Lead Opinion
OPINION
Burlington Northern Railroad Company (Burlington) appeals a judgment entered in favor of Southwestern Electric Power Company (SWEPCO) following a jury trial. Burlington challenges the trial court’s submission of certain jury questions, entry of a declaratory judgment, and award of attorney’s fees. SWEPCO raises two conditional cross-points of error challenging certain evi-dentiary rulings made by the trial court for our consideration only in the event we decide to revеrse the judgment. We sustain each of Burlington’s points of error, overrule SWEP-CO’s cross-points, and render judgment that SWEPCO take nothing.
In 1974, Burlington and SWEPCO entered into a long-term contract
Initial shipping rates to be charged by the railroads were listed in the contract. In an appendix to the contract, a clause entitled “Escalation Formula” provided that the rates would be adjusted once each year according to the AAR Western Index of Railroad Material Prices, Wage Rates and Supplements Combined, published annually by the Interstate Commerce Commission. Immediately following the escalation formula provision was this clause entitled “Formula Intent”:
It is the intent of [the parties] that the formula described above will compensate [the railroads] for any changes in the cost of transporting SWEPCO’s coal tonnages above or below the 1971 base cost level. If any one of the parties should suffer a gross inequity as a result of unusual economic conditions, which result in the formula failing to fairly cover cost changes, such inequities will be resolved by mutual agreement among [the parties]. Pending such agreement, no party shall be relieved of its*96 obligations as outlined in the effective tariff.
In 1984, the parties entered into a second contract which superseded the original contract as to the Welsh plant only. The terms of this contract were similar to those of the first, including the escalation formula and formula intent clauses, except that the rates were to be adjusted quarterly based on the Interstate Commerce Commission Interim Mid-Quarter Forecast Index. The first contract continued in force as to the Flint Creek plant. Both contracts specified minimum and maximum quantities of coal to be shipped each year.
Each year since the effective dates of the contracts, Burlington has delivered and SWEPCO has received quantities of coal within the annual contractual ranges. Rates have been computed according to the formulas and indexes specified in each contract.
In thé late 1980s, SWEPCO began to suspect that Burlington’s costs of transporting coal were not increasing at the same rate at which the industry indexes were causing shipping charges to rise under the contract. Following unsuccessful negotiations with Burlington, SWEPCO filed this suit, claiming that under the contracts’ formula intent clauses, it had suffered gross inequities as a result of unusual еconomic conditions which caused the formulas to fail to fairly cover changes in the cost of transporting the coal. SWEPCO sought damages for alleged overcharges caused by discrepancies between Burlington’s actual shipping costs and the rates charged from 1987 to 1994.
The jury found that SWEPCO had not suffered a gross inequity under either contract as a result of the escalation formulas failing to fairly cover changes in Burlington’s cоst of transporting SWEPCO’s coal.
Burlington contends that the trial court erred in submitting to the jury the questions regarding unjust enrichment. Burlington argues that recovery by SWEP-CO of alleged overcharges under principles of unjust enrichment is barred because the issue of the rates to be charged for the coal shiрments was fully addressed by the contracts themselves. Burlington asserts that the jury’s finding that SWEPCO suffered no gross inequity, as defined in the contracts’ formula intent clauses, prohibits SWEPCO from challenging the rates it paid under the express terms of the contract.
The doctrine of unjust enrichment belongs to the measure of damages known as quasi-contract or restitution. LaChance v.
The unjust enrichment doctrine applies the principles of restitution to disputes which for one reason or another are not governed by a contract between the contending pаrties. See Lone Star Steel Co. v. Scott,
A remedy such as unjust enrichment that is based on quasi-contract or a contract implied in law is unavailable when a valid, express contract governing the subject matter of the dispute exists. Woodard v. Southwest States, Inc.,
The fact that a party to a contract has made a profit is an insufficient ground on which to order restitution on a theory of unjust enrichment. City of Corpus Christi v. S.S. Smith & Sons Masonry, Inc.,
In this case, the rates charged for Burlington’s hauling of SWEPCO’s coal were fully governed by the terms of the contracts. The contracts established base rates to be applied initially and then incorporated formulas by which the rates were to be adjusted periodically. SWEPCO concedes that Burlington satisfied all of its contractual duties pertaining to the shipment of coal and that the rates assessed were in accordance with the formulas set out in the contracts.
The trial court is required to submit requested questions to the jury if the pleadings and any evidence support them. Elbaor v. Smith,
*98 It is the intent of [the parties] that the formula described above will compensate [the railroads] for any changes in the cost of transporting SWEPCO’s coal tonnages above or below the 1971 base cost level.
SWEPCO argues that under this provision, evidence at trial that the formula overcompensated Burlington for changes in its shipping costs raised an issue of unjust enrichment which the court was required to submit to the jury.
