266 P. 60 | Kan. | 1928
Lead Opinion
The opinion of the court was delivered by
The Brown-Crummer Investment Company sued Arkansas City to recover $18,878.51, as damages for its failure to deliver certain bonds of the city in compliance with an alleged agreement. The cause was submitted on pleadings, opening state
The record discloses that Arkansas City created a sewer district designated as sewer district number six and advertised for bids for the sewer’s construction. A bid made by C. H. Everett was accepted, and on July 1,1921, a contract was entered into between the city and Everett, that he would construct the sewer at stipulated price for work actually done, the total price of which was later found to be $116,232. Among other things the contract provided that at the end of each month the engineer would make an estimate of the material delivered and work done, which would show the amount due to the contractor under the estimate. It was provided also that a final estimate should be made on the completion of the improvement giving the total contract price for the work done. When a maintenance bond was given and receipts for material were shown, or in lieu of them a list of unpaid bills should be produced, and when the contract was completed and the work had passed a city test, the contractor, Everett, should be paid the total of the final estimate or as much as remained due after deducting the .total of all unpaid bills. As to payment under the contract it was provided that “payment shall be made in bonds with accrued interest or cash at the option of the city.” Everett arranged with plaintiff to finance the project. By their arrangement the plaintiff was to advance money to meet the bills for labor and material as the work progressed, upon notes to be given by Everett drawing interest at eight per cent-per annum, he to assign to plaintiff the estimates given by the city as security for the payment of the notes.
On September 15, 1921, the plaintiff proposed to Everett that he should assign all his rights to purchase sewer bonds on the condition that they would amount to approximately $115,000, bearing interest at the rate of six per cent per annum, and that they should be delivered to plaintiff at par value and accrued interest to date of payment, and that if not delivered to plaintiff by January 15, 1922, plaintiff should have the benefit of accrued interest from that date to the date of payment. Plaintiff also proposed to cash and carry the estimates to be delivered to Everett in part payment of the improvement, these to be assigned to plaintiff with proper recogni
“Whereas, The city of Arkansas City, Kan,, has entered into a contract with C. H. Everett for the construction of sewer improvements in sewer district No. 6 of said city; and
“Whereas, The city of Arkansas City has agreed to deliver to said C. H. Everett its negotiable, bonds for the payment of such wotIc; and
“Whereas, Said C. H. Everett has made an assignment of all his right, title and interest in and to said bonds to the Brown-Crummer Investment Company, of Wichita, Kan.:
“Now, therefore, be it resolved by the board of commissioners of Arkansas City, Kan/., That said city shall pay said C. H. Everett, the contractor, in bonds, for all work in sewer improvement district No. 6, and that it accepts the terms of said assignment and agrees to deliver the bonds to be issued in full payment of such work, to the Brown-Crummer Investment Company of Wichita, Kan., as soon as the same can legally be issued, subject to the full performance of the terms and conditions in the contract for said sewer improvements entered into between said Everett and city of Arkansas City, and all. the terms and conditions of said assignment and indorsements thereon.”
The plaintiff alleged that relying on the resolution quoted and the agreement of the city to deliver the bonds, it advanced to Everett the further sum of $35,000. Later, and on January 23,1922, when the sewer was completed, 'the city claimed that it still had the
The principal point in controversy is whether the city had exercised its option to pay for the improvement in bonds or money. It is conceded that it alone had that option, but it is contended that when the city passed the resolution recognizing the assignment by Everett to plaintiff of all his right, title and interest to the bonds, and had expressly agreed to deliver the bonds to plaintiff, the option had been effectively exercised, and- that payment could only be made in bonds. It was alleged that the city announced to bidders at the letting of the contract that the one who secured the contract must accept in payment six per cent bonds at par, and the import of the resolution quoted and its acceptances and agreements noted on earlier estimates, is that the cost of the improvement was to be paid in bonds instead of money. The court is of the opinion that the resolution and the action taken under it constitutes an unequivocal election to deliver bonds in payment of the improvement, and that when issued they were to be delivered to the plaintiff. In connection with the election there was an independent agreement to deliver them to the plaintiff. On the faith of that election and agreement the plaintiff had advanced a large sum of money towards the payment of the expense of the improvement. One of the contentions of the city is that the resolution related to a public governmental function, and finding that the action taken was improvident and erroneous, it could at will rescind its action and repeal the resolution. It must be granted that the construction of a sewer being a provision to conserve the public health is a governmental or public function rather than a private or proprietary one. (Foster v.
Although the consideration of the contract is challenged, there can be little doubt as to the sufficiency of the consideration. The plaintiff which had previously advanced more than $50,000 to the contractor, which was the amount it had agreed to advance to him on the improvement, made another advance of $35,000 after the city had agreed to deliver the bonds to it. This was-done in reliance upon the agreement the city had made with it. Preliminary arrangements for the disposition of the bonds were made by the plaintiff, and it had caused the printing of blank bonds with a view of facilitating the prompt delivery of them. Plaintiff, which was a dealer in bonds, had obligated itself to purchase and dispose of the bonds and had assumed the hazard of a falling market and to suffer a loss if they brought less than'the current value.
