Building & Construction Trades Department v. AllbaughBuilding & Construction Trades Department v. Allbaugh
MEMORANDUM OPINION
Plaintiffs Building and Construction Trades Department of the AFL-CIO (“BCTD”), Contra Costa Building and Construction Trades Council (“Contra Cos-ta BCTC”), and the City of Richmond (“Richmond”) commenced this lawsuit to enjoin the enforcement of Executive Order 13202 (“EO 13202”), issued by President George W. Bush on February 17, 2001. EO 13202 prohibits federal agencies or recipients of federal funding from requiring or prohibiting Project Labor Management Agreements (“PLAs”) in the bid specifications or other authorizing documents for construction contracts. Plaintiffs argue that EO 13202 is without authority and is preempted by the National Labor Relations Act (“NLRA”). Plaintiffs
Pending before the Court are cross-motions for summary judgment. Upon consideration of the parties’ motions, oppositions, replies, and counsels’ representations at oral argument, the motions by amicus curiae, as well as the applicable statutory and case law, the Court concludes that the plaintiffs’ motion for summary judgment and for permanent in-junctive relief must be GRANTED and the defendants’ motion for summary judgment must be DENIED. Constitutional and statutory precedent of longstanding persuades the Court that the President lacked the requisite authority for Executive Order 13202. Accordingly, enforcement of EO 13202 is permanently enjoined.
BACKGROUND
1. Project Labor Management Agreements
Executive Order 13202 prohibits federal agencies and recipients of federal funding from requiring or prohibiting PLAs in the implementing documents for construction projects. Exec. Order No. 13,202, 66 Fed. Reg. 11225 (February 22, 2001),
amended by
Exec. Order No. 13,208, 66 Fed.Reg. 18717 (April 6, 2001). PLAs are “pre-hire” collective bargaining agreements that are generally prohibited by the NLRA. Contractors or owners and labor unions in the construction industry, however, are explicitly exempted from that prohibition.
See
PLAs are generally negotiated at the beginning of a construction project. Once an agreement has been reached, the employer will award contracts only to those contractors and subcontractors who agree to abide by the PLA. The process by which the PLA is negotiated and the contracts are awarded differs slightly depending on whether an employer is a private or public entity.
Private employers may negotiate directly with labor unions to create a PLA that will bind all contractors and subcontractors on a project to its terms. The employer can then either simply hire contractors who agree to abide by those terms, or grant the contracts through a competitive bidding process. If there is a bidding process, the employer will include the PLA in the bid specifications as a material requirement.
For public entities, the process is slightly more complicated. The process includes assessing the value of a PLA for a particular project, selecting a construction or project manager to negotiate and implement the agreement, negotiating the agreement, reviewing the agreement, and enforcing the agreement. Most public entities by law must use a competitive bid process to award contracts.
See
Mem. of Law of Amicus Curiae New York State
In the absence of a PLA, individual unions and individual contractors can negotiate pre-hire agreements that set the terms and conditions for the workers and subcontractors who work for that particular contractor. However, these individual pre-hire agreements are not PLAs in that they can not establish uniform standards for an entire project.
2. EO 13202
Section 1 of EO 13202 applies to federal agencies who award construction contracts, and specifies the substantive prohibitions of the EO. Section 3 of EO 13202 applies to recipients of federal funding and incorporates the prohibitions of § 1:
Section 1. To the extent permitted by law, any executive agency awarding any construction contract after the date of this order, or obligating funds pursuant to such a contract, shall ensure that neither the awarding Government authority nor any construction manager acting on behalf of the Government shall, in its bid specifications, project agreements, or other controlling documents:
(a) Require or prohibit bidders, offer-ors, contractors, or subcontractors to enter into or adhere to agreements with one or more labor organizations, on the same or other related construction projects); or
(b) Otherwise discriminate against bidders, offerors, contractors, or subcontractors for becoming or refusing to become or remain signatories or otherwise to adhere to agreements with one or more labor organizations, on the same or other related construction project(s).
(c)Nothing in this section shall prohibit contractors or subcontractors from voluntarily entering into agreements described in subsection (a).
Sec. 3. To the extent permitted by law, any executive agency issuing grants, providing financial assistance, or entering into cooperative agreements for construction projects, shall ensure that neither the bid specifications, project agreements, nor other controlling documents for construction contracts awarded after the date of this order by recipients of grants or financial assistance or by parties to cooperative agreements, nor those of any construction manager acting on their behalf, shall contain any of the requirements or prohibitions set forth in section 1(a) or (b) of this order.
Executive Order 13202, 66 Fed.Reg. 11225 (February 22, 2001). EO 13202 states that its authority lies in “the Constitution and laws of the United States of America, including the Federal Property and Administrative Services Act, 40 U.S.C. 471 et seq.” Id.
EO 13202 superceded President Clinton’s June 1997 memorandum, which directed that executive agencies “may, on a project-by-project basis, use a project labor agreement on a large and significant project” when that agency determines it will “advance the Government’s procurement-interest in cost, efficiency and quality and in promoting labor-management stability ...” President’s Memorandum, “The Use of Project Labor Agreements for Federal Construction Projects” at 1,
3. Plaintiffs
Plaintiff BCTD is a an organization within the AFL-CIO consisting of fourteen national and international unions representing more than one million employees in construction and related industries throughout the United States and Canada. See Pis.’ Motion for Summ. J., Ex. 4 (Second Decl. of Edward C. Sullivan). BCTD is the parent organization to over 300 local building and construction councils in the United States, including the Contra Costa BCTC, also a plaintiff here. Id. The Department and its affiliated councils are parties to PLAs across the United States on projects conducted by both private and public entities. Id. at ¶ 6 Prior to the issuance of EO 13202, many of these PLAs were on federal agency projects and projects receiving federal financial assistance. Id.; see also Pis.’ Motion for Summ. J., Ex. 5 at ¶ 4 (Decl. of Wiliam “Giz” Kaczo-rowski).
BTCD entered into a PLA with the construction manager for Maryland’s State Highway Administration, for the purpose of participating in Maryland’s construction of the Woodrow Wilson Bridge Project. The project was slated to receive over $1.5 billion in Department of Transportation funds. BTCD’s PLA was submitted to the Federal Highway Administration (“FHWA”) in order to be included in the State’s bid solicitation for the project, but was denied by FHWA because FHWA believed the PLA was prohibited by EO 13202.
Richmond was planning on negotiating PLAs in two of its upcoming urban renewal construction projects with plaintiff Contra Costa BCTC, the Richmond Transit Village (“RTV”) and the Ford Assembly Plant (“Ford”). Both projects secured funds from FEMA and HUD of $4.5 million and $20 million respectively, and the RTV project also received approximately $1.7 million of DOT funds. The City Council passed a resolution deciding not to authorize a PLA, citing their belief that EO 13202 would bar federal funding needed to complete the projects. FEMA and HUD since informed Richmond that EO 13202 did not apply to funding pledged by their agencies, as'it was already awarded before EO 13202 was executed. The DOT funds for the RTV project are subject to EO 13202. Richmond has not indicated whether it would change its decision on including PLAs as a result, or whether it would be unable to do so for want of the DOT funds.
