The record we are called upon to inspect and examine bears the handiwork of ver y many learned and skilful legal artists. The names of six able and competent lawyers appear on the briefs of respondent, and the learned referee informs us “ that the defense of this action has been conducted by four different city attorneys with conspicuous zeal and ability, which would certainly have resulted in a victory for the city if the facts in the case had made such a victory possible.” We are confronted with no less than five briefs of considerable length, which have served to increase our labors with no great corresponding benefit. The practice of filing several briefs, unsanctioned by any rule, tends rather to the confusion than the enlightenment of the court. Several important and interesting questions are involved in the decision of this case, which have .been ably argued by counsel, and which we have taken time to consider with the attention and deliberation their importance and difficulty seemed to require.
The plaintiffs’ claim seems to be one largely sounding in damages, based upon certain alleged faults or imperfections in the plans and specifications for the sewer, and shortcomings of the board of public works, but, inasmuch as counsel on both sides, as well as the referee, have treated it as a claim for extra work under the contract, we shall consider it in that view. So far as we are able to group the claims upon which the plaintiffs’ right of recovery is based, they are as follows: (1) Defects or imperfections in the plans and specifications. (2) Failure of the board of public works to provide a suitable foundation for the sewer where it passed over soft and mucky ground. (3) Failure and refusal of the board of public works to settle and adjust the plaintiffs’ claims for extra compensation under the contract. (4) Waiver by defendant of the provisions of the contract requiring extra work to be agreed upon and written monthly statements of
1. The plans and specifications do not provide definitely for a foundation to be placed under any part of the work. The specifications, however, contain the following provision: “ "Whenever the soil is sufficiently firm, the sewer of either design will be laid directly upon the bottom of the proper excavation; but when, in the opinion of the board of public works or engineer in charge, an extra foundation will be necessary to insure stability to the work, the contractor will be required to erect and put into place such timber, piling, brick, masonry, concrete, gravel, sand, or other suitable materials, in the manner directed by the board of public works, which shall be measured by the engineer in charge of the work, and paid for at the schedule rates set forth in the accepted bid of the contractor; but no allowance shall be made to the contractor for any extra excavation incurred by building and putting in place such extra foundation or extra work.” The plans contained a sketch or drawing of the foundation to be provided for such sewer whenever the same might be found necessary and be directed by the board of public works; so that with reference to the straining chamber and the sewer proper it was a matter resting wholly in the good judgment and discretion of the board whether a foundation should be required and put in or not. This discretion was to be exercised in view of all the circumstances, and with reference to all of the work required under the contract. The straining chamber was a part of the sewer, and from the very nature of the situation no human foresight could determine in advance whether a foundation would be necessary or not. Any attempt to base a liability on the part of the city because the plans and specifications did not absolutely require a foundation to be placed Thereunder is without support.
2. As has already been stated, the plans and specifications did not specifically require a foundation to be placed under the sewer. Under the provisions already quoted the necessity of such foundation was left to the judgment and discretion of the board of public works. Under the plainest principles, whatever talk or understanding there might have been prior to the execution of the written contract became merged therein, and the embraet thereafter became their rule and guide with reference to the subject matter thereof. One of the important claims of the contractor is based upon the failure of the board of public works to cause a foundation to be laid under the sewer along South Water street. It is a fact concerning which there is no dispute that for a portion of the distance along said street the soil was wet and marshy, and consisted of black muck, mixed with sand and shells.' With reference to this matter the referee finds: “ That the plans and specifications contemplated the placing of a cradle or other suitable foundation under said sewer in and along such soil as the South Water street muck bed, and that, if said plans and specifications had been followed and carried out by said board of public works, such foundation would have been ordered.” He further found that the board “obstinately and unreasonably refused to order or permit any foundation to be placed under said timber sewer,” and that by reason thereof it “ was guilty of gross negligence.” Along this line he also makes a further finding “ that no person of ordinary skill and prudence would have attempted or required the construction of a wooden sewer laid directly upon said muck bed without any cradle or other suitable foundation provided therefor, and that the then city engineer of said defendant city had made special provision in said plans and specifications for such foundation, which
In speaking of the binding character of the finding of an arbitrator, Bovill, C. J., in Pappa v. Rose, L. R. 7 C. P. 32, at page 42, says: “ It by no means follows that when two persons submit a matter in difference to the arbitrament of a third, they agree to take a person of the greatest amount' of skill or intelligence. No matter what may be the degree of skill he possesses, the decision of the person selected is final and conclusive.” See, also, same case in same volume, page 525, and Tharsis S. & C. Co. v. Loftus, L. R. 8 C. P. 1. In this latter case it is distinctly held that there is no distinction between want of skill and want of diligence of the arbitrator. That the parties have agreed to be bound by his decision for better or worse, and when honestly made, is conclusive.
