Lead Opinion
Appellants Mr. and Mrs. Burns contracted with Blanken and Silverman Construction Company for the construction of two houses (for residential and rental usеs). When the construction company went into default, appellee-Hanover Insurance Company (as surety for the construction сompany) completed the contract at a date later than that originally scheduled. When the Burnses refused to pay the balance of the contract price and the cost of additional work Hanover brought an action for breach of contract. Apрellants counterclaimed for breach of contract by the construction company. The trial court found that appellants wеre liable for the unpaid balance on the contract and that appellee was liable as surety for damages for unexcused delay for seven months. The court further found that damages against appellee were limited by Article 3 of the contract.
The sole issue raised in this appeal is whether Article 3 constitutes a liquidated damages clause and the exclusive remedy for delay damages. We find the contested article to be a liquidated damages clause and therefore affirm.
Article 3 provides:
*327 Time of Commencement and Completion
The work to be performed under this Contract shall be commenced within two working days of issuance of necessary demolition and building permits, and completed within 200 days after all necessary building рermits have been issued by the appropriate authorities. (Here insert any special provisions for liquidated damages relating to failure to complete on time)
The Owner will suffer financial loss if the Project is not completed by the above date. The contractor shall be liable for and shall pay to the Owner, on an actual expense basis as established by receipts, not more than $1,000 for packing and storage of furnishing and $30 per day for temporary accommodation.
It is well-settled that parties to a contract may agreе in advance to a sum certain to be forfeited as liquidated damages for breach of contract. Such a bargained-for liquidated dаmages clause is valid unless it is found to constitute a penalty. Order of AHEPA v. Travel Consultants, Inc., D.C.App.,
damages stipulated in advance should not be more than those which at the time of the execution of the сontract can be reasonably expected from its future breach, and agreements to pay fixed sums plainly without reasonable rеlation to any probable damage which may follow a breach will not be enforced. [AHEPA, supra at 126 (quoting Davy v. Crawford, 79 U.S. App.D.C. 375, 376,147 F.2d 574 , 575 (1945)).]
There is no question that Article 3 does not constitute a penalty. Appellants posit that because the actual damages incurred by them exceeded the stipulated sum, Article 3 is unreasonable and therefore unenforceable.
Appellants assert thаt because Article 3 refers only to three specific areas of damage, the clause does not limit other delay damages. Parties may limit damages in certain areas and not in others by including in the contract both a liquidated damages clause applicable to damages which are difficult to ascertain along with a clause providing actual damages. Hathaway & Co. v. United States,
Interpretation of a contract provision is a question of law for the court to decidе and this court will not reverse such a decision absent a showing of error of law. D.C.Code 1981, § 17-305(a). Considering the evidence in light of this standard, we conсlude that the trial court did not err in ruling Article 3 to be an enforceable liquidated damages clause and the sole remedy for delay damаges under the contract. Finding no reversible error in the judgment, we
Affirm.
Notes
. Appellants did not present — nor have we located — any case wherе a liquidated damages clause was found unenforceable because the damages provided were disproportionately low in relation to the actual damage incurred. See Coast Trading Co. v. Parmac, Inc.,
. The fact that Article 3 deviates from the more common liquidated damages clause by sеtting a ceiling on damages in lieu of setting a finite per diem amount does not void the agreement entered into by the parties.
. Appellants contend that even if Article 3 is found to be a liquidated damages clause, it is unenforceable because the delays involved were рrolonged, almost rising to the level of abandonment. We find this argument unsupported by the facts.
Dissenting Opinion
dissenting:
I cannot agree with the majority’s determination thаt Article 3 constitutes a liquidated damages clause. By definition, a liquidated damages clause specifies a sum certain to be forfeited in the event of breach of contract. Order of Ahepa v. Travel Consultants, Inc., D.C.App.,