Richmond also claims it has numerous proposals for construction contracts pending anticipated federal funding, some of which Richmond would normally negotiate a PLA for. In addition, the plaintiffs also cite three other examples of projects that both anticipate receipt of federal funding, and expressed an intention to utilize a PLA before EO 13202 issued. These projects include the St. Louis Airport project, the Washington State Capitol, and the Walnut Creek-San Ramon Valley Improvement Project.
The plaintiffs, BCTD, Contra Costa BCTC, and Richmond, filed a motion for preliminary injunction and summary judgment against the defendant federal agencies, claiming that EO 13202 was unauthorized and preempted by the NLRA. Defendants filed a motion to dismiss or, in the alternative, for summary judgment, claiming that plaintiffs lacked standing to sue and that EO 13202 was valid.
Amicus Briefs were filed on behalf of the plaintiffs by: the State of Maryland, the New York State Thruway Authority, the State of New York, the Commonwealth of Massachusetts, and the National Economic Development & Law Center and the Sierra Club. On behalf of the defendants, ami-cus briefs were submitted by the Associated Builders and Contractors, Inc., 2 and the National Right to Work Legal Defense Foundation, Inc.
On August 13, 2001, this Court granted plaintiffs’ motion for preliminary injunction with respect to enforcement of EO 13202 and the Woodrow Wilson Bridge Project bid specifications that were to be advertised on August 14, 2001. The Court found that plaintiffs would suffer irreparable harm if ■ the bid specifications were advertised without the PLA requirement, and that the plaintiffs were likely to prevail on the merits of their NLRA preemption claim.
In response to this Court’s order, on August 20, 2001, the State of Maryland submitted a revised PLA to the Federal Highway Administration for its review, stating that it intended to include the PLA in the bid specifications for the superstructure contract by addendum upon approval by FHWA. See Defs.’ Mem. of P. & A. in Opp’n to Pis’ Mot. for Summ. J. and Mem. of P. & A. in Reply to Pis’ Opp’n to Defs.’ Mot. to Dismiss, or in the Alternative for Summ. J. (hereinafter “Defs.’ Opp’n and Reply”), Ex. 2 (August 20, 2001, letter from Parker Williams, Administrator of the Maryland State Highway Administration to FHWA). The FHWA has approval authority over the bid specifications on this project. On September 25, 2001, Administrator of the Maryland State Highway Administration wrote to the FHWA indicating that Maryland had not yet received a response to the revised bid specifications and also to a final financial plan submitted on September 4, 2001. See Pis.’ Reply to Defs.’ Opp’n to Mot. for Show Cause Order, Ex. 1. Maryland’s letter reiterated its concern that it receive a reply by September 28, 2001, or the October 18, 2001, bid opening date for the superstructure contract would be delayed. Id.
On September 28, 2001, the FHWA replied to the State of Maryland’s letter of September 25, 2001 in two separate letters. See Pis’ Unopposed Mot. for Leave to Supplement Reply to Defs.’ Opp’n to Mot. for Show Cause Order. The first September 28, 2001 letter approved the Financial Plan, thereby removing that impediment from proceeding on the superstructure contract. The second September 28, 2001 letter referred specifically to the bid specifications that were revised to include the PLA after this Court entered the preliminary injunction on August 13, 2001. In that letter, the FHWA stated:
With regard to the PLA, the FHWA has on several occasions advised the State that the recent judicial decision preliminarily enjoining President Bush’s Executive Order has required us to develop standards and procedures for reviewing the Woodrow Wilson Bridge PLA that Maryland submitted on August 20, 2001. That process is not yet complete and until it is, we are not able to properly review and approve or disapprove the PLA.
The FHWA offered no timeframe for when those standards and procedures may be in place. The FHWA further stated that it had already approved one set of bid specifications. The FHWA suggested “[w]e see no reason why Maryland cannot go forward with its scheduled October 18, 2001, bid opening date with the current bid specifications, thus avoiding any delay in the project completion date.” The approved bid specifications to which the FHWA referred are the subject of this Court’s preliminary injunction.
On October 3, 2001, the State of Maryland informed the Court that it has extended the bid opening for the superstructure contract until November 29, 2001.
DISCUSSION
Plaintiffs contend that the Executive Order is invalid, as the President lacked constitutional or statutory authority to promulgate EO 13202, and is preempted by the NLRA. Plaintiffs argue that EO 13202 conflicts with the NLRA because: (1) EO 13202 prohibits the use of PLAs by public agencies and the recipients of federal funding; (2) the NLRA authorizes the use of PLAs, or at least intended for the use of PLAs to be unregulated; and, (3) the D.C. Circuit requires that an Executive Order in conflict with the NLRA is invalid under NLRA preemption doctrine and must be enjoined. Defendants argue that plaintiffs lack standing to challenge EO 13202, the President had both constitutional and statutory authority to promulgate EO 13202, and the EO 13202 does not conflict with the NLRA.
All plaintiffs have standing in this case. The Court rejects the government’s extremely narrow understanding of the injury and causation requirements of standing doctrine. Moreover, the Court holds that the President lacked constitutional or statutory authority to promulgate at least Section Three of the EO 13202, which places conditions on the receipt of federal funds. Furthermore, the Court holds that EO 13202 violates both the Garmon and Machinists NLRA preemption doctrines. 3 EO 13202 violates Garmon preemption with respect to federally-funding projects conducted by private entities because the use of PLAs by private entities is expressly protected by the NLRA. EO 13202 violates Machinists preemption doctrine with respect to projects conducted by public entities, including both the recipients of federal funding and federal agencies themselves, because EO 13202 alters the balance of economic bargaining power between labor organizations and federally-funded project owners by eliminating the option of requiring a PLA in project bid specifications. Thus, both §§ 1 and 3 of EO 13202 are unlawful.
I. Standing
The three plaintiffs, BCTD, Contra Cos-ta BCTC, and the City of Richmond, have met the constitutional standing requirements. In order to satisfy Article Ill’s standing requirements, a plaintiff must meet three tests: injury, causation, and redressability.
Friends of the Earth, Inc.
A. BTCD
1. Individual standing with respect to § S.
BCTD has suffered a concrete and particularized injury, caused by EO 13202, that can be redressed by enjoining the enforcement of EO 13202. The government has advocated an extremely narrow conception of standing that goes far beyond Supreme Court precedent and the policy of judicial restraint that the standing doctrine reflects.
The government has repeatedly argued that Maryland, as the recipient of federal funding, is a more appropriate party than BCTD and is not present as a party in this case.
See
Defs.’ Opp’n and Reply at 34. However, in responding to a similar argument that the “wrong parties” were before the Court, the Supreme Court has held that it is “self-evident” that “more than one party may have standing to challenge a particular action or inaction. Once it is determined that a particular plaintiff is harmed by the defendant, and that harm will likely be redressed by a favorable decision, that plaintiff has standingregardless of whether there are others who would also have standing to sue.”
Clinton v. City of New York,
a. Injury in Fact
BCTD argues that the injury it has suffered as the result of the enactment of EO 13202 was the loss of the PLA it negotiated with the State of Maryland for the Woodrow Wilson Bridge Project and the ability to negotiate similar agreements with other project owners. That agreement named BCTD as the exclusive bargaining agent for the employees on the project, and determined the terms and conditions of employment for all workers on the project. The loss of that agreement is a particularized and concrete harm to BCTD, a labor organization that stood to play an important role in the project as the exclusive bargaining agent.