Cases are numerous where the parties have contracted with reference to the skill, judgment, or discretion of an architect. In Hudson v. McCartney, 33 Wis. 331, Dixon, C. J., says: “It was clearly competent for the plaintiffs to stipulate that they should only demand or receive payment for the work as the same was executed to the full and complete satisfaction of McDonald, the superintendent of the erection of the dwelling, and upon his certificates as the work progressed; and such satisfaction of the superintendent, and the execution of the certificate by him, became and was a condition precedent to the right of the plaintiffs to demand or sue for the price agreed to be paid by defendant for the work, unless the refusal to certify should be disregarded or annulled on the ground of fraud or bad faith, or clear evidence of mistake on the part of the superintendent. And, should the certificate, be fraudulently or corruptly withheld by the superintendent, it would be the opinion of some most respectable courts that there could be no recovery
These cases are cited only to sustain the proposition that, when contracting parties have seen fit to vest in some person the exercise of some judgment and discretion relative to the subject matter of the contract, no liability can arise in the exercise thereof, unless it be shown that his acts or refusal to act Avere so palpably perverse as to clearly indicate bad faith and dishonesty. Neither the evidence in the case nor the finding of the referee justifies any such conclusion. The sewer along South Water street was over a quarter of a mile in length. For a greater portion of the distance it was constructed over marshy and porous soil. The evidence is practically undisputed that the bottom of the sewer did not sink. A portion of it, from seventy-five to one hundred feet, Avhen the top had depressed, was rebuilt. The remainder seems to have stood in good shape, and was accepted by the city after the seams and abutting ends of timber had been calked to prevent the influx of water. The rebuilt portion, so far as we are able to discover, was reconstructed without a foundation, and the whole line was standing in good shape
3. It is insisted with great earnestness that the board of public works failed and refused to settle or adjust the plaintiffs’ claims for extra compensation under the contract. By sec. 20, subch. 5, ch. 184, Laws of 1814, the power is given the board of public works to determine all questions as to the amount earned under any contract according to its true intent and meaning, and it is provided that such adjustment and determination by said board shall be final between the parties, and binding upon them. It also provides that every contract with the city shall be made expressly subject to the
It needs but an inspection of the charter provisions and the contract to disclose the fact that the contractor was required thereby to present to the board a written statement of his claims for extra work or materials. It is an admitted fact that there has been no compliance with this requirement. Except in certain particulars, hereinafter noticed, there has been no attempt to comply therewith. The board of public works were appointed, bylaw and by the contract, arbiters to adj'ust and determine the proper performance of the work and the amount earned under the contract according to its true intent and meaning. It was likewise made the duty of the contractor to make out and present to them a written statement of the amount claimed for extra or additional work and materials. The claim sued upon, or anything like it, has never been presented.
