Bunkoff General Contractors, Inc. v. Dunham Electric, Inc.Bunkoff General Contractors, Inc. v. Dunham Electric, Inc.
Appeal from an order of the County Court of Albany County (Lamont, J.), entered December 3, 2001, which affirmed an order of the Albany City Court denying defendant’s motion for summary judgment.
Plaintiff was the successful bidder as general contractor for a local renovation project. In preparing its bid, plaintiff incorporated a quotation for electrical work submitted by defendant. According to plaintiff, before submitting its bid to the owner, its representatives contacted defendant’s president to confirm the quotation and informed him that if it was awarded the project, the electrical work would be awarded to defendant.
Defendant thereafter made two written proposals containing various cost reductions, which plaintiff passed on to the owner. According to plaintiff, before finalizing its own status as the successful bidder for the general contract, its president informed defendant’s president that the electrical quotation as amended was being used to bid the project and again reiterated that, if awarded, defendant would be given the electrical subcontract (but see n 1). After plaintiff was formally awarded the contract, but before any written subcontract was executed between them, defendant refused to perform the electrical work on the project.
As an initial matter, we reject defendant’s prefatory argument that the doctrine of promissory estoppel is not a legally cognizable cause of action in disputes of this type (i.e., construction contract bids) (see Nory Constr. Co. v Genesee LeRoy Stone Corp.,
We next reject defendant’s alternative contention that it is entitled to summary judgment. As aptly stated in Gellerman v Oleet (
Crew III, J.P., Mugglin, Rose and Kane, JJ., concur. Ordered that the order is affirmed, with costs.
Notes
. To be sure, defendant’s president disputes this point, claiming that no representative of plaintiff ever informed him that if plaintiff “got the job,” defendant “got the job.”
. Indeed, it appears that defendant refused to do the work before it received the written subcontract from plaintiff. Thus, defendant’s claim that
. The issue of whether the doctrine of promissory estoppel should be applied in construction bidding cases has been widely and continuously debated for nearly seven decades (see e.g. Schneider, Maryland’s Application of Promissory Estoppel in Construction Industry Bidding Disputes: Eliminating Further Confusion, 30 U Balt L Rev 171 [2000]; Siegfried & Lawrence, Home Electric v Hall & Underdown Heating & Air Conditioning: Mutuality Remains the Only Solution to the Construction Bidding Problem, 9 Construction Law 3 [1989]; Murphy, Promissory Estoppel: Subcontractors’ Liability in Construction Bidding Cases, 63 N C L Rev 387 [1985]; Bishop, The Subcontractor’s Bid: An Option Contract Arising through Promissory Estoppel, 34 Emory LJ 421 [1985]; Glosen & Weiland, The Construction Industry Bidding Cases: Application of Traditional Contract, Promissory Estoppel, and Other Theories to the Relations Between General Contractors and Subcontractors, 13 J Marshall L Rev 565, 583 [1980]; Schriber, Construction Contracts-The Problem of Offer and Acceptance in the General Contractor-Subcontractor Relationship, 37 U Ginn L Rev 798 [1980]; Schultz, The Firm Offer Puzzle: A Study of Business Practice in the Construction Industry, 19 U Chi L Rev 237, 239 [1952]; Note, Contracts-Promissory Estoppel, 20 V.A.L. Rev 214 [1933]).