Cf. Adarand Constructors, Inc. v. Pena,
One of the goals of the Department and its affiliated Councils is to exercise our rights under the National Labor Relations Act to negotiate PLAs to govern labor relations on construction projects, and to do so on as many projects as we are able under market conditions ... Prior to the issuance of Executive Order 13202 the Department regularly sought to negotiate, and did negotiate, PLAs on projects receiving federal funding.
Pis.’ Mot. for Summ. J., Ex.4 at ¶ 7. The uncontroverted fact that plaintiffs regularly negotiated and entered PLAs with both public and private recipients of federal funding, and are no longer able to do so because of EO 13202, is sufficient injury to support standing to challenge § 1 and § 3 of EO 13202 with respect to both public and private recipients of funding. Pis.’ Motion for Summ. J., Ex.4 at ¶ 6.
Defendants argue to the contrary that BCTD has not suffered an adequate injury in fact because the PLA it negotiated with the State of Maryland is outside the protection of the NRLA, and as a result plaintiffs have no legally protected interest under the NLRA on which to base standing. The government’s extremely narrow conception of standing’s injury requirement is not supported by the Supreme Court’s interpretation of Article III of the Constitution. Citing
Lujan,
defendants argue that standing should be limited to an injury to a “legally protected interest.” Defs.’ Opp’n and Reply at 7. However, defendants then narrow the range of possible legally protected interests on which standing can be based, arguing that when a plaintiff challenges an executive order as preempted by federal statute, the plaintiffs injured interest must be a right created by that statute. Thus, defendants argue that because the PLA negotiated by BCTD does not fall within § 8(e) of the NLRA, BCTD has no legally protected interest on which to base standing to challenge the EO as preempted by the NLRA.
Id.
at 9, 20. This argument misconstrues the language of
Lujan
on which defendants rely and conflates the issue of whether a plaintiff has a private right to sue under a particular statute with the constitutional standing requirement. In order to challenge a government action as violating a particular statute, a plaintiffs injury need not be specifically protected by that statute. For example, in
Bennett v. Spear,
the Supreme Court upheld the standing of ranchers who stood to lose water usage because of a biological decision issued by the Fish and Wildlife Service and who challenged the substance of that biological decision under the citizen suit provision of the Endangered Species Act (“ESA”).
Whether or not the PLA negotiated by BCTD falls within § 8(e) of the NLRA is an important question relevant to the merits of this case. Standing, however, does not turn on the applicability of the NLRA to this particular agreement. Even if the Woodrow Wilson Bridge Project PLA is not covered by § 8(e), BCTD had an agreement for that PLA that was rendered unenforceable by an allegedly unlawful government action. Because BCTD lost the benefits it stood to gain under that agreement, its designation as the exclusive bargaining agent for the employees on the project and the agreed upon terms and conditions for employment, as well as the opportunity to negotiate similar agreements with other owners, BCTD has suffered an actual injury sufficient for Article III purposes.
b. Causation
Of course, not every government action that somehow interferes with an existing contract or agreement gives the affected parties standing to challenge that government action. In addition to the requirement of injury, a party must show both causation and redressability.
Laidlaw,
The parties disagree as to the nature of the coercive effect of EO 13202 on the recipients of federal funding who negotiate with labor organizations like BCTD. Defendants contend that there can be no causation between EO 13202 and any harm to BCTD because the decision whether or not to require a PLA or accept federal funding was a voluntary action by an independent third party, the State of Maryland. The fact that a third party made the decision that directly impacted the plaintiff does not foreclose a determination of causation. As the Supreme Court in
Bennett v. Spear
recognized, this argument “wrongly equates injury ‘fairly traceable’ to the defendant with injury as to which the defendant’s actions are the very last
Defendants ask the Court to hold that the action of a recipient of federal funds is necessarily voluntary when the only threatened sanction is the loss of funds. Defendants concede that as a result of EO 13202, a “grantee may well decide that it would rather retain the federal grant funds and, therefore give up the option of mandating the use of a PLA on a federally financed construction project.” Defs.’ Opp’n and Reply at 30-31. Thus, defendants argue that even when EO 13202 is the actual and only cause of a recipient’s decision to accept federal funding and forgo a PLA, if there are no sanctions for the recipient beyond losing the funds, the recipient’s decision has not been coerced or determined.
To borrow the words of the D.C. Circuit, “we need not attempt any broad explanation of the justiciability of indirect injury, for one narrow proposition is clear.”
Telephone and Data Systems Inc. v. FCC,
BCTD has presented sufficient uncon-troverted evidence here to prove that the State of Maryland’s decision to forgo the PLA on the Woodrow Wilson Bridge Project was caused by the promulgation of EO 13202. The plaintiffs negotiated an extensive PLA for the Project.
See
Pis.’ Motion for Summ. J., Ex. A. On January 2, 2001, shortly before the agreement was publically announced, the State of Maryland informally submitted the PLA to FHWA for review.
See
Pis.’ Motion for Summ. J., Ex. 4 at § 19. On January 8, 2001, the State of Maryland informed potential bidders that a PLA had been negotiated and recommended to be included in the project contracts.
Id.
at § 20; Pis.’ Motion for Summ. J., Ex. B. On January 9, 2001, the
Furthermore, after the Court preliminarily enjoined the application of EO 13202 to the Woodrow Wilson Bridge Project bid specifications to be announced on August 14, 2001, Maryland revised those bid specifications to include the PLA. As explained above, Maryland’s request to FHWA for approval of the revised bid specifications was submitted on August 20, 2001 and is still pending. This evidence clearly indicates the but for EO 13202, Maryland would have included the negotiated PLA in its bid specifications for all contracts on the Woodrow Wilson Bridge Project.
Rather than focus on whether EO 13202 was the actual and only cause of Maryland’s decision to remove the PLA from the bid specifications, defendants focus on the level of coercion generally caused by an offer of conditional funding. Defendants argue that BCTD lacks standing because the decision by Maryland whether or not to comply with the requirements of EO 13202 in exchange for the federal funding, is necessarily a voluntary and independent action of a third party because there is no sanction beyond the threatened loss of funding. However, defendants have not offered sufficient justification, grounded in precedent, conceptions of federalism, or a coherent theory of standing doctrine, on which to base this bright-line distinction.
The implications of defendants’ standing argument are great; defendants’ interpretation of standing would allow only the recipient of federal funding to ever challenge restrictions placed on the receipt of funds by Congress through legislation or the President though an Executive Order. 4 Without a coherent theoretical justification, this Court declines to hold as a matter of law that in every conditional funding case the only entity with standing to sue is the recipient of the funds.
In support of its argument that decisions to accept funding are never determined or coerced, defendants cite Supreme Court precedent upholding conditional spending grants as legitimate exercises of Congress’ Spending Clause authority.
South Dakota v. Dole,
Furthermore, a crucial step in the logic of defendants’ argument is that a “voluntary” decision is necessarily not a coerced or determined decision for standing purposes. Defendants cite cases for the proposition that compliance with an Executive Order by the recipients of federal funding is voluntary because the Executive Order does not have the force of law.
