Opinion by
Joseph E. Burke and the North Huntingdon Township Municipal Authority (herein called Township Authority), 1 on June 3, 1954, entered into a written contract. The Township Authority, intending to enlarge its water works by constructing additional water lines, a filtration plant and a dam, selected Burke as its engineer for the project. Under the contract Burke agreed to furnish and perform certain specified professional engineering services in connection with the project for which the Township Authority agreed to pay him for such services “Six (6%) per Cent of the cost of the construction of the entire water system . . . .” The total estimated cost of such construction was $760,-000.
Almost two years later — May 28, 1956 — the Township Authority sold its water works to the Municipal Authority of Westmoreland County (herein called County Authority) under a contract to which North Huntingdon Township (herein called Township) was a signatory. Paragraph XII of this agreement recites: “The seller and the Township will pay out of the monies paid to them jointly . . . [iii] the reasonable fees and expenses of consulting engineers employed by the seller in connection with the transactions contemplated hereby and for past services but not to exceed Twenty thousand ($20,000) Dollars.”
Burke’s claim not having been paid, he instituted an assumpsit action, joining as defendants therein the Township, the Township Authority and the County Authority. Three causes of action were stated in the Complaint. The cause of action stated against the Township Authority is based upon the contract of June 3, 1954 between the Township Authority and Burke; the cause of action stated against the Township is based upon two grounds: (a) that the Township became liable to Burke by virtue of the provisions of the “Municipality Authorities Act of 1945”, providing for the assumption of an Authority’s projects by the municipality which created it and (b) under the terms of the contract of May 28,1856 between the Township Authority and the County Authority to which the Township was a signatory; the cause of action stated against the
The Township Authority having filed an answer upon the merits, the question of its liability to Burke is not presently at issue.
Both the Township and the County Authority filed separate preliminary objections each of which raised two questions of law: (a) that the Township and County Authority were improperly joined as parties defendant and (b) that Burke’s complaint failed to set forth a cause of action against either the Township or the County Authority. The court below sustained the preliminary objections and directed that plaintiff’s complaint as to the Township and the County Authority be stricken. Prom that decree this appeal was taken.
The procedure for the joinder of defendants is prescribed by Pa. It. C. P. 2229, subsections (b) and (d), which read as follows: (b) “A plaintiff may join as defendants persons against whom he asserts any right to relief jointly, severally, separately or in the alternative, in respect of or arising out of the same transaction, occurrence, or series of transactions or occurrences if any common question of law or fact affecting the liabilities of all such persons will arise in the action. ... (d) A person who asserts a cause of action ex contractu may join as defendants all or any one or more persons alleged to be liable to him on or by reason of the breach of the contractual obligation sued upon, regardless of the capacities in which such persons are respectively liable or whether they are primarily or secondarily liable or whether their liabilities arise from the same or separate acts or undertakings;
While the complaint states three different causes of action, yet all the causes of action arise out of the
The complaint as against the Township states two causes of action each of which will be discussed separately.
Section 18 of the Municipality Authorities Act of 1945, supra, as amended, 53 PS §2900z-19 provides: “(A) If a project shall have been established under this act by a board appointed by a municipality or municipalities, which project is of a character.which the municipality or municipalities have power to establish, maintain or operate, and such municipality or municipalities desire to acquire the same, it or they may by appropriate resolution or ordinance adopted by the proper Authorities, signify its or their desire to do so, and thereupon the [Authority], shall convey by appropriate instrument said project to such municipality or municipalities, upon the assumption by the latter of all the obligations incurred by the Authorities with respect to that project.” Burke contends that the Township, by signing the contract of May 28, 1956, in effect acquired the water works under this statute and therefore assumed the Authority’s obligations with respect to this project.
In
Harris v. Philadelphia et al.,
The next facet of Burke’s argument dealing with the liability of the Township applies equally to the liability of the County Authority. Burke claims that, even though he was not a party to the contract of May 28. 1956 nor the understanding contained in the “letter of intent”, yet he stands as to both in the position of a creditor beneficiary entitled to sue both the Township and the County Authority.
Assuming, arguendo, the Township to be a primary party to both the contract and the “letter of intent”, is Burke a creditor beneficiary entitled to maintain 8 suit against both Township and County Authority?
That a third party, not in privity to the original contract, may sue as a creditor beneficiary is now the rule in Pennsylvania:
Mowrer v. Poirier & McLane Corporation,
In Spires et ux. v. Hanover Fire Insurance Company, supra, pp. 56, 57, it was stated: “To be a third party beneficiary entitled to recover on a contract it is not enough that it be intended by one of the parties to the contract and the third person that the latter should be a beneficiary, but both parties to the contract must so intend and must indicate that intention in the contract; in other words, a promisor cannot be held liable to an alleged beneficiary of a contract unless the latter was within his contemplation at the time the contract was entered into and such liability was intentionally assumed by him in his undertaking; the obligation to the third party must be created, and must affirmatively appear in the contract itself . .
Burke’s right to sue the Township and the County Authority depends upon a construction of the con* tract to determine from its terms and the circumstances under which it was made what the parties intended. An examination of Paragraph XII of the contract, illuminated by the “letter of intent”, reveals the following undertakings by the parties: the seller (Township Authority) and the Township are to “pay out of the monies paid to them jointly” by the County Authority the “reasonable fees and expenses of consulting engineers employed by the seller” up to the amount of $20,-000; the buyer (County Authority) is to “pay any sums or amounts which [the Township Authority and the Township] are found to be responsible- to pay, includ
Burke is not a creditor beneficiary under this contract but simply occupies the status of an incidental beneficiary.
6
As an incidental beneficiary Burke acquired “by virtue of the promise no right against the promisor or the promisee”: Restatement of the Law, Contracts, §147;
Spires et ux. v. Hanover Fire Insurance Company,
supra;
Klingler v. Wick,
An additional reason precludes Burke’s suit against the County Authority. The County Authority’s promise to pay engineering fees and expenses was a condi
Burke has not stated a valid cause of action against either the Township or the County Authority. The action of the court below in sustaining the preliminary objections was eminently proper.
Decree affirmed. Costs to be paid by appellant.
Notes
Created under the Municipality Authorities Act of May 2, 1945, P. I». 382, 53 PS §2900z.
For a discussion of the use of “letters of intent”: 9 Williston on Contracts (Kev. Ed.), §198, pp. 290, 291.
In the present suit Burke claims $42,500.
National Container Corporation of Pennsylvania v. Regal Corrugated Bow Company,
It is highly questionable whether an improper joinder may be attacked by preliminary objections rather than by a motion for severance.
Restatement of the Law, Contracts, §133 (1) (c).
Proof of actual loss is prerequisite to recovery upon an indemnity undertaking:
Wilbur Trust Company, to use, v. Eberts et al.,
“A mere promise to indemnify against damages must also be distinguished. Here the promisor’s liability does not arise until the promisee has suffered loss or expense. Until then the promisee has no right of action, and consequently one claiming damages can assert no derivative right against the promisor, .much less a direct right . . . .” 2 Williston on Contracts (Rev. Ed.), §403, p. 1159.
