Bulova Watch Co. v. Celotex Corp.Bulova Watch Co. v. Celotex Corp.
OPINION OF THE COURT
At issue on this appeal is the timeliness of a suit brought to recover damages for a roofing materials supplier’s failure to live up to its express promise to repair its so-called "bonded” roof for a period of 20 years from the date of sale. We hold that a cause of action accrues upon each breach of that undertaking which occurs within the 20-year period and that the Statute of Limitations runs after six years from the date when the particular breach for which any such suit is brought has taken place.
In 1952, plaintiff Bulova Watch Company contracted for the installation of a roof on its factory in Jackson Heights, Queens. As per its obligations under a construction agreement, the contractor purchased roofing materials from defendant Barrett Division, Allied Chemical & Dye Corporation, which issued two "20-Year Guaranty Bond[s]” to Bulova, one for its "Barrett Specification Pitch and Felt”, limited to the recovery of sums up to $8,000 and the other for its "Barrett flashing materials”, with a ceiling of $700. The bonds, which recited that they were effective as of February 20, 1953 and
In effect, Bulova has alleged that the guaranteed roof turned out to be no more waterproof than a sieve. The first evidence of leakage purportedly came to light at least as early as September 6, 1955, and, despite repeated demands that the bonds’ terms be fulfilled, Barrett’s intermittent and allegedly inadequate attempts at repair did not prevent the defects from persisting throughout the balance of the 20 years. Even as the guarantee period was about to expire, Celotex, on February 14, 1973, found it necessary to respond to the recurring complaints by sending Bulova a letter acknowledging its responsibility to repair leaks present in the roof during the fall and winter of 1972-1973.
Not much later, on July 10, 1973, Bulova brought this action to recover $65,000 in damages, the amount it would cost to replace the roof, on two theories, one for breach of an implied warranty of fitness for use and the other for breach of the express terms and conditions of the guarantee bonds. Perhaps because the two theories, though discernible, were intermingled in the pleadings, Special Term, on defendants’ motion for summary judgment, treated the suit as though it were premised on implied warranty alone. It then proceeded to dismiss on the ground that it was barred by the Statute of Limitations. The Appellate Division affirmed, without opinion (
Thus, insofar as suit was posited on a warranted theory, whether the transaction here is looked at as a sale of goods or a services contract or a combination of both, in 1953 it was governed by the six-year contract Statute of Limitations.* 2 So measured, it was correctly held to be time-barred.
Nevertheless, plaintiffs rights under the bonds enable its suit to weather the storm of defendants’ attacks. The bonds embody an agreement distinct from the contract to supply roofing materials. The former expressly promise to furnish whatever labor and materials are required for future repairs; the latter deals only with those provided at the time of the installation. The period during which performance may be required under the bonds is expressly stipulated to be 20 years; the only time specified for the performance of the sales contract was that of the original installation. The form of the bonds was one highlighting the obligation of Continental as
On the limitations question, it is clear that the separate bond obligations, as agreements contemplating services, were subject to a six-year statute (CPLR 213, subd 2; 1 Weinstein-Korn-Miller, NY Civ Prac, par 213.13) running separately for the damages occasioned each time a breach of the obligation to repair the bonded roof occurred (see
Putnam’s Sons v Owens,
Finally, some comments are in order on the attempt by each of the parties to bring the rights flowing from the guarantee bonds under the umbrella of the "prospective warranty” doctrine. True, when a warranty expressly guarantees the future performance (as opposed to present condition) of goods, some courts have held that a cause of action for breach of warranty accrues when the breach is or should have been discovered (e.g.,
Mittasch v Seal Lock Burial Vault,
But, there is no need at this juncture for us to endeavor to lift the fog that envelops the perhaps questionable distinctions made in these prospective warranty cases. Their analysis
Accordingly, the order of the Appellate Division, insofar as appealed from, should be reversed, with costs, and plaintiffs second and fourth causes of action reinstated.
Chief Judge Cooke and Judges Jasen, Gabrielli, Jones and Wachtler concur with Judge Fuchsberg.
Order, insofar as appealed from, reversed, etc.
Notes
. The causes of action based on the warranty and bond theories were designated the second and fourth causes of action. Special Term also dismissed and severed two other causes of action sounding in negligence, to the extent that they pleaded damages which antedated the three-year tort Statute of Limitations period preceding
. As a result of the adoption of the Uniform Commercial Code in 1964, the statute is now four years in sales of goods cases (Uniform Commercial Code, § 2-275, subd [1]).
. Although it might be argued that the bonds’ prospective promises give rise to an implied future performance warranty, we note, without reaching the question, that no case appears to have applied the doctrine to implied warranties (Schmitt & Hanko, 28 Ark L Rev 311, 328; but see
Mittasch v Seal Lock Burial Vault,