See AFL-CIO v. Kahn,
Defendants also attempt to distinguish
Bennett v. Spear,
where the Court upheld the standing of individuals impacted by a third party decision, by identifying reasons why the third party’s decision in
Bennett
was less voluntary than the funding recipients’ decisions here. Defendants correctly point out that the level of coercion in
Bennett v. Spear
between the Fish and Wildlife Service’s biological opinion under the ESA and the Bureau of Reclamation was greater than what occurred between the federal government and the State of Maryland with respect to the funding for the Woodrow Wilson Bridge Project. In
Bennett,
the Bureau was free to reject the FWS’s opinion only if it presented justifiable reasons for doing so, despite its own lack of expertise in the area, and if it was wrong, the FWS’s employees could be subject to criminal sanctions under the ESA. For these reasons, the Court held that the Bureau’s decision to follow the FWS’s opinion was sufficiently coerced to allow a challenge to the FWS by those ranchers impacted by the Bureau. Importantly, nowhere in
Bennett
did the Supreme Court indicate that
Bennett
established a floor or minimal standard for coercive effect. In fact, the
Bennett
Court thought it was presented with an easy case.
See Bennett,
In addition, the government relies on the standing holding in
Center for Reproductive Law & Policy v. Bush
(“CRLP”), No. 01-CIY-4986(LAP),
Furthermore, defendants’ position is undermined by Supreme Court precedent. Other Supreme Court cases that uphold standing for plaintiffs impacted when the government alters financial incentives for third parties, indicate that fairly traceable standard requires a level of coercion much lower than the circumstances at issue in
Bennett.
In
Adarand Constructors, Inc. v. Pena,
a white subcontractor who had submitted the low bid on a federally-funded project but was denied the contract challenged the constitutionality of a federal policy of giving financial incentives to general contractors who hire minority subcontractors.
Similarly, in
Clinton v. City of New York,
the Court held that an association of potato farmers formed for the purpose of
acquiring
potato processing facilities had standing to challenge the line item veto by the President of a statutory provision that gave tax relief to the
sellers
of such facilities.
For all these reasons, the Court rejects the government’s argument that funding recipients’ decisions to accept funds are necessarily voluntary and holds that BCTD has met the causation requirement.
c. Redressability
If this Court grants the requested permanent injunctive relief and invalidates EO 13202, Maryland has indicated that it will require a PLA for the Woodrow Wilson Bridge project. 6 After the preliminary injunction hearing on August 13, 2001, Maryland submitted a revised PLA to the FHWA for approval, indicating that it intends to include the PLA in the bid specifications by addendum. See Defs.’ Opp’n and Reply, Ex. 2. Maryland has since communicated with the FHWA its request that the FHWA approve the revised bid specifications that include the PLA as soon as possible. See Pis.’ Reply to Defs.’ Opp’n to Motion for Show Cause Order, Ex. 1. Maryland clearly intends to include the PLA in the bid specifications should this Court grant permanent injunction invalidating EO 13202. Accordingly, plaintiffs have met their burden of establishing that the proposed injunctive relief will redress the injury caused by EO 13202.
2. Individual standing toith respect to § 1.
BCTD also has standing to challenge § 1 of EO 13202 because it has been injured by EO 13202’s prohibition on federal agencies requiring PLAs on construction contracts for federally-owned projects. That injury is the loss of the ability to negotiate and enter into project-wide agreements that benefit labor interests. EO 13202 has taken from plaintiffs the valuable economic weapon of negotiating PLAs with project owners, the opportunity to represent all workers on a project in
BCTD’s injury with respect to federal agencies is real and actual, and not just speculative. Plaintiffs have produced un-controverted evidence that prior to the effective date of EO 13202, BCTD regularly entered into PLAs with public and private project owners, including both federal agencies and those who receive federal funding. See Pis.’ Motion for Summ. J., Ex. 5 at ¶ 4. As the Kaezorowski Declaration explained:
Each year, the Department and its Councils enter into numerous PLAs. Many of these PLAs involve projects financed at least in part with federal funding, including agreements with federal agencies or federal contractors. The Department and its Councils will continue to enter into numerous PLAs, and but for Executive Order 13202, would continue to do so on projects funded by the Federal Government.
Id.
Furthermore, the causal chain with respect to § 1 is clear: EO 13202 prohibits federal agencies from including PLAs in the bid specifications or other contract documents for federally owned projects. EO 13202 does not present federal agencies with a choice; rather it directly prohibits federal agencies from including PLAs in their bid specifications.
Finally, given the size and nature of BCTD, and the regularity with which BCTD entered into PLAs with federal agencies prior to EO 13202, an injunction invalidating § 1 will result in BCTD’s negotiations of further PLAs on federally-owned projects. There is nothing in the record to suggest that some other intervening factor will prevent federal agencies from entering any PLAs in the future on construction projects- and when they do, BCTD is the most likely candidate to participate in those negotiations. In addition, the invalidation of EO 13202 will return to BCTD the valuable tool it has lost the ability to negotiate a PLA with federal project owners and their construction managers.
For all these reasons, BCTD has standing to challenge § 1 of EO 13202.
3. Associational standing
BCTD also has associational standing on behalf of its members. In addition to having standing in its own right, an organization or association may have standing to bring suit on behalf of its members when: 1) the members would otherwise have standing to sue in their own right; 2) the interests at stake are germane to the organization’s purpose; and 3) neither the claim nor the requested relief requires the participation of the individual members.
Laidlaw,
The above discussion of injury, causation, and redressability also applies to the standing of BCTD’s members. Thus, the first prong of the associational standing test is satisfied because BCTD’s member unions also have standing in their own right.
The interests at stake in this litigation— the ability of federal agencies and the recipients of federal funding to require PLAs for their projects- — are germane to the purpose of BCTD. BCTD is an organization comprised of fourteen national and international unions representing more than one million employees in construction
Finally, the equitable relief sought, the invalidation of EO 13202 does not require the participation of those local councils.
B. City of Richmond
Richmond originally identified two federally-funded projects, the Ford and RTV projects, for which it intended to use PLAs prior to the issuance of EO 13202. See Pis.’ Mem. in Support of Pis.’ Mot. for Summ. J. or, in the Alternative, Application for Prelim. Inj. (hereinafter “Plfs.’ Opening Br.”) at 19. The Richmond City Council passed a resolution deciding not to authorize a PLA for either project, citing its belief that EO 13202 applied to the federal funding needed to complete the projects.
1. The Ford Project.
At the time this case was filed, Richmond was of the opinion that the federal funds to be received for the Ford project from both the Federal Emergency Management Administration (“FEMA”) and the Department of Housing and Urban Development (“HUD”) were subject to EO 13202. In the course of this litigation, however, the defendants informed Richmond that it may use a PLA on the Ford project without jeopardizing any federal funds because the funds were obligated to Richmond prior to the issuance of EO 13202. Section 2 of EO 13202 specifically exempts contracts awarded prior to the date of EO 13202. Because EO 13202 does not apply to the funds for the Ford Project, Richmond can not have standing to challenge EO 13202 based on that project.
