55 Mo. App. 453 | Mo. Ct. App. | 1893
Action to enforce a mechanics’ lien. On tbe trial tbe court refused to allow plaintiff to read bis lien paper' in evidence for tbe reason that, in tbe opinion of tbe court, it failed to answer tbe requirements of tbe statute, in that tbe statement of tbe account was too indefinite. Tbe court, sitting as a jury, found for tbe plaintiff in tbe sum of $385.54, and judgment was entered against the defendant for that amount. Tbe court also found that tbe mechanic’s lien bad not been
The plaintiff alleged in his petition, and his evidence tended to prove, that he made a contract with the defendant, who was about to commence the erection of a building on premises owned by him, to do the stone work on the house, consisting of “cut stone, rubble masonry and range material,77 and to furnish the necessary materials therefor, for the sum of $364; that he fully performed the work, and that he also did extra work at the request of the defendant, which was reasonably worth $25. The court held the petition to be bad as to the item for extra work, and the parties proceeded to trial on the other item of the account.
That the lien paper was properly filed within the time prescribed by law is not disputed.' It reads:
“State of Missouri, “City of St. Louis. ss.
“The undersigned, John Busso, states that he was the original contractor with Anton Eette, hereinafter mentioned, for the furnishing and setting of cut stone, rubble masonry and range material, and labor in setting same, in the erection of a certain new two-story building situated on lot number 30, as represented in the amended plat of Gartside’s subdivision in the Prairie Des Noyers fields, and in city block number 5016 of the city of St. Louis, state of Missouri, having a front of fifty feet on the west line of Alfred avenue, by a depth running westwardly, between parallel lines, of one hundred and fifty-two feet, six inches to an alley; that Anton Eette aforesaid was, and is, the owner of said house and lot at the time the contract with affiant was made, and now; that the 'materials and labor men*455 tioned were furnished and rendered at his special instance and request, and that the following is a just and true account of the demand due affiant after all just credits have been given therefor, to-wit:
“To material and labor furnished and rendered thereupon, as per original bid and contract, $364.
“To materials and labor furnished and rendered thereupon, extra or change in plans, $25.
“That the work was begun, to-wit, on March 16, 1892, and was finished and the indebtedness accrued April 5,‘1892, and that the sum of three hundred and eighty-nine dollars ($389), is due said Busso from said Eette for and on account of the premises.
“John Busso.
“The above named John Busso, being duly sworn, on his oath says that the matters and things stated in the above and foregoing statement are true.
“John Busso.
“Sworn to and subscribed before me this eighteenth day of May, 1892. My term expires thirty-first of October, 1893; witness hand and seal. '
“Alston L. Byland, [seal]
• “Notary Public.”
Under the decision of the supreme court in the case of Rude v. Mitchell, 97 Mo. 365, and that of Hilliker v. Francisco, 65 Mo. 599, both of which involve the sufficiency of mechanics’ lien accounts, it is made difficult to apply the law in some cases. The objectionable item in the Hilliker case reads: “To Junction Oity. Stone furnished First National Bank, as per contract, $7,790.” This was held sufficient to satisfy the statute. The main item in the Eude case reads: “1892. Dec. 1st. For alterations and additions to buildings Nos. 210 and 212 N. Third St., as per plans and specifications, $22,287.” Then followed'
The court in its opinion in the Rude case approved its previous ruling in the Hilliker case, and undertook to distinguish the cases. In referring to the Hilliker case, Judge Black said: “The suit was one by the subcontractor, and there was evidence to show that the bank had agreed with the contractor to the sum of $7,000 as compensation to the plaintiffs for the material and labor mentioned in the item. Under these circumstances it was held that the item was sufficiently specific. The item there in dispute, it will be seen, related to the stone work and labor of setting only, and the price is given. In the present case the first item is for $22,287, and there is nothing to show, on the face of the account, what is, or what is not, intended to be included.”
It seems to us that another distinctive difference between the two cases, and which perhaps would require greater particularity in the statement of one 'account than the other, is, that the recovery in the Hilliker case was- on a special contract, in which the parties had agreed on a lumping price, for the work which was actually performed and which was designated in the account, whereas in the Rude case the recovery was on a quantum meruit, — the referee holding that there could be no recovery under the. contract for the reason that the difference in the price for the alterations and extra work had not been fixed by the architects as the contract required.
In the case at bar the lien paper states that there was a special contract with the owner of the building to furnish the stone and other materials, and do the necessary work for the “cut stone, rubble masonry and range material,” in the construction of the house for the sum of $364. The petition stated the same
With the concurrence of the other judges the judgment of the circuit court will be reversed and the cause remanded. It is so ordered.