The issue in this case is whether the course of conduct and communications between plaintiff-respondent Brown and defendants-appellants Cale created a legally enforceable agreement. Trial Term found that it did and entered judgment for the plaintiff for the balance due for electrical work Brown had performed at Gale’s building project. Cale now appeals from the Appellate Division’s order of affirmance.
Cale was the owner and builder of Northway Shopping Plaza in the City of Glens Falls. In January, 1967, it entered into a written contract whereunder the defendant Beam became general contractor for a section of the plaza. At about the same time, Beam, in turn, subcontracted in writing with Brown for the installation of the electrical work.
Starting as early as March, Beam, though it was more than current in the receipt of moneys requisitioned by it pursuant to the terms of its agreement with Cale, was running into arrears in its own payments to Brown. As a result, Brown began to entertain such serious doubts about whether Beam would carry out its end of their agreement that it threatened in writing to claim a breach of contract unless the payments were brought up to date. True to the forebodings which
Before handing down its decision for the plaintiff, the trial court, sitting without a jury, received oral as well as written evidence. In affirming the judgment, the majority at the Appellate Division found that the record confirmed the existence of a direct contract between Brown and Cale and that, in accordance with that contract, Cale was obligated to pay Brown the balance due for the electrical work up to the time of its completion. Our own examination of the proof reveals that the course of conduct between Cale and Brown, including their writings, especially taken against the continuum of events from March through September, was sufficient to spell out a binding contract between Brown and Cale independent from the one that had pre-existed between Brown and Beam. We therefore affirm.
In accordance with long-established principles, the existence of a binding contract is not dependent on the subjective intent of either Brown or Cale (Mencher v Weiss,
Generally, the aim is a practical interpretation of the expressions of the parties to the end that there be a "realization of [their] reasonable expectations” (1 Corbin, Contracts, § 1). That principle is especially applicable here, where, at least until the litigation ensued, the actions of neither party appears to have been guided by the norms and forms of legal counsel (cf. Matter of Doughboy Inds. [Pantasote Co.],
And, while "it is the responsibility of the court to interpret written instruments (4 Williston, Contracts, § 601, supra)] where a finding of whether an intent to contract is dependent as well on other evidence from which differing inferences may be drawn, a question of fact arises (Mallad Constr. Corp. v County Fed. Sav. & Loan Assn.,
Turning to that proof, we note that, though Brown’s written notice in March that unless payments were brought up to date he would regard Beam as having breached his contract was made to Beam alone, it may be inferred that the problem it reflected was one which in the natural course of events caused Cale concern as well. Obviously, it raised a threat to the scheduled completion of his building project. It may also be said to have evidenced that Beam’s requisitions, which other proof showed had in fact resulted in advances to it in excess of Gale’s obligation, were not being rechanneled by Beam to Brown and other subcontractors in sufficient amounts to assure the expeditious progress of the construction. Indeed, by June, one of the Browns had already spoken of this problem directly by telephone to Castle, Gale’s president, several times and, early that month, in a personal meeting between Castle and Brown, Castle offered to include Brown’s name on Gale’s future checks to Beam; immediately thereafter, that practice was put into effect. The making of this arrangement was not
The extent of Brown’s and Gale’s reliance on one another could be found too in the fact that Brown did not exercise its right to leave the job on Beam’s default. Instead, it continued performing the work, foregoing its right to treat Beam’s abandonment and arrearages as a breach justifying its own departure (cf. Wharton v Winch,
This step-by-step continuum of events and permissible inferences, viewed in totality, brought the determination of whether there was an intent to contract within the realm of fact finding. The consideration for such an independent contract between Brown and Cale can easily be found in the detriment to Brown in continuing the work and the benefit to Cale in having it done (1 Corbin, Contracts, §§ 122, 124). The Appellate Division found that Brown and Cale had in fact made a direct contract by the terms of which Brown would be bound to continue to perform the electrical installations which remained undone and Cale would be bound to pay Brown all
Accordingly, the order should be affirmed.
Chief Judge Breitel and Judges Jasen, Gabrielli, Jones, Wachtler and Cooke concur.
Order affirmed, with costs.