2. The RTV Project.
The parties dispute whether the RTV project can serve as a basis for Richmond’s standing in this lawsuit. Richmond will receive federal funding from three sources for the RTV project: FEMA, HUD, and the Department of Transportation (“DOT”). As with the Ford project, neither the FEMA nor the HUD funds are subject to EO 13202 because they were granted prior to February 17, 2001. The DOT funds, however, are subject to EO 13202, and it is on those funds that Richmond bases its standing argument. DOT has committed $1.7 million, which, according to the government, is approximately three percent of the project’s anticipated total cost of $55 million.
Defendants challenge Richmond’s standing by claiming that Richmond has not been injured by the EO 13202 for two reasons: first, the City has not yet decided whether or not to use a PLA on the project now that only three percent of the federal funds are subject to EO 13202; and second, the City can easily segregate the DOT funds and use a PLA for the rest of the project at no cost to the City or harm to the project.
The City Counsel resolution makes clear that Richmond originally decided not to use a PLA on the RTV project because of EO 13202. See Plfs’ Opening Br., Ex. C. The loss of a PLA that would benefit Richmond is sufficient injury for standing purposes.
However, even if defendants’ claim that Richmond has not made a final decision as to whether or not it will use a PLA on the RTV project is true, Richmond still has standing to challenge the federal pro
Second, defendants argue that Richmond has suffered no injury because it is possible to segregate the funds that are subject to EO 13202 from the 97 percent of the project funds that are not. This argument fails for several reasons. First, the plain language of EO 13202 contradicts the defendants’ assertion that Richmond should be able to negotiate a PLA for 97 percent of the project as long as the three percent of federal funds subject to EO 13202 are segregated. Defendants cite no language from EO 13202 to support its assertion; in fact, the only authority they cite is a statement from the City Manager that the City may consider this option. Defs.’ Opp’n and Reply at 24. The language of EO 13202 is clear: any recipient of federal funding for a project will lose that funding if a PLA is negotiated for the project. Section 3 states: “ neither the bid specifications, project agreements, nor other controlling documents for construction contracts ... by recipients of grants or financial assistance ... shall contain any of the requirements or prohibitions set forth in section 1(a) or (b)... ” Nowhere does this language indicate that a recipient may segregate funds within a project. In fact, the language of EO 13202 does not even limit the prohibition on required PLAs to the project for which the funds have been granted it prohibits “construction contracts” by a recipient of federal funding from requiring PLAs. Because the plain language of EO 13202 requires a recipient to give up funding if any of the bid specifications for the project require a PLA, Richmond would not be able to avoid injury by segregating the DOT funds.
Furthermore, even if Richmond could segregate its DOT funds, the loss of a PLA for the portion of the project covered by $1.7 million is still a sufficiently concrete and particularized injury to justify standing. The primary purpose of a PLA is to cover all of the contracts on a project. The loss of that uniformity is a specific and concrete injury. In addition, the cost and inconvenience to Richmond associated with segregating the DOT funds from the FEMA and HUD funds, and with writing a PLA for only 97 percent of the project, would in itself be economic injury sufficient to support standing to challenge EO 13202.
Thus, defendants’ arguments that Richmond has not suffered sufficient injury to support standing are unpersuasive. Furthermore, as a recipient of the federal funds in question, Richmond is the direct object of the EO 13202, and therefore easily satisfies the causation requirement for standing. 7 Finally, the requested injunc-tive relief will redress Richmond’s injuries by allowing Richmond to go forward with a PLA on the RTV project or any other federally-funded project.
C. Contra Costa BCTC
The standing arguments for Contra Cos-ta County BCTC are subject to the same analysis as BTCD, discussed above.
See
However, the Court need not determine standing for Contra Costa BCTC because it has found standing for BCTD and Richmond. It is well-settled that a .court need not determine the standing of all plaintiffs when the standing of others has been established.
See, e.g., Clinton,
II. Standard of Review
Summary judgment should be granted only if the moving party has shown that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law.
See Celotex Corp. v. Catrett,
III. Constitutional and Statutory Authority
The President’s authority to issue an Executive Order “must stem either from an act of Congress or from the Constitution itself.”
Youngstown Sheet & Tube Co. v. Sawyer,
EO 13202 cites the President’s general authority under the “the Constitution and laws of the United States of America,” and in particular, the Procurement Act (or “the Federal Property and Administrative Services Act, 40 U.S.C. 471
et seq.”).
Despite the fact that the Procurement Act is the only specific authority cited in EO 13202, and despite the fact that defense counsel initially represented to the Court at oral argument that the Procurement Act authorized § 3,
8
defen
Defendants now argue that EO 13202 § 3 is authorized by both the Constitution and several federal statutes other than the Procurement Act. See Defs.’ Surreply at 1.
A. Constitution
Defendants’ constitutional argument rests on the “well-established” power of the President to supervise and guide subordinate executive officials to ensure the consistent execution of the laws.
See
Defs’ Surreply at 2
(citing Meyer v. Bush,
Defendants’ argument that EO 13202 is simply a constitutionally-authorized guidance by the President on the implementation of existing law is unpersuasive. EO 13202 does much more than guide agencies as to how to implement existing statutes it creates substantive prohibitions for federal agencies and substantive conditions on the receipt of federal funding. Once again, the words of the Supreme Court in the
Youngstown
case are particularly applicable here.
In the framework of our Constitution, the President’s power to see that the laws are faithfully executed refutes the idea that he is to be a lawmaker. The Constitution limits his functions in the lawmaking process to the recommending of laws he thinks wise and the vetoing of laws he thinks bad. And the Constitution is neither silent nor equivocal about who shall make laws which the President is to execute. The first section of the first article says that ‘All legislative Powers herein granted shall be vested in a Congress of the United States * * *.’ After granting many powers to the Congress, Article I goes on to provide that Congress may ‘make all Laws whichshall be necessary and proper for carrying into Execution the foregoing Powers and all other Powers vested by this Constitution in the Government of the United States, or in any Department or Officer thereof.’
Id. The reasons that the Youngstown Court believed the President’s action at issue in that case exceeded his Constitutional authority and intruded upon Congress’ law-making powers are also particularly applicable here:
The preamble of the order itself, like that of many statutes, sets out reasons why the President believes certain policies should be adopted, proclaims these policies as rules of conduct to be followed, and again, like a statute, authorizes a government official to promulgate additional rules and regulations consistent with the policy proclaimed and needed to carry that policy into execution. The power of Congress to adopt such public policies as those proclaimed by the order is beyond question.
Id. Here, the preamble of EO 13202 sets forth the policy justification for the order, § 1 and § 3 establish substantive rules of conduct, and § 7 directs the Federal Regulatory Council to amend its regulations to implement the order. As the Youngstown Court concluded, the Constitution does not independently authorize such a legislative action by the President absent a direct Congressional authorization.
B. Statute
In defending the statutory authority for § 3, defendants make two somewhat conflicting arguments. First, as explained above, defendants argue for the very first time in their surreply that, “in order to determine whether, and to what extent, Section 3 of EO 13202 will apply to a particular grant, the legislation and regulations governing that grant must be examined.” Defs’ Surreply at 3. Second, defendants argue that there is one general statute that authorizes § 3, independent from the specific statutes under which particular grants have been authorized. That statute is
The heads of executive agencies shall, within 30 days of the date of issuance of this order, review all statutes under their jurisdiction that provide authority to issue grants or enter into cooperative agreements for construction projects and identify any statute that provides authority to condition a grant award orcooperative agreement on the recipient’s or party’s agreement that neither bid specifications, project agreements, nor other controlling documents pertaining to the grant or cooperative agreement contain any of the elements specified in section l(a)(l)-(3), above.
