Plaintiff, a test pilot, brought suit for $2,500 against defendant, a manufacturer of aircraft, as the balance of an agreed price for the testing of a glider which defendant was manufacturing for the Air Corps of the War Department. Plaintiff upon full performance of his contract was to receive $5,000 for his services, he was paid $2,500, and was sued by cross-complaint for the sum of $1,000 which defendant claimed to have paid him in excess of the amount he had earned. Judgment was in favor of plaintiff on his complaint and the cross-complaint, and defendant appeals. Defendant’s contract with the War Department called for ten gliders to be furnished, at $8,725 each, and a glider trailer at $1,500, or a total of $88,750. The gliders and the trailer were delivered' and accepted. In negotiations with the War Department following completion of the contract, defendant agreed to accept a reduction of $2,500 in the contract price and was paid $86,250.
Defendant’s contract with the Air Corps called for testing only the first glider and provided in part as follows: “Reference Paragraph 7, after acceptance of the first Glider, the Contractor shall perform flight tests under the supervision of the procuring agency. These tests shall be performed at Muroe Bombing Range, Muroc, California and shall include the checking of the towing, climbing, and gliding characteristics as well as the functioning of the Government-furnished
The contract between plaintiff and defendant, in its material provisions, reads as follows: “For the sum.of five thousand ($5,000.00) dollars, I, La Verne W. Browne, agree to supply all the necessary test piloting called for under United States Army Air Force Contract W 535 ae 26734. These tests shall be performed at Muroc Bombing Range, Muroc, California, and shall include the checking of the towing, climbing, and gliding characteristics as well as the functioning of the Government furnished Television, Radio and Servo Equipment installed therein. The tests shall not exceed ten (10) flight hours. . . . This agreement may be eoneelled by mutual, agreement of the parties hereto and it is further agreed that on payment of monies due for test flying on a pro rata basis (ratio of hours flown to total ten (10) flight hours) at the time of termination will complete the obligation of both parties. Fletcher Aviation Corporation agrees to pay the five thousand dollars in the following manner: Two thousand five-hundred ($2,500.00) dollars prior to the flight tests and the remaining two thousand five-hundred ($2,500.00) dollars at the completion of this contract. ’ ’
The evidence disclosed that if the glider should be flown before the radio equipment was installed, it would be controlled manually by the pilot. The radio equipment was for control of the glider by someone who would operate a radio control from another plane or from the ground, although a pilot would be aboard the glider and would be able to exercise manual control if necessary. Plaintiff made three manually controlled test flights under the supervision of the Army Air Corps on April 26 and 27, 1942, without any of the special equipment having been installed, a total of three hours being required for such flights. He was at all times ready, able and willing to make further test flights, as defendant was to have them made, but the Air Corps furnished no television, radio or Servo equipment, requested no further tests,' and on January 5, 1943, after it had accepted delivery of the gliders
Defendant advanced three theories of nonliability: (1) that plaintiff did not fully perform his obligation; (2) that the modification of the government contract omitting further flight tests made further performance of the Browne contract impossible, and (3) said modification frustrated the object and purpose of the Browne contract and excused further performance'of that contract on the part of defendant.
In the argument of its first point defendant challenges the sufficiency of the evidence to support the court’s finding that plaintiff fully performed the contract on his part. In determining whether the evidence justified this finding, we must first' examine the contract to see what services plaintiff agreed to perform. Defendant’s contention is twofold: (a) that plaintiff’s services could not have been completed without the making of two kinds of tests, manual and radio controlled, and (b) that they could not have been completed without test flying the glider for a full ten hours. Plaintiff’s contention is that his contract was completed when the Air Corps accepted as sufficient the test flights that had already been made and waived the right to require further testing.