The only excuse offered is that the board knew ‘the contractor had a claim for extras, and from time to time had discussed matters with him, and it seems to be assumed that, because certain inspectors and certain members of the board were present during the progress of the work and knew
The plaintiffs’ dilemma is not relieved by the finding of the referee. He simply finds that, after the work was completed, Burnham “made numerous attempts to induce the said board of public works to adjust and settle his various claims for extra compensation under said contract, and that said board refused to give the said Burnham a full or fair hearing in and about said matter.” It appearing affirmatively that no statement of the contractor’s claims was ever presented, it is but a waste of time to pursue this discussion further.
5. It now remains for us to consider the character and amount of the contractor’s demands, and the action of the board with reference thereto. Aside from the amount admitted to be due by the defendant, which will be noted hereafter, the plaintiffs base their right of recovery upon the failure of the defendant to cause a foundation to be placed under the sewer, and the change in the curve and the straining chamber. To their complaint are attached two exhibits, supposed to contain a statement of their claims. The first (Exhibit A) commences in June, 1881, and runs to June, 1882, and assumes to cover the expenditures made by Rice while attempting to carry out the contract. It is made up of items for fuel, use of pump, and labor, amounting to $15,639; brick, extra spikes, and extra lumber, $774; and superintendence, $3,000,— making, in the aggregate, $19,413. The larger amount is made up of items ranging from $35 to $1,870, without dates, except the names of the months are noted on the margin, and running through a period of thirteen months. The other claim (Exhibit B) commences April 17, 1884, and runs to May 7, 1885. It is itemized somewhat more at length than the other exhibit as to amounts and dates, but is equally indefinite as to what part of the work
The testimony to support Exhibit B is even more unsatisfactory. The bill itself furnishes absolutely no information as to the circumstances under which the expenditures were incurred, and it is not helped out by the oral testimony. There are dozens of items, “Cash, pay men; ” also for cash paid to different men and firms, without any explanation as to the purpose or necessity therefor. One of the most familiar rules of evidence is that the best evidence the nature of the case is susceptible of should be produced. It is significant in this case that the books containing a record of the expenditures, etc., claimed to have been incurred by the contractor were not produced. Owing to the peculiar nature of the plaintiffs’ claim, it was necessary that they make out a case with reasonable certainty, and to produce such evidence as would enable the court to readily ascertain a basis upon which to found a recovery. Maas v. Succession of
The evidence shows that when the excavation of the straining chamber was about completed, it was discovered that it had been located on land to which the city had no right, and the location was changed. On March 17, 1884, Mr. Rice, the contractor, presented a petition to the common council, setting out the change, and stating that he had been put to large expense, being obliged to sink two chambers instead of one, and asking for an allowance of §700 therefor. The petition was laid over until the final completion of the work. On March 16, 1885, the board of public works sent a communication to the council to the effect that it was their opinion that the contractor was entitled to extra pay for such work, and asking the council to adjust the claim. Accordingly an order was drawn in favor of Mr. Burnham for §700. In March, 1882, Rice presented claims for extra excavation at the curve, and extra brick, amount
This case is a striking example of the exceeding looseness with which municipal contracts are sometimes carried out. Contractual obligations rests very lightly when there is influence with the governing power. Whether the plaintiffs in this case might have been entitled to some greater allowance for extras than they received, had they placed themselves in a position to demand it, it is not our purpose to inquire. We simply pass upon the situation as presented, and do not hesitate to conclude that under no theory of the law or of the facts in the record can the plaintiffs’ recovery be sustained. The defendant virtually admits that the plaintiffs are entitled to the $700 allowed by the council, and the-sum of $4,787.48 found due by the board of public works. Orders for these amounts were tendered to the plaintiffs, but were refused. For these amounts the plaintiffs are entitled to judgment, with interest, unless there has been a tender of money, kept good under the rule, or a tender of judgment, which the record here fails to disclose.
By the Cowt.— The judgment of the superior court of Milwaukee county is reversed, and the cause is remanded with directions to enter judgment for plaintiffs and respondents in accordance with this opinion.