Id. at Sec. 2. (a).
Second, even if defendants’ argument were a plausible reading of EO 13202’s “to the extent permitted by law” language, the underlying grant-authorizing statutes simply do not support the prohibition on the use of PLAs that the EO 13202 has created. The Court has not surveyed the countless statutory provisions that authorize the distribution of federal funds, and neither have defendants. Defendants erroneously assert that the only statutes at issue here are those that authorized the funds for the Woodrow Wilson Bridge Project and Richmond’s RTV Project. The issue before the Court is the President’s authority to issue this EO 13202 § 3, not just the authority of DOT to implement EO 13202 with respect to these projects. If defendants are going to rely on the authority of the underlying funding statutes for this Executive Order, then defendants should have pointed to the language that supports EO 13202’s blanket PLA prohibition in every statute that appropriates funds for entities conducting construction projects. Defendants have not, and the Court believes, can not, do that.
If the language of defendants’ chosen examples is any indication of Congress’ general practice, there is no statutory authority for § 3 to be found. Defendants argue that both the Woodrow Wilson Bridge Project and the RTV Village Project receive funding “under programs established pursuant to the Federal-Aid Highway Act,
(a) In all cases where the construction is to be performed by the State transportation department or under its supervision, a request for submission of bids shall be made by advertisement unless some other method is approved by the Secretary. The Secretary shall require such plans and specifications and such methods of bidding as shall be effective in securing competition.
Id.
Congress was clearly discussing the procedures for bid submission, and not the substantive requirements that a State may impose upon prospective bidders. The Act does discuss substantive requirements that
No requirement or obligation shall be imposed as a condition precedent to the award of a contract to such bidder for a project, or to the Secretary’s concurrence in the award of a contract to such bidder, unless such requirement or obligation is otherwise lawful and is specifically set forth in the advertised specifications.
Defendants’ second statutory authority argument is equally unpersuasive. Defendants rely on
The purposes of the OMB statute are: 1) to “help eliminate unnecessary administrative requirements on recipients of Government awards by characterizing the relationship between executive agencies and contractors,” 2) “prescribe criteria for executive agencies in selecting appropriate legal instruments,” and 3) “promote increased discipline in selecting and using procurement contracts, grant agreements, and cooperative agreements, maximize competition in making procurement contracts, and encourage competition in making grants and cooperative agreements.”
In sum, neither the Constitution, the Procurement Act, the individual funding statutes, nor the OMB statute provide the necessary authority for § 3 of EO 13202. This Court has no choice but to invalidate § 3 of EO 13202 as an action beyond the scope of the President’s authority.
IV. NLRA Preemption
If any doubt remains as to whether the President had the constitutional or statutory authority to promulgate § 3 of EO 13202, the Court also holds that both § 1 and § 3 of EO 13202 are preempted by the NLRA. In the guise of preserving open competition and government neutrality, EO 13202 has altered the balance of power between labor unions and employers on federally-funded construction projects. Couched in the language of creating a free market in which unions and employers can negotiate PLAs without the mandate or support of the project owners, EO 13202 has actually interfered with existing market conditions. EO 13202 removes the ability of labor organizations, federal agencies, and recipients of federal funding to negotiate PLAs to be included in the bid specifications for construction projects. EO 13202 has thus altered market conditions by removing both a significant bargaining chip from the hands of
A. Preemption and the NLRA
Because the NLRA does not contain an express preemption provision, a court should not find a governmental regulation pre-empted “... unless it conflicts with federal law or would frustrate the federal scheme, or unless [the court] discernís] from the totality of the circumstances that Congress sought to occupy the field to the exclusion of the States...”
Metropolitan Life Ins. Co. v. Massachusetts,
While most Supreme Court cases developing NLRA preemption doctrine have dealt with state regulation, it is clear that the same principles apply when the President attempts to regulate an area preempted by the NLRA through an Executive Order.
Reich,
B. Garmon Preemption
EO 13202 does not violate the
Garmon
preemption rule with respect to
The Supreme Court in
Garmon
recognized that Congress’ intent to exclusively occupy the field of labor policy would require judicial elucidation via inquiry into the scope of the NLRA: “Congress has formulated a code whereby it outlawed some aspects of labor activities and left others free for the operation of economic forces. As to both categories, the areas that have been pre-empted by federal authority and thereby withdrawn from state power are not susceptible of determination by fixed metes and bounds... This penumbral area can be rendered progressively clear only by the course of litigation.”
Garmon,
1. EO 13202
EO 13202 functions in two ways: it effectively prohibits federal agencies and recipients of federal funding from negotiating a project-wide PLA with labor unions, and it prohibits agencies or recipients from including any agreements voluntarily negotiated between labor unions and contractors directly in any bid specifications for the project. As discussed above, EO 13202 prohibits federal agencies and the recipients of federal funding from requiring or prohibiting PLAs in their construction contracts, bid specifications, or other controlling documents. EO 13202 § 1, 3 (a recipient shall not “require or prohibit bidders, offerors, contractors, or subcontractors to enter into or adhere to agreements with one or more labor organizations on the same or other related construction project(s).”) This effectively prohibits recipients of federal funding from negotiating with labor unions and agreeing to a project-wide PLA that will be required of all contractors.
Generally, the method by which contractors are required to agree to a PLA is through the bid specification process a project owner will include the PLA in the
In addition, while EO 13202 prohibits agencies and funding recipients from requiring PLAs, it also states that “nothing in this section shall prohibit contractors or subcontractors from voluntarily entering into agreements described in subsection [a].” EO 13202 at § 1(c). Thus, under EO 13202 labor unions and contractors are free to negotiate individual labor agreements. Plaintiffs argue that such individual agreements differ from a PLA in that they are unlikely to cover an entire project. Further, EO 13202 prohibits any such individual agreements from being included in the bid specifications for the project if the project is to receive federal funding. As discussed above, the mechanism by which PLAs are negotiated for public construction projects relies for the enforcement of the agreement on the inclusion of that agreement in the bid specifications. Indeed, many states statutorily require that any PLAs be included in those bid specifications. See Mem. of Law of Amicus Curiae New York State Thruway Authority at 5-6; Mem. of Law of Amicus Curiae State of Maryland at 9. Thus, the “voluntary” negotiation provision of EO 13202 is a poor substitute for the ability of recipients and labor organizations to negotiate and require PLAs.
Defendants have argued that EO 13202 requires only that a recipient not use a PLA for the portion of the project using federal funds subject to 13202. See Defs.’ Opp’n and Reply at 21 — 27 (arguing that the City of Richmond can segregate funds and use a PLA on the 97 percent of the project not subject to the EO). As discussed above with respect to Richmond’s RTV project, such segregation is contrary to the plain language of EO 13202. EO 13202 clearly prohibits the requirement of a PLA in any bid specifications or contracts for a federally-funded project.