SWEPCO’s reliance on a contractual provision to justify the court’s submission of the unjust enrichment questions exhibits a misunderstanding of the basis of the unjust enrichment doctrine. SWEPCO is actually arguing that Burlington breached the formula intent provisions of the contracts by charging excessively high rates pursuant to the escalation formulas. SWEPCO’s pleadings properly complained of this alleged breach by claiming that the rates had risen so high as to constitute a gross inequity as defined in the formula intent clause. Not only was this claim the primary ground of recovery SWEPCO pursued at trial, it was in fact the only valid ground. The jury failed to find that SWEPCO suffered a gross inequity under the contract. Because the issue of shipping rates was completely governed by the contract, there was no evidence to justify the court’s submission to the jury of additional questions concerning unjust enrichment.
SWEPCO cites the opinion of this court in Bowers v. Missouri, K & T. Ry. Co.,
SWEPCO cites numerous other cases in an attempt to support its novel interpretation of the unjust enrichment doctrine. Staats v. Miller,
Burlington also contends that the trial court erred in granting the declaratory judgment establishing the method by which rates are to be assessed for the remainder of the life of each contract.
In the declaratory judgment, the trial court held that the rates produced by the contracts’ escalation formulas were interim rates and decreed that the final rates were to be based on the amounts necessary to compensate Burlington for any changes in the cost of transрorting the coal above or below the base levels specified in the contracts. These declarations fatally conflict with the jury’s answers to the two questions regarding gross inequities under the contract.
Issues of fact in a declaratory judgment proceeding may be decided by a jury. Tex. Crv.PRAC. & Rem.Code Ann. § 37.007 (Vernon 1986). The court’s charge listed each of the material terms of the formula intent and gross inequity provisions of the contract and instructed the jury to interpret them. Cf. Exxon Carp. v. West Texas Gathering Co.,
The trial court based its award of attorney’s fees on Tex.Civ.Prac. & Rem.Code Ann. §§ 37.009 and 38.001 (Vernon 1986). Section 37.009 allows the award of attorney’s fees in declaratory judgment actions. Section 38.001 allows attorney’s fees in a suit for freight or express overcharges. Because we invalidate both grounds of recovery contained in the judgment, the award of attorney’s fees must be reversed as well.
SWEPCO raises two conditional cross-points to be considered by this court only in the event that we dеcide to reverse the trial court’s judgment. See Shearson Lehman Hutton, Inc. v. Tucker,
SWEPCO contends that the trial court erred in granting Burlington’s motion for sanctions for abuse of discovery under Tex.R.Civ.P. 215(5) with regard to a copy of deposition testimony given in an unrelated proceeding by Burlington vice-president Richard Sandgren. The evidence indicated that Burlington made numerous requests in the months preceding trial for SWEPCO to produce all documents in its possession containing any testimony by Burlington employees or former employees. In April 1994, Burlington specifically requested production of any statements made by Sandgren. Counsel for SWEPCO testified that they became aware that the Sandgren deposition was in their possession sometime in September or October 1994. SWEPCO notified Burlington of the document’s existence on October 7. Burlington repeated its request for the document during pretrial hearings on October 12 and 17. The document was ultimаtely produced to Burlington on October 21. Jury selection for the trial began on October 18, and opening statements were made on October 24.
The trial court based its imposition of the sanction primarily on a certification date contained on the front of the document in question. The date indicated that SWEPCO’s attorneys obtained a certified copy of the deposition on September 11, 1994. The trial court held that, based on this certification date, it was an abuse of discovery for SWEP-CO to fail to deliver the document until October 21.
A trial court’s ruling on a discovery motion will be reversed only upon a showing that the court committed a clear abuse of discretion. Global Servs., Inc. v. Bianchi,
SWEPCO further contends that the trial court erred in allowing Burlington to introduce evidence of SWEPCO’s financial condition. Evidence of a party’s financial condition is admissible if it is pertinent to a material issue in the case. See Birchfield v. Texarkana Memorial Hosp.,
The trial court’s judgment is reversed, and judgment is rendered that SWEPCO take nothing by its suit.
Notes
. Because the enforceability of a long-term contract between a railroad and one of its customers was unclear under the regulatory system prevailing at the time, the terms of the contract were set out in a letter of understanding signed by each of the parties.
. The Kansas City Southern Railway Company and the Louisiana and Arkansas Railway Company wеre also parties to the contract and were original defendants in this suit. Before trial these parties settled with SWEPCO.
. The questions regarding gross inequity read as follows:
Do you find that SWEPCO has suffered a gross inequity as a result of unusual economic conditions resulting in the escalation formula in the [Flint Creek, Welsh] Contract ... failing to fairly cover changes in the Railroads' cost of transporting SWEPCO's coal tonnages from Wyoming to Flint Creek above or below the [1971, 1984] base cost level?
