Clyde Burnham and fourteen other plaintiffs, representing nine households, purchased nine modular
The jury verdict established that Mark IV breached the implied warranty of merchantability. See G. L. c. 106, § 2-314. In the circumstances, that breach was a violation of G. L. c. 93A, § 2. The plaintiffs, therefore, are entitled to recover their reasonable attorney’s fees and costs, G. L. c. 93A, § 9 (4), which the judge shall determine on remand. We remand the case also for him to determine whether, upon demand, Mark IV refused to grant relief to the plaintiffs in bad faith with knowledge or reason to know that the act or practice complained of violated G. L. c. 93A, § 2, and for him to assess damages if appropriate in accordance with that determination.
1.
Background.
The evidence tended to prove the following. Eugene Kapper, doing business as Snow’s Modular and Mobile Home Sales (Kapper) from his place of business in Winchester, New Hampshire (a few miles north of the
At various times within a few months of installation, the roofs of the plaintiffs’ units began to leak. During the winter, snow built up on the relatively flat roofs of their units and, since these roofs did not overhang the sides of the units, melted snow ran down their outside walls, saturating the walls and occasionally covering walls, windows, and doors with sheets of ice. Water pipes in some of the units also froze in the winter, allegedly due to improper placement and insulation.
Employees of Kapper and, eventually, the plaintiffs themselves, attempted to solve the leakage problems by applying liquid sealers to some of the roofs. These attempts did not prevent leakage for any significant length of time. Other plaintiffs had new roofs laid over the old, which stopped the leakage. By letters dated September 3, 1975, an attorney representing Stone and the five households that had purchased units from him notified both Kapper and Mark IV of
2. Exemption from, G. L. c. 93A liability. Mark IV based its motion to dismiss the plaintiffs’ c. 93A claims solely on its entitlement to the exemption from liability created by c. 93A, § 3 (1) (b). 8 Since the judge granted Mark IV’s motion without making findings of fact, we assume (with the parties) that he accepted Mark IV’s argument. The plaintiffs argue that the judge erred in granting Mark IV’s motion. We agree.
The parties stipulated at trial that the only issue raised by the judge’s granting of Mark IV’s motion to dismiss is whether the transactions and actions complained of by the plaintiffs
One of the theories on which the plaintiffs’ case was submitted to the jury was that Mark IV had breached the im
The sales of the modular homes to the plaintiffs constituted “transactions in goods” under G. L. c. 106, § 2-102, because those units were “movable at the time of identification to the contract for sale” and hence are “goods” as defined in c. 106, § 2-105 (1).
Fuqua Homes
v.
Evanston Bldg. & Loan,
The question dispositive of the plaintiffs’ appeal is whether Mark IV presented evidence warranting a finding that its breach of the implied warranty of merchantability did not occur “primarily and substantially within the commonwealth.” G. L. c. 93A, § 3 (1)
(b)
(i). The evidence is un
3.
Multiple
damages,
attorney’s
fees,
and costs.
The plaintiffs’ right to recover under G. L. c. 93A, § 2, entitles them to an award of reasonable attorney’s fees and costs incurred in asserting their rights. G. L. c. 93A, § 9 (4).
12
The plaintiffs, while conceding that their actual damages have been established by the jury’s verdict, assert that they are entitled, in addition, to multiple damages under G. L. c. 93A, § 9 (3). Under G. L. c. 93A, § 9 (3), as amended through St. 1979, c. 406, § 2, the judge may award up to three but not less than two times the amount of the plaintiffs’ actual damages if he finds that “the use of employment of the [unfair or deceptive] act or practice was a willful or
This alternative basis for an award of multiple damages “is an attempt to promote prelitigation settlements by making it unprofitable for the defendant either to ignore the plaintiff’s request for relief or to bargain with the plaintiff with respect to such relief in bad faith. The knowledge or reason to know is that which exists after receipt of the complaint and not at the time of the alleged violation. The standard is objective and requires the defendant to investigate the facts and consider the legal precedents.”
