AI BURTON v. JEREMIAH BEACH PARKER RESTORATION AND CONSTRUCTION MANAGEMENT CORP. and Jeremiah Beach Parker
No. 09-312
Supreme Court of Vermont
June 21, 2010
2010 VT 55 | 6 A.3d 38
Motion for reargument denied July 22, 2010.
¶ 1. June 21, 2010.
¶ 2. The basic facts of this dispute may be briefly summarized. Additional material facts will be set forth in the discussion which follows. In February 2002, Burton entered into an agreement with contractor for substantial renovations to Burton‘s property in Benson, Vermont. Contractor began work, but disputes over certain changes in the renovation plans led to a breakdown in the relationship, and Burton ultimately filed this lawsuit seeking damages for breach of contract, breach of the implied covenant of good faith and fair dealing, common law fraud, breach of fiduciary duty, violation of the Consumer Fraud Act, and negligent misrepresentation. Contractor counterclaimed for breach of contract, claiming that Burton had wrongfully hired other contractors to perform work specified in the contract, and failed to pay invoices in a timely manner.
¶ 3. The trial court (Judge Katz presiding) granted contractor‘s pretrial motion to dismiss several of the counts, and the remaining claims were tried before the court (Judge Toor presiding) over several days in March and July 2008. In August 2008, the court issued written findings and conclusions, ruling in favor of Burton on his breach-of-contract claims for defective
¶ 4. Contractor then moved for an award of attorney‘s fees under the Prompt Payment Act, which provides that, “[n]otwithstanding any contrary agreement, the substantially prevailing party in any proceeding to recover any payment within the scope of this chapter shall be awarded reasonable attorneys’ fees in an amount to be determined by the court or arbitrator, together with expenses.”
¶ 5. Burton first contends the trial court lacked statutory authority to award attorney‘s fees because the fee provision of the Prompt Payment Act,
¶ 6. Burton did eventually raise the issue below, but not in a timely manner. In granting the motion for attorney‘s fees, the trial court ordered contractor to submit an affidavit “detailing the fees so that Burton may be heard on their reasonableness” and authorized Burton to submit within ten days “written objections” to contractor‘s submission. About a month later, Burton filed a response citing the sunset provision and “ask[ing] the Court to reconsider its award of attorney[‘s] fees.” The motion to reconsider was plainly untimely, however, and the trial court properly denied it. See
¶ 7. Burton next contends the trial court violated public policy in awarding attorney‘s fees to a party in breach of contract. Burton relies on Fletcher Hill, Inc. v. Crosbie, 2005 VT 1, 178 Vt. 77, 872 A.2d 292, where we upheld the trial court‘s finding that it would be unfair to base an award of attorney‘s fees on a contract which the contractor had violated. As the trial court here correctly observed, however, our holding in Fletcher Hill was based on a contractual fee provision and did not apply to the statutory fee provision of the Prompt Payment Act, which we analyzed separately. Accordingly, the claim has no merit.
¶ 8. Burton further contends the trial court erred in determining that contractor was the “substantially prevailing party” under
¶ 9. Assessed in light of this flexible standard, we find no basis to conclude that
¶ 10. The record thus firmly supports the trial court‘s finding that contractor not only prevailed on its own counterclaim for breach of contract, but also successfully defended against the bulk of Burton‘s claims. The court was therefore well within its discretion in concluding that, all things considered, contractor was the substantially prevailing party in this lawsuit despite the fact that Burton was the “net victor” to the tune of $566. As noted, we have squarely rejected the notion that “the party with a net verdict is automatically the substantially prevailing party.” Fletcher Hill, 2005 VT 1, ¶ 15. Furthermore, while Fletcher Hill merely affirmed the trial court‘s decision not to award attorney‘s fees to the party obtaining a net judgment, other courts have specifically upheld attorney‘s fee awards to a party that failed to obtain a net monetary judgment but otherwise achieved the greater success on the issues litigated. See, e.g., Matthews v. Candlewood Builders, Inc., 685 S.W.2d 649, 650 (Tex. 1985) (per curiam) (holding that, although contractor obtained a net judgment after set-offs of over $2,000, the trial court should have awarded attorney‘s fees to homeowner as the prevailing party on its counterclaims for construction defects and fraud); Occidental/Neb. Fed. Sav. Bank v. Mehr, 791 P.2d 217, 221-22 (Utah Ct. App. 1990) (applying a “flexible and reasoned approach” the court concluded that defendants were the statutorily “prevailing” party where the plaintiff had claimed $600,000 in damages but recovered only about $7,300). We thus find no basis to conclude that the trial court abused its discretion in determining that contractor was the substantially prevailing party.