2. The Scope of NLRA § 8(e) and (j)
The NLRA defines and proscribes unfair labor practices and creates a uniform system of labor law for the country.
nothing in this subsection shall apply to an agreement between a labor organization and an employer in the construction industry relating to the contracting or subcontracting of work to be done at the site of the construction, alteration, painting, or repair of a building, structure, or other work.
[i]t shall not be an unfair labor practice under subsections (a) and (b) of this section for an employer engaged primarily in the building and construction industry to make an agreement covering employees engaged (or who, upon their employment, will be engaged) in the building and construction industry with a labor organization of which building and construction employees are members,
and then goes on to describe several types of generally prohibited agreements to which the exception is created.
It is evident from the face of the statute that in enacting exemptions authorizing certain kinds of project labor agreements in the construction industry, Congress intended to accommodate conditions specific to that industry. Such conditions include, among others, the short-term nature of employment which makes posthire collective bargaining difficult, the contractor’s need for predictable costs and a steady supply of skilled labor, and a long-standing custom of prehire bargaining in the industry. See S.Rep. No. 187, 86th Cong., 1st Sess., 28, 55-56 (1959); H.R.Rep. No. 741, 86th Cong., 1st Sess., 19-20 (1959) U.S.Code Cong. & Admin. News p. 2318.
507 U.S. at 23f,
Sections 8(e) and (f) of the NLRA do not apply to PLAs negotiated and required by public recipients of federal funding, like the State of Maryland or Richmond in this case, or by federal agencies themselves, for two reasons that were articulated by the Supreme Court in
Boston Harbor.
Plaintiffs argue that PLAs required by public recipients of federal funding are authorized by the NLRA, and rely on language from
Boston Harbor. See
Pis.’ Opening Br. at 19, 33-34, 43-44. However, the passages from
Boston Harbor
cited by plaintiffs do not bear the weight plaintiffs would have them support. The Supreme Court did recognize in
Boston Harbor
that public owners should be able to require PLAs because Congress intended for that decision be left to the free play of economic forces, and therefore recognized the applicability of
Machinists
preemption doctrine. However, contrary to plaintiffs’ argument, the Court did not conclude that a public owners’ PLA was authorized or protected by the NLRA. Rather, for the two reasons described above, the Court concluded that these PLAs were beyond the reach of express NLRA regulation. In a footnote, plaintiffs seem to concede that PLAs “negotiated directly between a public entity and a union” would not be covered by §§ 8(e) and (f).
See
Pis.’ Opening Br. at 38 n .34. In distinguishing “directly” negotiated PLAs, which would not be covered, from the PLA at issue on the Woodrow Wilson Bridge Project, which they claim is covered, plaintiffs must be relying on the fact that the State of Maryland hired a project manager, Kaiser, to negotiate the PLA. However, because Kaiser was clearly acting as an agent of the state, that distinction makes no difference here. The PLA negotiated between BCTD, Kaiser and the State of Maryland for the Woodrow Wilson Bridge Project,
However, §§ 8(e) and (f) clearly apply to PLAs required by private employers.
See, e.g., Woelke & Romero Framing, Inc. v. N.L.R.B.,
3. Garmon Applied to EO 13202.
Because the NLRA does not specifically prohibit or authorize the use of PLAs by construction projects owned by public entities, there is no conflict between EO 13202 §§ 1 and 3 with Congress’ “integrated scheme of regulation” specified in NLRA §§ 7 and 8.
Garmon,
However, because the NLRA does specifically authorize the use of PLAs by private employers in § 8, EO 13202’s prohibition of required PLAs does violate Garmon preemption doctrine with respect to any private recipients of federal funding who act as employers in construction projects. Private entities are being prohibited by EO 13202 from requiring PLAs that are expressly allowed by the NLRA. Garmon preemption will not allow this direct conflict. EO 13202 is preempted with respect to private recipients of federal funding.
C. Machinists Preemption
1. EO 13202 §§ 1 and 3 Violate Machinists Preemption.
As the Supreme Court explained in
Boston Harbor, “Machinists
preemption preserves Congress’ intentional balance between the uncontrolled power of management and labor to further their respective interests.”
As the D.C. Circuit explained in
Reich,
the principle underlying
Machinists
preemption is that “union and management proceed from contrary and to an extent antagonistic viewpoints and concepts of self-interest ... The presence of economic weapons in reserve, and their actual exercise on occasion by the parties, is part and parcel of the system that the [NLRA] recognized.’”
In
Boston
Harbor; the Supreme Court addressed the argument that a decision by the State of Massachusetts and its project manager for the Boston Harbor clean-up to include a PLA in its bid specifications was government regulation that violated NLRA preemption principles. The Court rejected that argument, holding that the decision by the State with respect to this one project did not constitute regulation, but rather was the action of a market participant, and as such could not run afoul of either
Garmon
or
Machinists
preemption.
While the Court in
Boston Harbor
was discussing the impact of its own decision on actors in the labor market, there is no material difference between a judicial action and the Executive Order as forms of government regulation. Both would im-permissibly “deny[] an option to public owner-developers that is available to private owner-developers.”
Id.
at 232,
Furthermore, while the
Boston Harbor
Court focused on the disparity between public and private developers, EO 13202 also removes an economic weapon from the arsenal of labor organizations.
Machinists
preemption is concerned with the areas left to the free play of economic forces between both employers and employees.
Reich,
2. Defendants’ Arguments to the Contrary are Not Persuasive.
Defendants have raised several arguments during the course of this litigation against the applicability of Machinists preemption. First, EO 13202 is not preempted by the NLRA because it imposes no sanctions on funding recipients. Second, EO 13202 was the act of the federal government as a market purchaser, and under Boston Harbor is therefore not subject to NLRA preemption. Third, Machinists preemption does not apply here because the government has only attempted to establish neutrality, rather than skewing the labor market. Fourth, Machinists preemption does not apply here because while NLRA preemption precludes government interference with rights protected by the NLRA, it does not require the government to subsidize those rights. Fifth, because EO 13202 allows “voluntary” PLAs among contractors and labor unions, it represents a minimal intrusion into the collective bargaining process.
a. Defendants’Sanction Argument.
Defendants argue that EO 13202 does not conflict with the NLRA because it imposes no sanctions on entities regulated or protected by the NLRA. See Defs.’ Opp’n and Reply at 39 — 46. Thus, defendants attempt to distinguish the Reich case by demonstrating that the Executive Order in Reich directly sanctioned employers who were subject to express NLRA provisions. While it is unclear from defendants’ brief, this argument can best be understood as a variation on the Garmon theme: that here there is no direct conflict between EO 13202 and an area expressly protected or prohibited by the NLRA, and therefore EO 13202 is not pre-empted under Garmon principles. While defendants’ focus on sanctions is misplaced, 16 the basic thrust of the argument has merit. See Defs’ Opp’n and Reply at 45 and 56. As discussed above, with respect to public recipients of federal funding, Garmon preemption does not apply.
b. Defendants’ Market Participant Argument.