The jury answered "no” as to both contracts.
. The questions regarding unjust enrichment read as follows:
Did the Railroads receive an unjust enrichment by retaining all or a part of the difference, if any, between the rate actually charged for shipping SWEPCO’s coal tonnages from Wyoming to [Flint Creek, Welsh] and the rates that should have been charged?
The jury answered “yes” as to the rates for shipments to both power plants.
. SWEPCO asserts that the jury question was valid as an element of an action for “money had and received," which belongs conceptually to the doctrine оf unjust enrichment. See Staats v. Miller,
. We concur with the court's conclusion on similar facts in Barrett that:
There is . nothing in the evidence to suggest that appellant obtained the funds wrongfully or that in good conscience and justice he should not be allowed to keep the consideration paid him_ Appellee does not aver fraud, accident, mistake, duress or bad faith on the part of appellant. Appellee is in no position to seek restitution ... since appellant fulfilled his obligation under the agreement.
Barrett v. Ferrell,
.SWEPCO maintains that Burlington has waived this point of error by failing to preserve the complaint through objection in the trial court. Burlington repeatedly moved for an instructed verdict on the declaratory relief requested by SWEPCO. Furthermore, following the entry of judgment, Burlington was not required to raise its insufficient evidence point on this issue in a motion for new trial, because the declaratory judgment itself was not an issue tried to the jury. Tex.R.App.P. 52(d).
Lead Opinion
OPINION ON MOTION FOR REHEARING
On motion for rehеaring, SWEPCO directs the court’s attention to a letter sent by Vernon A. Williams, Secretary of the Interstate Commerce Commission, to the trial court during trial of this matter. In the letter, Secretary Williams states that the certification date stamped on the Sandgren deposition is incorrect. The letter confirms that the correct date on which SWEPCO received the certified copy of the deposition from the ICC was not September 11,1994, as the stamp indicates, but instead October 11, 1994. SWEPCO introduced this letter into evidence on November 16, 1994, and on the basis of the information contained therein, asked the trial court to reverse its earlier ruling excluding the Sandgren deposition. The court once again refused to admit the deposition, however, ruling that SWEPCO had still failed to show good cause for not producing the document earlier. SWEPCO now contends that the trial court abused its discretion in excluding the deposition after receiving uneontroverted evidence that the original certification date was incorrect, and that this error probably caused the rendition of an improper judgment.
After reviewing the record, we believe that it was within the trial court’s discretion to exclude the deposition despite the evidence of the incorrect certification date. Counsel for SWEPCO told the trial court that it discovеred the document in its files on September 30, 1994. The deposition itself, however, was taken in an unrelated proceeding before the ICC on June 21, 1979. In a request for production made April 28, 1994, Burlington asked SWEPCO to produce any sworn testimony given previously by Sand-gren which SWEPCO intended to use at trial. SWEPCO responded that it had no such statements in its possession.
On October 7, 1994, counsel for SWEPCO sent a letter to Burlington stating that it had discovered the Sandgren deposition in its files. In the letter, SWEPCO identified the date of the deposition and the docket number of the proceeding in which it was taken, but did not include a copy of the document. Burlington then made specific requests on October 12 and October 17 for a copy of the document. SWEPCO finally produced a copy of the document on October 21, after trial had begun.
Based on this evidence, the trial court could have found that SWEPCO had a duty to furnish the document to Burlington earlier than it did. The evidence indicated that the document was in the files of SWEPCO’s counsel long before it was claimed to have been discovered. The trial court could have concluded that had SWEPCO been diligent in responding to the request for production, it could have located and furnished the document earlier. Furthermore, the court could have found that it was unreasonable for SWEPCO to fail to enclose a copy of the deposition in the letter notifying Burlington of the existence of the document, and that SWEPCO’s ultimate production of the document after trial had begun was therefore unreasonably late. See Foster v. Cunningham,
Furthermore, even if we believed that the court’s exclusion of the evidence was error, we would hold that the error was not so serious as to warrant reversal. SWEPCO argues that the excluded testimony was crucial, because it demonstrated that Sandgren, a top Burlington official, once interpreted the gross inequity clause of the contracts in the same manner SWEPCO urged that they be intеrpreted at trial. The trial court allowed SWEPCO, however, to offer extensive evidence of substantially similar statements made by other high-ranking Burlington officials. SWEPCO relied heavily on this evidence in its arguments to the jury, advancing precisely the theory it now claims it was precluded from presenting at trial. Because the excluded evidence was thus substantially similar to other, admitted evidence, any error committed by the trial court probably did not cause the rendition of an improper judgment in this case. Tex.R.App.P. 81(b)(1).
The motion for rehearing is overruled.