Heller
v.
Silverbranch Constr. Corp.,
4. Grant of directed verdict. In its appeal, Mark IV argues that the judge erred in granting a directed verdict in favor of Ronald Stone with respect to a counterclaim made by Mark IV against Stone. In that counterclaim, Mark IV had alleged that Stone “caused, or . . . permitted, said mobile home units to be improperly erected and improperly placed on site prior to sale,” and that the damage to the plaintiffs’ property resulted from this improper placement and erection. Mark IV failed to sustain its burden of proof in regard to this claim. There is no dispute that each of the units in which the plaintiffs resided was erected by employees of Kapper, a dealer of Mark IV homes, or that Mark IV homes always were erected by the dealer. The defendant directs us to no evidence from which a trier of fact reasonably could conclude that Stone erected the homes or that Kapper, in erecting the six homes originally sold to Stone, was acting as Stone’s agent. There was no error.
5.
Admission of testimony relevant to notice.
Mark IV claims error in the admission of the testimony of Lowell Baldwin who, as a New York dealer of homes manufactured by Mark IV, had sold three such modular homes with roofs substantially similar to those of the plaintiffs’ units. Baldwin testified, over Mark IV’s objection, that in March, 1974, he
Evidence was introduced from which a trier of fact reasonably could conclude that Stone bought two Mark IV units in April, 1974, and later resold one of them to the Burnhams. The plaintiffs alleged that Mark IV negligently tested, inspected, marketed, advertised, and sold the homes. 16 Whether Mark IV reasonably should have known of these leakage problems at the time of the sale of its units to Stone in April, 1974, is relevant to the issue whether Mark IV was negligent in the testing, inspection, marketing, and sale of the homes. Baldwin’s testimony regarding complaints he made to Mark IV’s employee in March, 1974, bears on that issue. Since notice was therefore an issue in the case, the defendant’s claim of error is without merit.
6.
Jury instructions.
Mark IV objected to the judge’s instruction to the jury that, with respect to mitigation of damages, “a plaintiff cannot sit idly by and let damages increase without doing something about it. . . . [T]he plaintiffs, however, are not obligated to expend more than a nominal sum to repair the damages. . . . [I]t’s the law
that the plaintiffs . . . must take all reasonable means to mitigate the dam
The general rule with respect to mitigation of damages is that a plaintiff may not recover for damages that were avoidable by the use of reasonable precautions on his part.
Fairfield
v.
Salem,
While the judge perhaps should have explained the law regarding mitigation of damages more clearly, emphasizing the factor of reasonableness and laying less stress on the amount of money expended which a trier of fact might find to have constituted a reasonable effort at mitigation, we do not comprehend how his use of the term “trifling” could have misled the jury. It appears that all plaintiffs took some measures, ranging from coating all or parts of their roofs
Mark IV also asserts that the judge erred in instructing the jury on the assessment and measure of damages, in that his instructions allegedly led the jury to believe that, if they found for the plaintiffs, the plaintiffs were entitled to recover the amount it would cost them to have their roofs replaced. The judge instructed the jury that the plaintiffs’ recovery, if any, with respect to the problems with their roofs, should be “a sum of money that would place them back in the position that they were. In other words, [with] a good leak-proof roof.” He further instructed them that because, as “we are all aware of the fact that inflation has swept the country, . . . the amount of damages [awarded should] be based upon [the amount necessary] to fix the roof, at a reasonable time after the damage has occurred.” This was clearly not an instruction that the jury should find in an amount that would enable the plaintiffs to replace the roofs. Taken in its entirety, the charge left to the jury to decide what constituted a reasonable remedial measure and what the cost of that measure would be. This claim of error is therefore groundless.