¶ 11. The dissent‘s arguments to the contrary are unpersuasive. First, the dissent fails to consider the trial court‘s detailed findings rejecting nearly all of Burton‘s construction-defect claims, as well as its related findings carefully explaining its
¶ 12. Burton next contends the trial court erred in awarding attorney‘s fees incurred in defending the claims that contractor ultimately lost — specifically, the claims for defective workmanship on the ridge beam and overbilling. Burton asserts that the court improperly failed to address this argument in its decision and unfairly denied Burton a hearing on the issue. Burton‘s assertion to the contrary notwithstanding, the trial court specifically addressed and rejected this argument, finding that Burton had “fail[ed] to specify which portions of the fee affidavit it feels are inappropriate” and that, in any event, Burton had cited “no authority to suggest that the court must break down the winning and losing claims in determining the reasonableness of [the] fee award.” The court‘s ruling was correct. See Elec. Man, Inc. v. Charos, 2006 VT 16, ¶ 9, 179 Vt. 351, 895 A.2d 193 (rejecting a request under
¶ 13. Burton additionally contends the court erred in awarding contractor its litigation costs totaling $8,124. Burton asserts that contractor was not the “prevailing” party under
¶ 14. Burton next claims that contractor‘s motion for attorney‘s fees was untimely. Burton argues in this regard that “judgment” was entered with the issuance of the trial court‘s findings and conclusions on August 21, 2008, rather than its judgment order on October 20, 2008, so that the motion for attorney‘s fees filed on November 3, 2008 was not within the requisite fourteen days “after entry of judgment.”
¶ 15. Finally, Burton contends the court erred in denying his motion to extend
¶ 16. Burton‘s reliance on this provision is misplaced. Although contractor filed a timely motion for attorney‘s fees, Burton did not request, nor did the court order, that the appeal period be tolled before it expired in late November. As the trial court here correctly observed,
Affirmed.
¶ 17. Zonay, District Judge, Specially Assigned, concurring and dissenting. While I concur with the majority opinion as it relates to the timeliness of the attorney‘s fee request, and the denial of Burton‘s
¶ 18. The majority reasons that because Burton did not raise his statutory argument in his initial opposition to contractor‘s motion for attorney‘s fees, he did not preserve it for our review. This approach misapplies both the rules of civil procedure and our rules on preservation.3 The record
¶ 19. The majority construes Burton‘s April 22 filing as a motion to alter or amend under
¶ 20. The trial court‘s ruling in this case, by its own terms, was not a final judgment that set forth the actual award but merely an interlocutory order from which no appeal could be taken. See Morissette v. Morissette, 143 Vt. 52, 58, 463 A.2d 1384, 1388 (1983) (holding that for a judgment to be final it must make a final disposition of the subject matter before the court); see also
¶ 21. While the rules did not impose a ten day requirement, the trial court‘s March 23 ruling itself contained such a requirement. Notably, however, the trial court did not decline to consider the sunset issue on the basis of the date of Burton‘s filing. Rather, in its July 31, 2009 ruling granting the motion for attorney‘s fees, the trial court acknowledged Burton‘s filing and wrote: “Treating those objections as a motion to reconsider, they are denied.” While I agree with the majority that the
¶ 22. That the trial court may not have been obligated to consider the opposition under its March 23 ruling does not mean that it did not have the ability to consider it on its merits, or that it did not actually consider it. Without a clear indication that the trial court was declining to address the merits of the opposition as a sanction for the late filing, I cannot read its decision as one where it did not consider it. Given that a trial court reaches the merits of motions to reconsider filed under