"Upon the trial testimony of defendant’s officers was introduced to the effect that in the negotiations which preceded the execution of the contract, plaintiff agreed to test the glider under manual control for $2,500, and raised his price to $5,000 when it was learned that the Air Corps contract would call for testing under radio control, and one of them testified that it was understood that one type of test would entail approximately equal time with the other. Plaintiff testified that there was no such agreement or understanding. Defendant insists that the testimony of its officers was introduced for the purpose of proving that the contract could not be performed by plaintiff without tests being made of the. special equipment. At the same time it disclaims a purpose to prove' that plaintiff was to receive $2,500 for the manual flying and $2,500 for the radio controlled flying. When settlement was made with the Air Corps, defendant’s intention apparently was to withhold $2,500 from plaintiff’s compensation because he had not made the radio controlled tests, and it is clear from the testimony of defendant’s officers and from their conduct as well, that when they undertook to
Again, defendant contends that plaintiff was required to make test flights for the full ten hours which the Air Corps could have insisted upon. One of defendant’s officers testified, without objection, that it was understood in the negotia
Plaintiff’s construction of the contract is that he was only required to do the “necessary” test flying required by the Air Corps contract. In this he is correct, as the agreement provides that he was required “to supply all the necessary test piloting called for under United States Army Air Forces contract W 535 ac 26734. ” (Italics added.) A proper construction of defendant’s contract with the Air Corps is that tests were to be made for ten hours, or for such lesser time as would be satisfactory to the Air Corps. No specific tests were stipulated in either contract. The uncertainty as to the nature and the extent of the tests that would be required was evidenced by the stipulation that they should not exceed ten flight hours. Plaintiff’s contract was prepared by defendant and the use of the qualifying word “necessary” clearly implied that the parties had in mind that full ten hours’ testing might not be necessary. The Air Corps, having supervision of the tests, could, at any stage thereof, accept those already made as performance by defendant of its contract and could waive any further tests. Performance by defendant of its contract with the Air Corps, and performance of plaintiff’s contract as well, was complete when the Air Corps declared the tests to be sufficient, and it is wholly immaterial that this occurred before any of the special equipment had been installed for testing. The finding that plaintiff fully performed his services under the contract was justified by the evidence.
Defendant’s next points, namely, alleged impossibility of further performance, and alleged frustration of the object and purpose of both parties to plaintiff’s contract are discussed together in defendant’s brief and we will so consider them. The principles under which relief may be granted where further performance has become impossible and those which apply where some occurrence that was not reasonably foreseeable has defeated the object and purpose of a contract were fully considered and discussed in the recent
When the Air Corps accepted the tests as sufficient to furnish all of the information it required, the purpose of the employment contract was fully accomplished. Another answer to the claim of frustration is that the contract did not give defendant the right to deduct any sum from the amount of plaintiff’s compensation in the event the Air Corps was satisfied with less than the maximum amount of testing, and it must be deemed to have waived that right. Defendant’s argument is essentially the following: it was expected that the Air Corps would require both manual and radio controlled tests for the full ten hours and that plaintiff therefore would be required to make such tests; that the waiver of some of the tests was unexpected and beyond the control of defendant, and that plaintiff, having been relieved of his obligation to make those tests, should not be paid the full sum he would have been entitled to if he had made them. It may be that the Air Corps was entitled to credit under its contract with defendant in case it did not require full ten hours of testing. The entire contract was not received in evidence and we do not know whether there was such a pro
One additional argument is made by defendant in support of its demand under the cross-complaint. Its agreement with plaintiff provided for payment upon an hourly basis for the work that had been done in ease of termination of the contract by consent of the parties. It is argued that the value of plaintiff’s services was fixed by this provision and that plaintiff earned only $1,500 at the hourly rate and was overpaid to the extent of $1,000, which he should return. A sufficient answer is that there was no termination of the agreement by mutual consent. The action of the Air Corps
We are of the opinion that the judgment is a correct and just determination of the case and that it should be affirmed.
The judgment is affirmed.
Desmond, P. J., and Wood (Parker), J., concurred.
A petition for a rehearing was' denied March 5, 1945, and appellant’s petition for a hearing by the Supreme Court was denied April 4, 1945.