BURTON DRYWALL, INC. v KAUFMAN
Docket No. 19113
Court of Appeals of Michigan
May 27, 1976
69 Mich. App. 85
BURTON DRYWALL, INC. v KAUFMAN
OPINION OF THE COURT
1. MECHANICS’ LIENS-STATUTES-COMMON LAW-STRICT CONSTRUCTION-ATTACHMENT-LIBERAL CONSTRUCTION.
The mechanic‘s lien statutes are in derogation of the common law and must be strictly construed to the point at which the lien attaches; thereafter, they may be liberally construed to fulfill the remedial objectives of the statutes (
2. MECHANICS’ LIENS-NOTICE TO OWNER-TIME LIMITATIONS.
A party seeking to claim a lien against a building for any amounts unpaid on material or labor furnished for that building must serve the owner with written notice within 90 days after furnishing the first of such materials or labor even where the lien claimant is dealing directly with the owner and not a contractor (
3. COURTS-SUPREME COURT-COURT OF APPEALS-APPEAL AND ERROR-OVERRULING PRECEDENT-OVERWHELMING AUTHORITY.
The Court of Appeals is not bound to follow a decision of the Michigan Supreme Court if it is convinced by overwhelming authority that the Supreme Court would overrule that authority were it deciding the question today.
DISSENT BY R. B. BURNS, J.
4. COURTS-PRECEDENT-INTERMEDIATE COURTS-SUPREME COURT-APPEAL AND ERROR.
It is inappropriate for an intermediate court to decide cases contrary to established precedent of the Supreme Court.
Appeal from Wayne, Charles S. Farmer, J. Sub-
REFERENCES FOR POINTS IN HEADNOTES
[1] 53 Am Jur 2d, Mechanics’ Liens §§ 17-25.
[2] 53 Am Jur 2d, Mechanics’ Liens § 174.
[3, 4] 4 Am Jur 2d, Appeal and Error §§ 11-16.
Complaint by Burton Drywall, Inc., against Harry Kaufman and Ben Kaufman, doing business as Westland Park Apartments, and against Kaufman Brothers Investment Company, Citizens Mortgage Corporation and Joseph Rickard seeking to foreclose a mechanic‘s lien. Summary judgment for defendants. Plaintiff appeals. Affirmed.
Gottlieb & Goren, for plaintiff.
Weiner & Hauser, for defendants.
Before: BASHARA, P. J., and R. B. BURNS and QUINN, JJ.
BASHARA, P. J. Plaintiff appeals a summary judgment granted to the defendants in an action to foreclose a mechanic‘s lien.
The defendant, Westland Park Apartments, was a partnership formed for the purpose of developing an apartment complex. The partners were the defendants Harry Kaufman, Ben Kaufman, and Joseph Rickard. The partnership entered into an agreement with Ricco, Inc., to act as general contractor on the project. The president and sole shareholder of Ricco, Inc., was Joseph Rickard.
Ricco, Inc., subcontracted with the plaintiff to provide drywall materials and labor to the project. Plaintiff‘s lien states that it began furnishing materials and/or labor to the construction site on January 12, 1971. The proof of service for the notice of intent to claim a lien discloses that the notice was served on the partnership on June 2, 1971, some 141 days after the work began.
The trial judge granted summary judgment on
Plaintiff contends that notice is not required where the party seeking the lien deals directly with the owner. The argument is that the plaintiff contracted with Ricco, Inc. Joseph Rickard is an officer and sole shareholder of Ricco, Inc. as well as a partner in Westland Park Apartments. Rickard‘s knowledge of plaintiff‘s claim is binding on the partners and partnership.
The mechanics’ liens act,
Section 1 of the mechanics’ liens act requires, inter alia, that the party seeking the lien serve the owner with a written notice of intent to claim a lien against a building for any amounts unpaid on material or labor furnished to that building. Such notice must be served within 90 days after furnishing the first of such materials or labor.1
However, there is a judicially created exception that one need not serve a notice of intent to claim a lien, where the lien claimant is dealing with the owner and not a contractor. Mielis v Everts, 264 Mich 363, 364; 249 NW 875 (1933). Since Mielis, no case law has examined the authority for such an exception, although subsequent cases have explained its rationale.
