183 Ky. 500 | Ky. Ct. App. | 1919
(Opinion op the Court by
Reversing.
The appellants, Bugg & Franks, liad a contract -with Ballard county to construct about ten miles of macadamized road; they sublet to appellee the construction of slightly over two miles of the road by written contract,' by which they agreed to furnish him a roller and grader for use in performing his contract. Alleging a failure to furnish the roller as agreed, appellee brought this action to recover $1,000.00 as damages for the alleged breach of contract, and upon a trial, the jury .returned a verdict in his favor for $500.00; and to reverse the judgment entered thereon the defendants have prosecuted this appeal.
The principal grounds of complaint are that the court erred in defining the measure of damages in the instructions to the jury, the admission of incompetent evidence, and that the verdict is excessive.
The measure of damages fixed by the court was the difference between the amount it would have cost plaintiff to have constructed so much of the road he had contracted to build before the filing of the suit, if the road roller had been furnished to him by the defendants as agreed, and the cost of constructing the road, after their refusal to furnish him with the road roller,, if they did refuse, not exceeding the sum of $1,000.00.
Plaintiff’s evidence'was that he had the grade of the road ready for the roller on the 6th or 7th of November, and demanded of the defendants that they furnish him the roller, with which to complete the grade as required by the specifications and contracts with the county and between the parties, but that they did not furnish it until November 17th; that upon one or two occasions thereafter, and before December 5th, he was delayed by the failure of the defendants to furnish the .roller promptly upon demand; that altogether between the 7th of November and 5th of December, he was. delayed from ten to fifteen days by the failure of the defendants to furnish the roller when required and demanded of them.
Within this rule evidence of expenses necessarily incurred by plaintiff, if any, while waiting for the roller, of the difference between what it would have then cost him to construct so much of the road as he could have completed by December 5th, if the-re had been no breach and what it would have cost him to do the same work the next June, as well as of the cost of repairing any damage to the same incompleted portion of the road as resulted from the delay occasioned by the breach, was competent and properly admitted, as.these several items of possible damage it seems to us must have been reasonably contemplated as .a probable consequence of such a breach of the contract as is alleged, and which are capable of being reasonably ascertained, but the instruction upon the measure of damages should have been restricted to such of these several items as were supported by sufficient evidence to permit of a reasonably accurate estimation by the jury.
Wherefore the judgment is .reversed and the Gause remanded for another trial consistent with this opinion.