Defendants also argue that EO 13202 is a reflection of the federal government’s proprietary interest and not an attempt to regulate the labor market. Relying on the Supreme Court’s holding in Boston Harbor that Massachusetts was not subject to NLRA preemption when acting as a market participant rather than as a regulator, defendants argue that EO 13202 is a reflection of the government’s proprietary interest in determining how its money is spent. See Defs.’ Opp’n and Reply at 58.
In support of this argument, defendants claim that in order for government action to be considered regulatory for NLRA
EO 13202 is clearly a regulatory act rather than the government “act[ing] just like a private contractor would act.”
Reich,
Finally, defendants argue that EO 13202 must be a proprietary action because it imposes no sanctions or restrictions on anyone other than federal agencies and recipients of federal funds. However, by imposing a general condition for all federal agencies and all recipients of federal funding under all funding statutes, the government has acted in a regulatory capacity. The fact that no one other than the agencies or the funding recipients may be sanctioned does not alter the broad policy implications of EO 13202. The government is using the power of its purse to control and regulate the behavior of other market participants.
Boston Harbor,
c. Defendants ’ Neutrality Argument.
In attempting to counter plaintiffs’ Machinists argument, defendants argue that EO 13202 was intended to “take governmental entities out of the decision-making process” and “to allow the question of whether or not to use a PLA to be settled through bargaining between construction contractors and labor organizations.” Defs.’ Opp’n and Reply at 67. Defendants actually concede that “[t]o be sure, EO 13202 affects market conditions by precluding federal agencies and federal grantees from mandating the use of PLAs on federal or federally financed construction projects.” Id.
Machinists
preemption applies to governmental attempts to establish “neutrality” in the labor market as much as it does to attempts to skew the balance of power in favor of employers or employees. Government “lacks the authority to introduce some standard of properly balanced bar
d. Defendants’ Rights Sttbsidization Argument.
Defendants also attempt to avoid
Machinists
preemption with the argument that government refusals to subsidize rights do not infringe upon rights. Citing
Rust v. Sullivan,
e. Defendant’s Voluntary PDA Argument.
Defendants also argue that because EO 13202 allows for voluntary PLAs, the intrusion on the collective bargaining process is minimal and therefore can not violate
Machinists
preemption. Even if voluntary PLAs were an adequate substitute for mandatory PLAS, as the D.C. Circuit stated in
Reich,
“[w]e do not think the scope of the President’s intervention into and adjustment of labor relations is determinative.”
Defendants arguments have not persuaded the Court that both § 1 and § 3 of EO 13202 can avoid Machinists preemption. The President has intruded upon a sphere that only Congress can regulate and therefore this Court must permanently enjoin EO 13202.
CONCLUSION
For the foregoing reasons, the Court is persuaded that all plaintiffs in this case
Accordingly, the plaintiffs’ motion for summary judgment is GRANTED and the defendants’ motion for summary judgment is DENIED. Constitutional and statutory precedent of long-standing persuades the Court that the President lacked the requisite authority for Executive Order 13202 § 3 and that Executive Order 13202 in its entirety is preempted by the NLRA. Accordingly, enforcement of Executive Order 13202 is permanently enjoined by the Court.
An appropriate Order accompanies this Memorandum Opinion.
ORDER
For the reasons stated in the Memorandum Opinion filed today, it is hereby
ORDERED that plaintiffs’ motion for summary judgment is GRANTED; it is
FURTHER ORDERED that defendants’ motion for summary judgment is DENIED; it is
FURTHER ORDERED that the President lacked the requisite authority for Executive Order 13202 § 3 and that Executive Order 13202 in its entirety is preempted by the NLRA; it is
FURTHER ORDERED that enforcement of Executive Order 13,202 is permanently enjoined; it is
FURTHER ORDERED that the Clerk of the Court enter final JUDGMENT in favor of plaintiffs and against defendants.
IT IS SO ORDERED.
Notes
. Executive Order 12818, titled "Open Bidding on Federal and Federally Funded Construction Projects,” October 23, 1992, revoked by Executive Order 12836, titled "Revocation of Certain Executive Orders Concerning Federal Contracting,” Feb. 1, 1993.
. Joining this same amicus brief were the Associated Builders and Contractors of the Metropolitan Washington, Inc., Associated Builders and Contractors, Golden Gate Chapter, Hispanic Chamber of Commerce of Contra Costa County, Western Electrical Contractors Association, Independent Roofing Contractors of California, and the Coalition for Fair Employment in Construction.
.
See generally San Diego Bldg. Trades Council v. Garmon,
. From the perspective of a funding recipient, there are no relevant differences in the level of coercion created by conditions on funding placed through an act of Congress or through an Executive Order. Thus, the government's argument about coercion (or lack thereof) in this case would apply to any challenge to legislation authorized by the Spending Clause.
. In order to reach the merits of the plaintiffs' constitutional claims in
Planned Parenthood,
the Second Circuit assumed standing.
. Defendants have not challenged standing on redressability grounds.
. Defendants have not challenged Richmond's standing on either causation or redressability grounds.
.
See
Transcript of September 19, 2001 hearing at 78 ("It's a procurement regulation, and
. The Court need not reach the scope of the Procurement Act and the authority for § 1 because the parties have not briefed that issue. The authority for § 1 is presumed for purposes of deciding the NLRA preemption issue.
. The reason these two arguments conflict is that if the OMB statute really provided authority for § 3's conditions on grant assistance, there would be no need to examine the scope of each individual grant statute for independent authority.
. Curiously, defendants do not point to any language in the statute that actually appropriated the funds for the Woodrow Wilson Bridge Project. See Woodrow Wilson Bridge Authority Act, as amended, Pub.L. 105-78, 112 Stat. 159.
. The Court notes that what the President has attempted to achieve here through an Executive Order is a regulation that the Secretary of Transportation could promulgate only through rule-making procedures required by the Administrative Procedures Act (APA). Because the statutory language does not provide the authority for the President's action, the Court need not address the questions raised by the President’s attempted bypass of the APA's requirements.
.
Reich
also rejected the claim that a President’s Executive Order was insulated from judicial review.
. Much of defendants’ discussion of this issue comes during its standing argument. See Defs.' Opp'n and Reply at 7 — 20 (arguing that because these PLAs are not protected by the NLRA, plaintiffs have no legally protected interest on which to base standing). As noted above, whether or not the NLRA regulates PLAs entered by public entities is relevant to the merits of the preemption claim, not to standing and thus will be discussed here. Plaintiffs have not taken an entirely clear position on this issue, as their brief at times claims the PLAs negotiated by public entities are protected by the NLRA and at times admits that they are not. Compare Pis.' Opening Br. at 19, 43-44 (NLRA applies) with Pis.’ Opening Br. at 38 n. 34 (NLRA does not apply to public projects).
. While the Court in
Boston Harbor
did recognize that public entities' PLAs were outside the scope of the NLRA’s express regulations, importantly, the Court recognized that these PLAs were within “Congress’ intended free play of economic forces” for purposes of
Machinists
preemption, discussed below.
.
Garmon
preemption is clearly not limited to those government actions that impose sanctions or deny government benefits to entities covered by the NLRA. Rather, interference of any form, with the activities that constitute "Congress' integrated scheme of regulation,” meaning "activities that are protected by § 7 of the NLRA, or constitute an unfair labor practice under § 8” is prohibited under
Garmon. Boston Harbor,