In Wallich Lumber Co v Golds, 375 Mich 323; 134 NW2d 722 (1965), the Court considered the priorities between a mechanic‘s lien and a mortgage. The mechanic‘s lien was found to have priority. The Mielis exception was inapplicable to the fact situation in Wallich and was only discussed to bolster the result. In obiter dictum the Court stated that notice was not required where the lien claimant deals directly with an owner, because the owner knows there is a claim against him. Wallich Lumber Co v Golds, supra, 328.
In J Altman Companies, Inc v Saginaw Plumbing & Heating Supply Co, 42 Mich App 747; 202 NW2d 707 (1972),2 the Mielis exception was again considered and its rationale approved. However, the Court found that Mielis did not apply because the lien claimant did not deal directly with the
We are of the opinion that Mielis3 was erroneously decided. Without explanation it made the following statement:
“It is first claimed that the lien of Albert Mielis is invalid because a notice of intention to claim a lien was not served upon the owners. It was not necessary. The lien claimants were dealing with the part-owner, not with a contractor. 3 Comp. Laws 1929, § 13101; Smalley v Ashland Brown-Stone Co., 114 Mich 104 [72 NW 29 (1897)].” Mielis v Everts, supra, 364.
Mielis’ reliance on Smalley v Ashland Brown-Stone Co, supra, was misplaced. That case interpreted the notice of intent to claim a lien requirement of § 1 of the mechanics’ liens act of 1891 PA 179, § 1, as amended by 1893 PA 199. The Smalley Court found that the notice was for protection of the subcontractor, materialman, or laborer to preserve its claim against the owner, and as such, was not a condition precedent to the lien attaching.
However, it apparently escaped the attention of the Mielis Court that § 1 of the mechanics’ liens act was amended by 1929 PA 264 to add the following:
“No person shall have a right to claim a lien as in this act provided, unless and until he shall have served a notice as in this section provided, and proof of the service of such notice shall be attached to the verified statement or account when filed with the registrar of
Webster v Cooper Development Co, 266 Mich 505, 507; 254 NW 186 (1934), construed this provision to require compliance with the notice provisions of the act as a condition precedent to the acquisition of a mechanic‘s lien. To the extent that Smalley v Ashland Brown-Stone Co, supra, held otherwise it was overruled sub silentio by Webster. Therefore, the Mielis exception is grounded on authority no longer of precedential value.
The Court of Appeals is not bound to follow a decision of the Michigan Supreme Court if it is convinced by overwhelming authority that the Supreme Court would overrule that authority were it deciding the question today.5 Duncan v Beres, 15 Mich App 318; 166 NW2d 678 (1968), Abendschein v Farrell, 11 Mich App 662, 680-684; 162 NW2d 165 (1968) (LEVIN, J., dissenting), affirmed, 382 Mich 510; 170 NW2d 137 (1969).
We believe that were Mielis examined today by the Supreme Court, it would be overruled for the following reasons. First, the amendment of 1929 PA 264 apparently escaped the attention of the Mielis court. That amendment clearly requires compliance with the notice provisions before a lien can attach. Webster v Cooper Development Co, supra. Second, Mielis failed to strictly construe the act by erroneously following obsolete law, and inadvertently judicially legislating an exception to the notice requirements. For these reasons we decline to follow Mielis.
Affirmed.
QUINN, J., concurred.
R. B. BURNS, J. (dissenting). Reluctantly, I must dissent. In my opinion we are bound by Mielis v Everts, 264 Mich 363; 249 NW 875 (1933). Mielis has not been overruled, but has been acknowledged in Wallich Lumber Co v Golds, 375 Mich 323; 134 NW2d 722 (1965), and J Altman Companies, Inc v Saginaw Plumbing & Heating Supply Co, 42 Mich App 747; 202 NW2d 707 (1972).
I do not think it appropriate for an intermediate court to decide cases contrary to established precedent of the Supreme Court.