¶ 23. It is clear that the sunset issue was directly raised before the trial court and, in my view, was properly preserved. As this Court has held, “[t]he purpose of the [preservation] rule is to ensure that the original forum is given an opportunity to rule on an issue prior to our review.” In re Entergy Nuclear Vt. Yankee, LLC, 2007 VT 103, ¶ 9, 182 Vt. 340, 939 A.2d 504 (quotation omitted). “The preservation rule is satisfied when the trial court had a fair opportunity to consider, evaluate and rule upon the question raised on appeal.” Vt. Built, Inc. v. Krolick, 2008 VT 131, ¶ 10, 185 Vt. 139, 969 A.2d 80 (quotation omitted). Burton‘s opposition clearly advanced the argument about the sunset provision, and the trial court had a fair opportunity to “consider, evaluate and rule upon” this question in its July 31, 2009 ruling. Thus, I believe the issue is properly before this Court and must be addressed on its merits. Cf. ante, ¶ 6 n.1 (citing Reed v. Zurn, 2010 VT 14, ¶ 12, 187 Vt. 613, 992 A.2d 1061 (mem.) (holding that issue not preserved for this Court‘s review where party did not raise legal argument at trial with specificity, but instead attempted — in a one-sentence argument — to raise issue post-judgment by citing to vague trial testimony)).
¶ 24. Burton correctly asserts that the attorney‘s fee provision is no longer in effect. The Act, as originally enacted, stated that “[t]he provisions of
¶ 25. The problem with this is simple: one cannot repeal the sunset provision on July 1, 1996, when the statute had already expired on June 30, 1996. While I recognize the clear legislative intent to repeal the sunset provision and to have the statutory provisions continue in effect after June 30, 1996, this is not a case of the courts interpreting an ambiguous statute
¶ 26. It also bears noting that, in declining to address the issue, the majority is leaving the validity of these statutory provisions for a future case. In my view, this imparts unnecessary uncertainty between those whose relationships are thought to fall within the Act, leads to legislative uncertainty since there is no determination from the Court as to whether the statutory provisions exist, and, most importantly, fails to address a properly preserved legal issue between the parties to the dispute now pending before the Court.
¶ 27. In sum, I would hold that
¶ 28. Even assuming that
¶ 29. In this case, Burton not only brought two claims in good faith equal to the amount he withheld from contractor, but he actually recovered on those claims — overbilling and faulty construction — to the point where contractor owed him money. The amount that Burton withheld bore a reasonable relation to the value of the claims he held in good faith; thus, the amount was not “wrongfully withheld.” See
¶ 30. Finally, contractor could not have been the substantially prevailing party in the proceeding because he did not actually recover any payment from Burton. Because of contractor‘s overbilling and faulty construction work, Burton had already
¶ 31. Under the majority‘s reasoning, a contractor who overbills a client and provides faulty construction work may recover attorney‘s fees even if the homeowner proves that all money withheld was withheld in good faith, as the statute allows. A contractor can accomplish this outcome as long as a homeowner simply brings too many claims against the contractor which cannot be proven (even if they were brought in good faith), despite the fact that the homeowner has not withheld any money for the nonprovable claims. Thus, while the purpose of the Act was to give a contractor a statutory right to recover for payments “wrongfully withheld,” the majority‘s holding will allow a contractor to recover attorney‘s fees even if he was not only never owed one cent, but in fact owed his client money.
¶ 32. The problem is even more apparent if the party roles of the homeowner and contractor are reversed, as it should not matter for prevailing-party status who was the plaintiff and who was the defendant. Take, for example, a case where a plaintiff-contractor brings a breach-of-contract claim for nonpayment against a defendant-homeowner. The defendant-homeowner brings counterclaims for overbilling, faulty construction, consumer fraud, and various other claims. Many of the homeowner‘s claims survive summary judgment. At trial, the plaintiff-contractor wins on his claim of breach of contract. However, the defendant-homeowner wins on his claims of overbilling and faulty construction. The plaintiff-contractor had overbilled and provided faulty construction to the homeowner in an amount that was more than the defendant-homeowner withheld in breach. The plaintiff-contractor ends up owing the defendant-homeowner money. I fail to see how the plaintiff-contractor can be a substantially prevailing party in this situation. Yet, this was the situation in the instant case, only with the parties’ roles reversed.
