95 Mo. App. 148 | Mo. Ct. App. | 1902
On the eleventh of May, 1899, the defendant sold to plaintiff a mining lease for the sum of three thousand dollars, agreeing, in certain conditions, to repurchase of plaintiff at the end of one year for the same sum. At the expiration of a year plaintiff offered to transfer the lease back to defendant and demanded the money he had paid him, which defendant refused. Plaintiff then instituted this action to recover that sum and prevailed in the trial court. The contract sued on was written in the following words:
“For and in consideration of the sum of three thousand dollars, the receipt of which is hereby acknowledged, I, this eleventh day of May, A. D. 1899, have bargained, sold and transferred all my right, title and interest in and to an undivided one-half interest in a mining lease described as follows, to-wit: [description] to I. W. P. Buchanan of Lebanon, Tennessee.
“It is agreed and understood by George W. Layne,*152 of Joplin, Missouri, party of the first part, and I. W. P. Buchanan, party of the second part, witnesseth: that the party of the first part agrees to 'pay the party of the second part, three thousand dollars on the eleventh day of May, 1900, for the above-described lease, providing, the party of the second part continues to mine and oper-, ate said land in good shape by developing and placing ore on the market, and carrying on a general mining business by subleasing and developing the property as is done throughout the mining district so as not to diminish in any way, shape or form, the value of the above lease. Should the party of the second part wish to retain or keep the above described lease at the expiration of one year as above named, he can do so and retain all royalties received during the year ending May 11, 1900. Signed this eleventh day of May, 1899, in duplicate. George W. Layne.”
The evidence tended to show that plaintiff substantially complied with the terms of the contract, except that he did not develop and place ore on the market. One of defendant’s principal objections to the judgment is that the developing and placing ore on the market, was a condition precedent in the contract and that it was necessary for plaintiff to allege its performance in order to have a hearing in court; and that he should prove its performance in order to recover his claim. The law is that a plaintiff in a suit upon a contract should allege a performance, on his part, of all conditions precedent, or allege an excuse for non-performance. Basye v. Ambrose, 32 Mo. 484: McNees v. Ins. Co., 61 Mo. App. 335. Here, the petition, when taken as a whole, does clearly state that no ore was developed or placed on the market from the fact that it could not be found on the leased ground. This was sufficient as to the pleading, and there was evidence tending to support the excuse thus set up.
2. "We are thus brought to a consideration of the point made by defendant that the contract, being in pos
The foregoing view discloses that the action of the court on the instructions was proper. They presented the issues of the case plainly and fairly and permitted the failure to produce and market ore to be excused if it was found that there was no ore on the land.
The judgment is affirmed.