Burt Welding & Automotive Repair, Inc. v. U.W. Marx, Inc.Burt Welding & Automotive Repair, Inc. v. U.W. Marx, Inc.
Appeal from a judgment of the Supreme Court (Maney, J.), entered January 21, 1999 in Albany County, upon a decision of the court in favor of defendants.
This is an appeal from a judgment dismissing plaintiffs complaint following a bench trial. Plaintiff was a subcontractor on a construction project in which it agreed to install structural steel and precast concrete panels for $301,400. The essence of plaintiffs claim is that, because defendant U.W. Marx, Inc. (the general contractor) failed to properly coordinate delivery of the precast concrete panels to the job site, plaintiffs cranes were idle much of the time and, consequently, it was unable to perform the subcontract in a “continuous integrated fashion” allegedly resulting in damages.
In dismissing plaintiff’s complaint, Supreme Court found that the subcontract incorporated by reference the terms and conditions of the contract between the owner and U.W. Marx. That contract specifically precluded the assertion of any claim for money damages based upon delay in the progress of the work. In addition to noting plaintiff’s failure to present testimony at trial “in a coherent fashion” to support its claim that it expended additional labor and materials as a result of U.W. Marx’s failure to efficiently coordinate the project, Supreme Court found no basis to avoid the application of the incorporated no-damage-for-delay clause, the validity of which was most recently reaffirmed in Corinno Civetta Constr. Corp. v City of New York (
To avoid the legal consequence of this provision, plaintiff
Plaintiffs remaining contentions have been rendered academic by our affirmance of Supreme Court’s interpretation of the legal obligations created by the contract documents or have been reviewed and rejected as unpersuasive.
Spain, J. P., Mugglin, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with costs.