70 Minn. 507 | Minn. | 1897
This was an action to enforce a mechanic’s lien for work performed and material furnished in the erection of a building pursuant to the provisions of the contract Exhibit 1 of the answers. The appealing defendants acquired their respective interests in the property after the execution of this contract and after the construction of the building had been commenced.
The court made some 13 or more findings of fact. The only assignment of error is tO' the effect that the decision of the court was not justified by the evidence, and was contrary to law. This is insufficient to call in question the correctness of any of the findings of fact. Smith v. Kipp, 49 Minn. 119, 51 N. W. 656; In re Granstrand, 49 Minn. 438, 52 N. W. 41; Moody c. Tschabold, 52 Minn. 51, 53 N. W. 1023; Dallemand v. Swensen, 54 Minn. 32, 55 N. W. 815.
At most, the only question open to appellants under this assignment of error is whether the conclusions of law were justified by the findings of fact. But, as no findings are required of facts not in issue, in determining the sufficiency of the findings they must be considered in connection with the facts admitted in the pleadings. These admit the execution of the contract Exhibit 1, and that the work and material for which a lien is claimed were performed under and in pursuance of it. Hence the question is presented whether the provisions of that contract constituted a waiver of the right to a lien for any part of the work and material performed or furnished under it. The price to be paid for the construction of the building was $82,645, subject to such additions or deductions
The contention of the defendants is that the provision for giving 12-months notes for $14,000 necessarily amounted to waiver of the right to a lien for that sum, for the reason that it would extend the time of payment beyond the time within which, under the statute, an action to enforce a lien must be commenced.
This contention seems to be based upon the false premise that .these notes were to be given after the completion of the building,
But we prefer to place our decision on the broader ground that, even if the contract had provided that the 12-months notes should be given after the building was completed, this would not have amounted to a waiver of a lien in view of the express stipulation “that the taking of any notes * * * pursuant to the provisions of this contract shall not be construed as a waiver of any right which it” (the plaintiff) “may have to impose or enforce a statutory lien.” It is not to be presumed that this was intended to be merely a repetition of the statutory provision that the taking of a promissory note shall not discharge a lien unless expressly received in payment, and so specified in the note.
No other meaning or effect can be given to it except that which its language clearly indicates, viz; that the taking of a promissory note according to the contract shall not constitute any waiver of the right either to impose or enforce the statutory lien, but leave the contractor at liberty to enforce it exactly as if no note had been taken. The result would be that, while no personal action on the notes could be maintained until they matured, yet the contractor would have the right at any time to bring his action to enforce his lien on the property.
There is nothing against public policy in this, and it is not without analogies in the law. For example, where a creditor whose debt is secured by a bond with sureties takes a time note from the principal debtor, with a distinct agreement that the taking of the note shall not suspend the remedy on the bond, it is held that the
The defendants attempt to raise the point that the evidence shows that the parties to the building contract modified it by making the notes payable in 11 instead of 12 months. Even if there was merit in the point, defendants are precluded from raising it, both by their assignments of error and by their pleadings. Their answers set out the building contract, and then allege that the $14,000 was paid in notes, “as provided in said contract.” No modification of the terms of the contract is alleged, or even suggested.
Order affirmed.
An application for a reargument having been made the following opinion was filed January 4, 1898.
Counsel for appellant applies for a reargument for the reasons— First, that the second, and principal, ground on which the decision was based was not argued by counsel; and, second, that it is opposed to Flenniken v. Liscoe, 64 Minn. 269, 66 N. W. 979. As the correctness of the first ground for affirmance stated in the opinion is not questioned, the fact that the second was not suggested or argued by counsel is no ground for a reargument. In Flenniken v. Liscoe there was no reservation, as in this case, of the right to enforce the lien. That reservation impliedly and necessarily included everything necessary to the full exercise of the main right, which was the enforcement of the lien.
Application denied.