2005 Ohio 2502 | Ohio Ct. App. | 2005
{¶ 2} Miller contracted with Ameriwash, American Autowash, LLC and Chadrick Newdigate (the owners) to act as the contractor in building a car wash in Lebanon, Ohio. Bunnell acted as a subcontractor and performed the electrical work on the project. Miller paid Bunnell for some of the work it performed on the project. After completion of the project, Bunnell filed a complaint against Miller and the owners alleging that the company was not fully compensated for the work it performed. After a trial, the court found Miller liable to Bunnell in the amount of $7,688 and that Bunnell was entitled to 18 percent interest from September 2001, the date charges were invoiced.
{¶ 3} Miller now appeals the trial court's decision and raises five assignments of error for our review. For ease of discussion, we begin with Miller's fifth assignment of error.
{¶ 5} Miller, however, responded to the second order with a motion for reconsideration, asking this court to include the statement as part of the record and to find that because the statement was filed by the trial court, it was approved by the trial court. This court responded by denying the motion for reconsideration, finding that it can not be assumed that a statement was approved by the trial court simply because it was filed. The statement of evidence was stricken from the record and Miller was again given time to file a conforming statement. No further action was taken.
{¶ 6} In this assignment of error, it appears that Miller is again urging this court to find his statement of evidence was approved. We further note that his brief includes citations to the statement. To the extent that Miller argues for admission of the statement, this court has already ruled on its admission. The statement has been stricken from the record and will not be considered.
{¶ 7} To the extent that Miller argues the trial court erred in not approving the statement, we find no merit to his argument. There is no indication that Miller did anything on the record to pursue the trial court's approval of the statement. An appellant has a duty to ensure the record is filed with the appellate court. Rose Chevrolet, Inc. v. Adams
(1988),
{¶ 9} In this case, only a partial transcript was submitted. If a partial record does not conclusively support the trial court's decision, it is presumed that the omitted portion provides the necessary support.Wozniak v. Wozniak (1993),
{¶ 11} Although the "liquidated-unliquidated" and "capable of ascertainment" tests were the prevailing standards in Ohio's appellate districts for a considerable period of time, the Ohio Supreme Court specifically rejected this rule of law nearly ten years ago in RoyalElec. Constr. Corp. v. Ohio State Univ.,
{¶ 12} In his third assignment of error, Miller argues that the trial court erred in granting prejudgment interest at the rate of 18 percent per annum. The version of R.C.
{¶ 13} "[W]hen money becomes due and payable upon any bond, bill, note, or other instrument of writing, upon any book account, * * * or a contract or other transaction, the creditor is entitled to interest at the rate of ten per cent per annum, and no more, unless a written contract provides a different rate of interest in relation to the money that becomes due and payable, in which case the creditor is entitled to interest at the rate provided in that contract."
{¶ 14} Therefore, for a rate other than the statutory rate of interest to apply, two prerequisites must be met: 1) there must be a written contract between the parties; and 2) the contract must provide a rate of interest with respect to money that becomes due and payable. HobartBros. Co. v. Welding Supply Serv., Inc. (1985),
{¶ 15} The limited record in this case contains documentary evidence, including the contracts and invoices between the parties. Because the statute requires a written contract, we are able to review Miller's assignment of error despite the limited record in this case. In reAdoption of Foster (1985),
{¶ 16} Bunnell argues that an invoice sent to Miller which, under the heading "Terms" states, "1.5% Over 30," created a contract between the parties to pay 18 percent interest per year on all amounts due over 30 days. No other documentary evidence supports an interest rate different from the statutory rate. In a similar case, the Tenth District found that "[a]n oral statement or a statement on an invoice or bill to which the other party has not assented does not meet the requirement of R.C.
{¶ 17} In conclusion, we find that the trial court erred in awarding 18 percent interest instead of the statutory rate of 10 percent. The trial court's judgment entry is hereby modified to reflect that the interest rate on the award is 10%. The trial court's decision is affirmed in all other respects.
{¶ 19} Judgment affirmed in part and reversed in part.
Powell, P.J., and Walsh, J., concur.
Valen, J., retired, of the Twelfth Appellate District, sitting by assignment of the Chief Justice, pursuant to Section