Another contention of the city is that if it be granted that there was an exercise of the option and an agreement to deliver the bonds to plaintiff, the agreement was too indefinite to be enforceable. In the agreement no mention was made of the rate of interest the bonds should bear or the period within which they would mature. It is argued that this was an important element of the agreement, the omission of which renders the agreement so incomplete as to be invalid. There was uncertainty in these respects at the time the agreement was made, but it cannot be said that there was any uncertainty after the city had issued the bonds. Both parties were negotiating as to sewer bonds of this particular sewer project, and which were referred to in the resolution which closed the agreement to deliver the bonds to plaintiff. Whatever indefiniteness there was as to rate of interest or time of maturity, these were made definite when the bonds were executed. In the contract with Everett the parties stipulated that if the improvement was paid for in bonds they should be accepted at par with accrued interest. Indefiniteness in an agreement when made may be cured by the subsequent acts of
“If, however, the side of the agreement which was originally too vague for enforcement becomes definite by entire or partial performance, the other side of the agreement (or divisible part thereof, corresponding to the performance-received), though originally unenforceable, becomes binding. And even without performance on either side the original indefiniteness may sometimes be cured by a subsequent definition of the intended performance.” (§ 49. See, also, Kansas City v. Construction Co., 86 Kan. 213, 120 Pac. 347; King v. Stephens et al., 113 Kan. 558, 215 Pac. 311; Jennings v. City of Pasco, 82 Wash. 335, 144 Pac. 37; Daily v. Minnick, 117 Ia. 563; Work v. Welsh, 160 Ill. 468.)
In Gould v. Gunn, 161 Ia. 155, it was^said:
“Again, a contract, uncertain when made, may, by practical construction or otherwise, be made certain after its execution and before suit brought; and practical construction is often a safe guide whereby to determine the intention.” (p. 164.)
The issuance of the bonds agreed to be delivered, fixing the rate and the time they were to run, cleared away the only uncertainty asserted. The bonds were issued bearing interest at five and one-half per cent per annum and running for a period of twenty years.
There is a further contention that the acceptance of payment in money of the contract price of the improvement was not only a satisfaction of the assigned claim, but operated as a waiver of all claims for damages that the assignee might have had for a breach of the agreement. Under the pleadings the effect of the tender of the contract price of the improvement and its acceptance was not left for determination under the general rules of law. It was expressly agreed between the plaintiff and the defendant that the payment and acceptance of the money should not affect or prejudice plaintiff’s right to damages for the failure of the city to deliver the bonds in accordance with the agreement. This express reservation left the matter of damages open for judicial determination.
Another proposition advanced by the city is that the issues in the action had formerly been adjudicated. In 1922 a mandamus action was instituted by the plaintiff to compel the issuance and delivery of the bonds to plaintiff. That action was challenged by a motion to quash the writ, which was sustained by, the court. Upon what ground the writ was quashed is not shown. Among the grounds asserted by the city was one that the action was prematurely brought. The mandamus proceeding was begun before the bonds had been
In Routh v. Finney County, 84 Kan. 25, 113 Pac. 397, it was said:
“A judgment which may have resulted from a determination of either one of two or more separate issues, does not constitute an adjudication as to either where it is not shown upon which it was in fact based.” (Syl. ¶ 2.)
In De Sollar v. Hanscome, 158 U. S. 216, it was said:
“If there be any uncertainty on this head in the record, as, for example, if it appear that several distinct matters may have been litigated, upon one or more of which the judgment . . . was rendered, the whole subject matter of the action will be at large, and open to a new contention, unless this uncertainty be removed by extrinsic evidence showing the precise point involved and determined.”
On the record presented we cannot hold that the doctrine of res adjudicata applies to this action.
A cross appeal is filed from the judgment rendered by the court against the city and in favor of C. H. Everett, the intervener. He had built and completed the sewer on January 23, 1922. On that date it was accepted by the city as a satisfactory compliance with the contract. He then became entitled to full payment of the contract price. He did not, it appears, have the means to carry on the w;ork, and had arranged with the investment company to finance him and thus enable him to meet bills for labor and material necessary to carry on the work. He executed his notes to the investment
“No good reason appears why he may not interplead in the action pending between the Brown-Crummer Investment Company and the defendant city.” (p. 447.)
It now appears that this feature of the controversy has been settled between Everett and the investment company, and the plaintiff in the present action made the following statement in open court':
“For the purposes of the record I want to concede as between Mr. Everett and ourselves, in order to settle the question about interest, Mr. Everett is entitled to this claim which he makes for interest. I think the court understands what the claim is. In other words, we are not claiming the fund he is in here intervening for.”
The city in its brief says that it had tendered the interest to the investment company, which was not accepted; but “if BrownCrummer Investment Company desires to waive its right to the interest tender, then the city has no objection to paying this
Dissenting Opinion
(dissenting): Inasmuch as the building of a sewer is a governmental function, it was within the power of the city commission to repeal the resolution and rescind its action relating to payment in bonds instead of in money, therefore I am unable to concur in the decision upon that point.
I also dissent from the determination that the resolution resulted in a valid contract. As the parties did not agree upon the rate of interest the bonds should bear nor as to the time the bonds should run, the so-called contract is so incomplete and indefinite as to be unenforceable.