Mark IV argues, finally, that the judge erred in instructing the jury, if they found for the plaintiffs, to deliver a verdict granting a single award of damages. This instruction was based on the judge’s belief that the complaint was so
7. Disposition. The case is remanded to the Superior Court where the judge shall determine the amount of reasonable attorney’s fees and costs which are to be awarded to the plaintiffs. The judge shall also determine whether Mark IV refused to grant relief upon demand to the plaintiffs in bad faith with knowledge or reason to know that the act or practice complained of violated G. L. c. 93A, § 2, and, if he determines that to have been the case, shall fix the amount of damages to be awarded to the plaintiffs. G. L. c. 93A, § 9 (3). The judgment in favor of the plaintiffs entered on October 27, 1980, is to be modified in accordance with these determinations. The judgment in favor of Stone on Mark IV’s counterclaim, entered on October 24, 1980, is affirmed.
So ordered.
Notes
These homes were designed to be transported in two sections to a homesite, and placed on permanent foundations.
Doing business as Homes by Dunhill.
Since the motion was filed during trial and pressed by the defendant at the close of the plaintiffs’ case, it was not error for the judge to rule on the motion at that time, although it would have been preferable for him to have heard all the evidence before disposing of the motion.
Stone sued Mark IV solely in his capacity as the “consumer” of the home he retained, and not as a purchaser of homes for resale. Compare §§ 9 and 11 of G. L. c. 93A.
Stone could not have been responsible, of course, for the installation of those units purchased directly from Kapper by the Heaths, Chaisson, and the Garbiels, and these plaintiffs signed releases to that effect.
The pertinent provisions of G. L. c. 93A, § 3, as amended by St. 1969, c. 814, § 2, are as follows:
“(1) Nothing in this chapter shall apply to it
“(b) trade or commerce of any person of whose gross revenue at least twenty per cent is derived from transactions in interstate commerce, excepting however transactions and actions which (i) occur primarily and substantially within the commonwealth, and (ii) as to which the Federal Trade Commission . . . has failed to assert in writing within fourteen days of notice to it and to said person by the attorney general its objection to action proposed by him and set forth in said notice; or
“(c) transactions or actions by any person who shows that he has had served upon him by the Federal Trade Commission a complaint ....
“(2) For the purpose of this section the burden of proving exemption from the provisions of this chapter shall be upon the person claiming the exemption” (emphasis supplied).
The Attorney General, in an amicus brief, urges us to set forth a list of factors similar to those considered by courts in choice of law situations (see Restatement [Second] of Conflict of Laws § 6 [1971]), to be used in determining whether a particular action or transaction occurred primarily and substantially within the Commonwealth. The Attorney General notes that, in the context of suits brought by businessmen under § 11 of G. L. c. 93A, several Federal courts have used what appears to be a variant of such an analysis, and concluded that recovery under c. 93A was barred by the provisions of § 3 (1) (£>). See, e.g.,
Boston Super Tools
v.
RW Technologies,
Regulation VII B, 20 Code Mass. Regs., Part 5, at 28 (1975), currently found in 940 Code Mass. Regs. § 3.08 (2) (1978).
But see
State ex rel. Tierney
v.
Ford Motor Co.,
The defendant did not attempt to limit the award of fees and costs by making a written offer of settlement. See G. L. c. 93A, § 9 (4).
Such a demand is unnecessary where the defendant does not maintain a place of business or keep assets within the Commonwealth. G. L. c. 93A, § 9 (3).
The regulation of the Attorney General, whereby breaches of warranty constitute unlawful acts under § 2 of G. L. c. 93A, was promulgated in 1971.
Since Mark IV maintained no place of business and did not keep assets within the Commonwealth, it could have limited any award of damages under the statute by making a reasonable written offer of settlement and paying the rejected tender into court as soon as practicable after receiving notice of commencement of suit against it. G. L. c. 93A, § 9 (3).
We note that those plaintiffs who purchased their units from Stone apparently did not begin to complain about leakage problems until after Stone had purchased the last of those units he later resold to other plaintiffs.
See
Matter of the Estate of Stannard,
Mark IV took the position at trial that the leakage problems could have been solved without replacement of the roofs.