¶ 33. As if the implications of the majority‘s holding here were not serious enough at the superior court level, they are even more concerning at the small claims level, where a homeowner is more likely to appear pro se. Under the majority‘s reasoning, a pro se homeowner who withholds money from a contractor in good faith, and in fact recovers from the contractor, will have to pay the contractor‘s attorney‘s fees if the homeowner brought too many claims or counterclaims which he could not prove. Even if the homeowner can prove overbilling and faulty construction, as in this case, the contractor can still recover attorney‘s fees if represented by counsel. A pro se homeowner, who believed he or she had won at trial, may end up owing the contractor many times more in attorney‘s fees. This creates an incentive for contractors to overbill their clients and hope that the client brings too many claims that he or she cannot prove. The result is a chilling effect on plaintiffs not to bring otherwise good faith claims or counterclaims against a contractor whenever a contractor has asserted a prompt payment claim or counterclaim.
¶ 34. Reversing the attorney‘s fee award in this case is consistent with previous decisions addressing the attorney‘s fee issue. See, e.g., Fletcher Hill, 2005 VT 1; DJ Painting, Inc. v. Baraw Enters., Inc., 172 Vt. 239, 247, 776 A.2d 413, 420 (2001) (affirming decision that contractor was the “substantially prevailing party” where all of plaintiff‘s claims against it were dismissed on summary judgment). The Court‘s decision in Fletcher Hill stands only for the proposition that the “net victor” in a construction contract dispute will not automatically
¶ 35. In Fletcher Hill, a jury rendered a split decision in a construction contract dispute, awarding $15,067 to the contractor for breach of contract, and $4,000 to the homeowner based on the contractor‘s failure to perform in a workmanlike manner. The trial court found that no party had substantially prevailed and declined to award attorney‘s fees under
¶ 36. With one exception, the remaining cases cited by the majority do not involve the construction of statutory language similar to
¶ 37. The Pennsylvania Superior Court‘s decision in Zavatchen v. RHF Holdings, Inc., cited by the majority, ante, ¶ 8, supports a conclusion opposite to that reached by the majority here. 2006 PA Super 240, 907 A.2d 607. In Zavatchen, a claimant filed suit against several contractors, seeking damages of approximately $90,000. The contractors denied liability and requested reimbursement of their attorney‘s fees under the state‘s Contractor and Subcontractor Payment Act (CSPA). The court entered a verdict in favor of claimant for $300. The contractors then requested attorney‘s fees, arguing that they were the “substantially prevailing party” under the CSPA given the claimant‘s small recovery in proportion to his claimed damages. Zavatchen, 2006 PA Super 240, ¶ 5; see also Fletcher Hill, 2005 VT 1, ¶ 17 (noting that Pennsylvania statute allowing for recovery of attorney‘s fees in construction-contract disputes is identical to Vermont statute). The trial court denied the contractors’ request, and the superior court affirmed its decision on appeal. The court rejected the contractors’ argument that they “substantially prevailed” because the claimant was awarded less than one percent of the damages sought in his complaint, as well as their assertion that “determining whether a party substantially prevails turns on a simple mathematical comparison of the parties’ respective recoveries.” Zavatchen, 2006 PA Super 240, ¶ 6. It found that the contractors “did not clearly prevail in the sense that a judgment was entered in their favor,” nor had they shown that the claimant‘s claim was “groundless or frivolous.” Id. ¶ 11. The same can be said in the instant case.
¶ 38. It simply makes no sense to conclude that contractor substantially prevailed in its quest to recover payment within the scope of the Act, as required by
¶ 39. I am authorized to state that Justice Johnson joins in this dissent.
Motion for reargument denied July 22, 2010.
