to task for their assertion that "a cause of this invasion is the defendants' unsuccessful abatement actions." Id., ¶ 32. Ultimately the majority concludes that "there is no dispute that the defendants did nothing to cause the Lake's rising water level." Id. It is with this ultimate conclusion that the inconsistency of the majority's position is highlighted.
¶ 89. How can the majority on the one hand conclude that there are no facts which would support a finding of causation, while on the other hand state that in its public policy determination it assumes the defendants' negligence caused the damages? See id., ¶ 21 ("[W]e assume there is negligence and that the negligence was a cause of the injury" when we apply public policy factors.).
¶ 90. The majority cannot have it both ways. It cannot both assume that the defendants' negligence was a cause of the plaintiffs' damages while at the same time conclude that there are no facts in dispute that would support a finding of causal negligence.
¶ 91. In addition, factual disputes remain as to the amount of damages, apportionment of liability, and
concern over the number of plaintiffs who would have to testify, the proof of individual damage claims [,] and how the affirmative defenses of contributory negligence and mitigation of damages would be dealt with as a class action.
¶ 92. Another defendant, in discussing why the circuit court properly denied class certification, explains similarly:
Each of those issues [apportionment of liability, mitigation, and the landowners divergent damages claims] involves complex and disputed sets of fact[s] that are unique to each particular property owner ....
(Emphasis added.)
¶ 93. As already explained, the court cannot meaningfully apply the public policy factors of whether the injury is too wholly out of proportion to the tortfeasor's culpability or whether allowing recovery would place too unreasonable a burden on the tortfea-sor when it does not know the extent of the requisite injuries or burdеns. The myriad factual disputes likely implicate additional public factors as well. Yet the majority assures us that the "relevant facts relating to the attempted water abatement are not disputed" and that "the facts of record are sufficiently developed ... to undertake a public policy analysis." Majority op., ¶ 21.
¶ 94. The remaining factual disputes preclude a meaningful application of the public policy factors. Moreover, if the majority were to construe reasonable
IV
¶ 95. In sum, I would follow the better practice and decline to apply the public policy factors on the summary judgment record before us. Even if I were to attempt an application of the factors on the present record, however, that application would not justify limiting liability at this stage of proceedings. Accordingly, I respectfully dissent.
1 need not and do not separately address the majority's analysis of the landowners' nuisance claims. As the majority correctly recognizes, liability for a nuisance claim based on negligence is subject to limitation based on the same public policy factors. See majority op., ¶ 32.
The majority cites some of these cases in passing when it sets forth the public policy factors. Majority op., ¶¶ 19-20.
1 acknowledge case law stating that liability may be denied solely on the basis of one public policy factor. See Smaxwell v. Bayard,
1 do not maintain that it is never correct to apply the public policy factors to preclude liability at the summary judgment or earlier stage of proceedings. Such application is appropriate, however, only when the facts are simple to ascertain and the public policy questions have been fully presented. Alvarado v. Sersch,
